Skip to content
Residential / Group Housing · 1 building · 24 unitsRERA P52000020562

Guru Ansh

Deedo IDDP-RAI-249C

MahaRERA shows it completed; no MahaRERA orders on record; 54% of its units are booked.

Ulawe, Raigarh 410206 · by Gurukrupa Infra Developers · 67% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales54% booked13 of 24 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 22 Apr 2019, completion promised 30 Mar 2022.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000020562
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200002056222 Apr 201930 Mar 202230 Mar 2022Gurukrupa Infra DevelopersProject page
Documents19

1 document held by Deedo, 18 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Legal Title reportSearch and Title Report.pdf · uploaded 12 Apr 2019Source
  • Declaration Form BForm-B.pdf · uploaded 12 Apr 2019Source
  • Other54-OC.pdf · uploaded 19 Apr 2021Source

Migrated

  • 1 Copy of the legal title reportSearch and Title Report.pdf · uploaded 12 Apr 2019Source
  • 1 Details of encumbrancesEncumbrance.pdf · uploaded 12 Apr 2019Source
  • 1 Copy of Layout Approval (in case of layout)layout plan.pdf · uploaded 12 Apr 2019Source
  • 1 Building Plan Approval (IOD)building approval plan.pdf · uploaded 12 Apr 2019Source
Show all 19 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 12 Apr 2019Source
  • 1 Declaration in FORM BForm-B.pdf · uploaded 12 Apr 2019Source
  • 1 Certificates of CA (Form 3)FORM-3.pdf · uploaded 12 Apr 2019Source
  • 1 Proforma of Allotment letterDraft agg and allotment letter.pdf · uploaded 12 Apr 2019Source
  • 1 Other54-OC.pdf · uploaded 19 Apr 2021Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 20 Apr 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development54-OC.pdf · uploaded 21 Jun 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)guru 54 20.pdf · uploaded 24 Jun 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)guru 54 21.pdf · uploaded 24 Jun 2021Source

Technical

  • Documentbuilding approval plan.pdf · uploaded 12 Apr 2019Source
  • Documentlayout plan.pdf · uploaded 12 Apr 2019Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO 54, SECTOR 17 ULWE

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 1RK WITH TERRACE, Shop24 units in all
Address
Plot No 54, Sector 17 Ulwe, Plot No 54, Sector 17, UlwePIN 410206
Village
Ulawe, Panvel taluka
Land area for this project
350 sq m (3,765 sq ft)
Permissible built-up area
523 sq m (5,629 sq ft)
Sanctioned built-up area
523 sq m (5,629 sq ft)
Designated bank account
43
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO 54SECTOR 17 ULWE

Land as published on MahaRERA's project page

PLOT NO 54, SECTOR 17 ULWE

Boundaries

North
Plot No 55
South
Plot No 53
East
11 Mtr Wide Road
West
Plot No 40

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking24 units

13 of 24 units booked (54%), as the promoter reported to MahaRERA

1BHK · 10 units1RK · 8 units1RK WITH TERRACE · 2 unitsShop · 4 units
TypeCarpet areaUnitsBooked
1BHK22.43 sq m · 241 sq ft10
1BHK25.27 sq m · 272 sq ft65
1BHK27.37 sq m · 295 sq ft32
1RK15.63 sq m · 168 sq ft32
1RK17.07 sq m · 184 sq ft30
1RK17.91 sq m · 193 sq ft11
1RK19.45 sq m · 209 sq ft11
1RK WITH TERRACE18.03 sq m · 194 sq ft20
Show all 11 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop12.86 sq m · 138 sq ft20
Shop13.61 sq m · 146 sq ft11
Shop13.63 sq m · 147 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAtul Patel Architect—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Ulawe

All 697 projects in Ulawe · Compare Guru Ansh with another project

Data through12 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology