Skip to content
Residential / Group Housing · 1 buildingRERA P52000007221

Vankvanis Ela

Deedo IDDP-RAI-06SG

MahaRERA shows it completed; 5 listings and orders with MahaRERA on record.

Ulawe, Raigarh 410206 · by Suresh Vankvani

DeliveryCompletedAs MahaRERA showsRegulatory5 listings and ordersLatest: complaint

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 17 Aug 2017, completion promised 31 Mar 2018.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory record5

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000007221
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200000722117 Aug 201731 Mar 2018—Suresh VankvaniProject page
Documents60

29 documents held by Deedo, 31 filings listed on MahaRERA's project page

Title report

Encumbrance details

Form 1 (2)

Form 2

Form B

Allotment letter (2)

Show all 60 documentsShow fewer documents

Registration certificate

Commencement certificate

Form 5

Form 4

Occupancy / completion certificate

  • Occupancy / completion certificate21 Aug 2022ViewSource

Other (11)

Layout plan (4)

Building plan

Document library

  • Details of encumbrancesNo encumberance declaration.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)CCcopyELA.pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ArchitectCertELA.pdf · uploaded 31 Jul 2017View
  • Copy of the legal title reportTitle CertificateELA.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)01.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)02.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)03.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)04.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)EngineerCertELA.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM BAffidavitcumDecl of R S Enterprise.pdf · uploaded 1 Aug 2017View
  • Proforma of Allotment letterAllotment letter ELA.pdf · uploaded 1 Aug 2017View
  • Proforma of Allotment letterAgmtRERAVankwanis Ela Plot 52 Sec18 Ulwe.pdf · uploaded 1 Aug 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch table A.pdf · uploaded 30 Oct 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch table A.pdf · uploaded 30 Oct 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch table A.pdf · uploaded 30 Oct 2017View
  • Commencement Certificates / NA Order for plotted developmentRSE RERA Document C C CopyELA.pdf · uploaded 22 Mar 2018View
  • Certificates of Architect (Form 4)Form 4.pdf · uploaded 9 Jun 2018View
  • Certificates of CA (Form 5)Form 5.pdf · uploaded 2 Mar 2019View
  • Certificates of Architect (Form 4)FORM 4.pdf · uploaded 2 Mar 2019View
  • OtherOccupancy Completion Certificate.pdf · uploaded 2 Mar 2019View
  • Status of Formation of Legal Entity (Society/Co Op etc.)Vankvani's Ela Society Registration Certificate.pdf · uploaded 21 Aug 2022View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate.pdf · uploaded 21 Aug 2022View

Promoter documents

  • Legal Title reportTitle CertificateELA.pdf · uploaded 31 Jul 2017View
  • Declaration Form BAffidavitcumDecl of R S Enterprise.pdf · uploaded 1 Aug 2017View

Technical documents

  • Layout Approval02.pdfView
  • Layout Approval04.pdfView
  • Layout Approval03.pdfView
  • Layout Approval01.pdfView
  • Building Plan ApprovalCCcopyELA.pdfView

Other legal documents

  • OtherOccupancy Completion Certificate.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment letter ELA.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot 52 52A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Address
Plot 52 52APIN 410206
Village
Ulawe, Panvel taluka
Land area for this project
650 sq m (6,993 sq ft)
Permissible built-up area
889 sq m (9,573 sq ft)
Sanctioned built-up area
889 sq m (9,573 sq ft)
Designated bank account
The Cosmos Co Operative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

Plot 52 52A

Land as published on MahaRERA's project page

Plot 52 52A

Boundaries

North
Plot 51
South
Plot 53
East
Plot 54
West
11 meters wide road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking3 parking spaces

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00002

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Vankvanis Ela

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure85%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & Footpathsin progress30%
  • Water Supplyin later scope work0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)in later scope work0%
  • Storm Water Drainsin later scope work0%
  • Landscaping & Tree Plantingin later scope work0%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingin later scope work0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsin later scope work0%
  • Electrical meter room, sub-station, receiving stationin progress20%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingVisitors parking100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAmit Patil—
EngineerBS Sukhthankar—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Ulawe

All 697 projects in Ulawe · Compare Vankvanis Ela with another project

Data through12 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Report a problemMethodology