Others · 1 building · 183 unitsRERA P52000034268

Nms One 8 One

Deedo IDDP-RAI-A72A

Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 39% of its units are booked.

Ulawe, Raigarh 410206 · by Nms Enterprises

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales39% booked72 of 183 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 30 Mar 2022, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000034268
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200003426830 Mar 202231 Dec 202830 Apr 2029Nms EnterprisesProject page
Documents179

1 document held by Deedo, 178 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card.pdf · uploaded 24 Mar 2022Source

Legal

  • Legal Title reportCopy of Legal Title Report.pdf · uploaded 24 Mar 2022Source
  • Declaration Form BDeclaration in FORM B.pdf · uploaded 24 Mar 2022Source
  • OthersCompletion Certificate.pdf · uploaded 11 Nov 2025Source

Migrated

  • 1 PAN CardPAN Card.pdf · uploaded 24 Mar 2022Source
  • 1 Copy of the legal title reportCopy of Legal Title Report.pdf · uploaded 24 Mar 2022Source
  • 1 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 24 Mar 2022Source
Show all 179 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)1 of 9.pdf · uploaded 24 Mar 2022Source
  • 2 Copy of Layout Approval (in case of layout)2 of 9.pdf · uploaded 24 Mar 2022Source
  • 3 Copy of Layout Approval (in case of layout)3 of 9.pdf · uploaded 24 Mar 2022Source
  • 4 Copy of Layout Approval (in case of layout)4 of 9.pdf · uploaded 24 Mar 2022Source
  • 5 Copy of Layout Approval (in case of layout)5 of 9.pdf · uploaded 24 Mar 2022Source
  • 6 Copy of Layout Approval (in case of layout)6 of 9.pdf · uploaded 24 Mar 2022Source
  • 7 Copy of Layout Approval (in case of layout)7 of 9.pdf · uploaded 24 Mar 2022Source
  • 8 Copy of Layout Approval (in case of layout)8 of 9.pdf · uploaded 24 Mar 2022Source
  • 9 Copy of Layout Approval (in case of layout)9 of 9.pdf · uploaded 24 Mar 2022Source
  • 1 Building Plan Approval / NA Order for plotted development1 of 9.pdf · uploaded 24 Mar 2022Source
  • 2 Building Plan Approval / NA Order for plotted development2 of 9.pdf · uploaded 24 Mar 2022Source
  • 3 Building Plan Approval / NA Order for plotted development3 of 9.pdf · uploaded 24 Mar 2022Source
  • 4 Building Plan Approval / NA Order for plotted development4 of 9.pdf · uploaded 24 Mar 2022Source
  • 5 Building Plan Approval / NA Order for plotted development5 of 9.pdf · uploaded 24 Mar 2022Source
  • 6 Building Plan Approval / NA Order for plotted development6 of 9.pdf · uploaded 24 Mar 2022Source
  • 7 Building Plan Approval / NA Order for plotted development7 of 9.pdf · uploaded 24 Mar 2022Source
  • 8 Building Plan Approval / NA Order for plotted development8 of 9.pdf · uploaded 24 Mar 2022Source
  • 9 Building Plan Approval / NA Order for plotted development9 of 9.pdf · uploaded 24 Mar 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificates.pdf · uploaded 24 Mar 2022Source
  • 1 Declaration about Commencement CertificateDeclaration about Commencement Certificat.pdf · uploaded 24 Mar 2022Source
  • 1 Declaration in FORM BDeclaration in FORM B.pdf · uploaded 24 Mar 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect’s Certificate of Percentage of Completion of Work (Form 1)_compressed.pdf · uploaded 24 Mar 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer’s Certificate (Form 2).pdf · uploaded 24 Mar 2022Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 24 Mar 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form 3.pdf · uploaded 24 Mar 2022Source
  • 1 Proforma of Allotment letterProforma of The Allotment Letter.pdf · uploaded 24 Mar 2022Source
  • 2 Proforma of Allotment letterDRAFT AGREEMENT FOR SALE.pdf · uploaded 24 Mar 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 11 Feb 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 11 Feb 2023Source
  • 1 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 14 Feb 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration of Separate bank.pdf · uploaded 14 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form-2A(21-22).pdf · uploaded 17 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form5.pdf · uploaded 18 Feb 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 5 Oct 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)NMS ONE 8 ONE.pdf · uploaded 5 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 (30-09-2023).pdf · uploaded 24 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FROM 5 NMS(181).pdf · uploaded 28 Nov 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 .pdf · uploaded 20 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 20 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 with sign.pdf · uploaded 23 Jan 2024Source
  • 2 Disclosure of sold/ booked inventoryNMS ONE 8 ONE-INVENTORY SOLD LETTER.pdf · uploaded 2 Feb 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 12 Apr 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)NMS 181.pdf · uploaded 12 Apr 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_signed_11zon.pdf · uploaded 23 Apr 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)NMS ONE 8 ONE _ ARCHITECT'S CERTIFICATE FORM 1.pdf · uploaded 13 Aug 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)NMS ONE 8 ONE.pdf · uploaded 13 Aug 2024Source
  • 2 Copy of Layout Approval (in case of layout)ACC DWG-2.pdf · uploaded 7 Oct 2024Source
  • 3 Copy of Layout Approval (in case of layout)ACC DWG-3.pdf · uploaded 7 Oct 2024Source
  • 4 Copy of Layout Approval (in case of layout)ACC DWG-4.pdf · uploaded 7 Oct 2024Source
  • 5 Copy of Layout Approval (in case of layout)ACC DWG-5.pdf · uploaded 7 Oct 2024Source
  • 6 Copy of Layout Approval (in case of layout)ACC DWG-6_.pdf · uploaded 7 Oct 2024Source
  • 7 Copy of Layout Approval (in case of layout)ACC DWG-7.pdf · uploaded 7 Oct 2024Source
  • 8 Copy of Layout Approval (in case of layout)ACC DWG-8.pdf · uploaded 7 Oct 2024Source
  • 9 Copy of Layout Approval (in case of layout)ACC DWG-9.pdf · uploaded 7 Oct 2024Source
  • 1 Copy of Layout Approval (in case of layout)drawing.pdf · uploaded 7 Oct 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 sign.pdf · uploaded 7 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_signed.pdf · uploaded 7 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_.pdf · uploaded 7 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 with sign_.pdf · uploaded 7 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 sign.pdf · uploaded 7 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_.pdf · uploaded 7 Oct 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 sign.pdf · uploaded 7 Oct 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC COPY.pdf · uploaded 7 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentACC DWG-10.pdf · uploaded 7 Oct 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentACC DWG-11.pdf · uploaded 7 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryInventory sold letter of Plot-181.pdf · uploaded 7 Oct 2024Source
  • 1 Declaration about Commencement CertificateDeclaration Commecement Certificate.pdf · uploaded 7 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form2A.pdf · uploaded 7 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2A.pdf · uploaded 7 Oct 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_.pdf · uploaded 21 Oct 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_.pdf · uploaded 21 Oct 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_.pdf · uploaded 21 Oct 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_.pdf · uploaded 21 Oct 2024Source
  • 3 Disclosure of sold/ booked inventoryInventory Sold Letter.pdf · uploaded 21 Oct 2024Source
  • 4 Disclosure of sold/ booked inventoryInventory Sold Letter.pdf · uploaded 21 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryInventory Sold Letter.pdf · uploaded 21 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3_.pdf · uploaded 22 Oct 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3_.pdf · uploaded 22 Oct 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmenthightlight plan 1.pdf · uploaded 5 Nov 2024Source
  • 2 Declaration about Commencement CertificateDeclaration Commecement Certificate.pdf · uploaded 5 Nov 2024Source
  • 1 Other – TechnicalNavi Mumbai pdf CC Granted Copy.pdf · uploaded 5 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Final FORM 5.pdf · uploaded 8 Nov 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 13 Nov 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 13 Nov 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 13 Nov 2024Source
  • 5 Disclosure of sold/ booked inventoryInventory Sold Letter.pdf · uploaded 13 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Final Form 1.pdf · uploaded 12 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 12 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final Form 2.pdf · uploaded 12 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final FORM 3.pdf · uploaded 19 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final FORM 2_.pdf · uploaded 19 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 23 Apr 2025Source
  • Form 1FORM 1_.pdf · uploaded 28 May 2025Source
  • Form 1FORM 1_.pdf · uploaded 28 May 2025Source
  • Form 2FORM 2_.pdf · uploaded 28 May 2025Source
  • Form 2FORM 2_.pdf · uploaded 28 May 2025Source
  • Form 3FInal Form 3.pdf · uploaded 28 May 2025Source
  • Form 3FInal Form 3.pdf · uploaded 28 May 2025Source
  • Disclosure of Sold and Booked InventoryInventory Sold Letter.pdf · uploaded 28 May 2025Source
  • Disclosure of Sold and Booked InventoryInventory Sold Letter.pdf · uploaded 28 May 2025Source
  • Withdrawal Update Form 1final form 1.pdf · uploaded 31 Jul 2025Source
  • Withdrawal Update Form 2final form 2.pdf · uploaded 31 Jul 2025Source
  • Withdrawal Update Form 3final form 3.pdf · uploaded 31 Jul 2025Source
  • Withdrawal Update Form 1final form 1.pdf · uploaded 5 Aug 2025Source
  • Withdrawal Update Form 2final form 2.pdf · uploaded 5 Aug 2025Source
  • Withdrawal Update Form 3final form 3.pdf · uploaded 5 Aug 2025Source
  • Withdrawal Update Form 1final form 1.pdf · uploaded 19 Aug 2025Source
  • Withdrawal Update Form 2final form 2.pdf · uploaded 19 Aug 2025Source
  • Withdrawal Update Form 3final form 3.pdf · uploaded 19 Aug 2025Source
  • Withdrawal Update Form 1FORM 1 Q2 25-26.pdf · uploaded 13 Nov 2025Source
  • Withdrawal Update Form 2FORM2 Q2 25-26.pdf · uploaded 13 Nov 2025Source
  • Withdrawal Update Form 3FORM3 Q2 25-26.pdf · uploaded 13 Nov 2025Source
  • Form 5 (FY 2024-2025)Form 5 (NMS Enterprises) 181 Sign.pdf · uploaded 13 Jan 2026Source
  • Withdrawal Update Form 1FORM1 Q3 25-26.pdf · uploaded 13 Feb 2026Source
  • Withdrawal Update Form 2FORM2 Q3 25-26.pdf · uploaded 13 Feb 2026Source
  • Withdrawal Update Form 3Form3 Q3 25-26..pdf · uploaded 13 Feb 2026Source
  • Withdrawal Update Form 1FORM 1 Q4 25-26.pdf · uploaded 29 Apr 2026Source
  • Withdrawal Update Form 2FORM 2 Q4 25-26.pdf · uploaded 29 Apr 2026Source
  • Withdrawal Update Form 3FORM 3 Q4 25-26.pdf · uploaded 29 Apr 2026Source
  • Withdrawal Update Form 1Form 1 Q1 26-27.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 2Form 2 Q1 26-27.pdf · uploaded 21 Jul 2026Source
  • Withdrawal Update Form 3Form 3 Q1 26-27.pdf · uploaded 21 Jul 2026Source

Technical

  • Document1 of 9.pdf · uploaded 24 Mar 2022Source
  • Document2 of 9.pdf · uploaded 24 Mar 2022Source
  • Document3 of 9.pdf · uploaded 24 Mar 2022Source
  • Document4 of 9.pdf · uploaded 24 Mar 2022Source
  • Document5 of 9.pdf · uploaded 24 Mar 2022Source
  • Document6 of 9.pdf · uploaded 24 Mar 2022Source
  • Document7 of 9.pdf · uploaded 24 Mar 2022Source
  • Document8 of 9.pdf · uploaded 24 Mar 2022Source
  • Document9 of 9.pdf · uploaded 24 Mar 2022Source
  • Document1 of 9.pdf · uploaded 24 Mar 2022Source
  • Document2 of 9.pdf · uploaded 24 Mar 2022Source
  • Document3 of 9.pdf · uploaded 24 Mar 2022Source
  • Document4 of 9.pdf · uploaded 24 Mar 2022Source
  • Document5 of 9.pdf · uploaded 24 Mar 2022Source
  • Document6 of 9.pdf · uploaded 24 Mar 2022Source
  • Document7 of 9.pdf · uploaded 24 Mar 2022Source
  • Document8 of 9.pdf · uploaded 24 Mar 2022Source
  • Document9 of 9.pdf · uploaded 24 Mar 2022Source
  • Documentdrawing.pdf · uploaded 7 Oct 2024Source
  • DocumentACC DWG-2.pdf · uploaded 7 Oct 2024Source
  • DocumentACC DWG-3.pdf · uploaded 7 Oct 2024Source
  • DocumentACC DWG-4.pdf · uploaded 7 Oct 2024Source
  • DocumentACC DWG-5.pdf · uploaded 7 Oct 2024Source
  • DocumentACC DWG-6_.pdf · uploaded 7 Oct 2024Source
  • DocumentACC DWG-7.pdf · uploaded 7 Oct 2024Source
  • DocumentACC DWG-8.pdf · uploaded 7 Oct 2024Source
  • DocumentACC DWG-9.pdf · uploaded 7 Oct 2024Source
  • DocumentACC DWG-10.pdf · uploaded 7 Oct 2024Source
  • DocumentACC DWG-11.pdf · uploaded 7 Oct 2024Source
  • Documenthightlight plan 1.pdf · uploaded 5 Nov 2024Source
  • Other – TechnicalNavi Mumbai pdf CC Granted Copy.pdf · uploaded 5 Nov 2024Source

Technical (Architect)

  • DocumentFORM-1_.pdf · uploaded 7 Oct 2024Source
  • DocumentFORM 1_signed.pdf · uploaded 7 Oct 2024Source
  • DocumentForm-1 sign.pdf · uploaded 7 Oct 2024Source
  • DocumentFORM 1_.pdf · uploaded 21 Oct 2024Source
  • DocumentFORM 1_.pdf · uploaded 21 Oct 2024Source
  • DocumentFORM 1.pdf · uploaded 13 Nov 2024Source
  • DocumentFinal Form 1.pdf · uploaded 12 Feb 2025Source
  • DocumentFORM 1.pdf · uploaded 23 Apr 2025Source
  • DocumentForm 1 Q1 26-27.pdf · uploaded 21 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2_.pdf · uploaded 7 Oct 2024Source
  • DocumentFORM 2 sign.pdf · uploaded 7 Oct 2024Source
  • DocumentFORM 2 sign.pdf · uploaded 7 Oct 2024Source
  • DocumentFORM 2_.pdf · uploaded 21 Oct 2024Source
  • DocumentFORM 2_.pdf · uploaded 21 Oct 2024Source
  • DocumentFORM 2.pdf · uploaded 13 Nov 2024Source
  • DocumentFinal Form 2.pdf · uploaded 12 Feb 2025Source
  • DocumentFinal FORM 2_.pdf · uploaded 19 Apr 2025Source
  • DocumentForm 2 Q1 26-27.pdf · uploaded 21 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 181 at Panvel

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
—183 units in all
Address
181, Plot No-181, Sector-19, UlwePIN 410206
Village
Ulawe, Panvel taluka
Land area for this project
4,176 sq m (44,953 sq ft)
Permissible built-up area
18,234 sq m (1,96,265 sq ft)
Sanctioned built-up area
18,234 sq m (1,96,265 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
109
Developed in phases
No

Survey, CTS, gat or plot numbers

181 at Panvel

Land as published on MahaRERA's project page

181

Boundaries

North
Plot No-180
South
Plot No-165
East
Plot No 166 167 168 169 170
West
30mtr Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking183 units

183 units registered

— · 183 units
TypeCarpet areaUnits
——183

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Other projects in Ulawe

All 697 projects in Ulawe · Compare Nms One 8 One with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology