Others · 1 building · 13 unitsRERA P52000052685

Galaxy Aura

Deedo IDDP-RAI-1Y26

Completion was pushed back 4 months, to Jul 2027; no MahaRERA orders on record; 46% of its units are booked.

Ulawe, Raigarh 410206 · by Ramesh Goma Gharat

DeliveryExtended 4 moPromised Mar 2027 · now due Jul 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales46% booked6 of 13 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2027

  • This projectRegistered 20 Sep 2023, completion promised 31 Mar 2027, revised to 31 Jul 2027.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000052685
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200005268520 Sep 202331 Mar 202731 Jul 2027Ramesh Goma GharatProject page
Documents71

1 document held by Deedo, 70 filings listed on MahaRERA's project page

Extension certificate

Finance

  • PAN CardRamesh Gharat PAN Card.pdf · uploaded 20 Jun 2023Source

Legal

  • Declaration Form BFORM B.pdf · uploaded 4 Jul 2023Source
  • Legal Title reportsearch and title.pdf · uploaded 28 Jul 2023Source

Migrated

  • 1 PAN CardRamesh Gharat PAN Card.pdf · uploaded 20 Jun 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 20 Jun 2023Source
  • 1 Declaration about Commencement Certificatedeclaration about cc aura.pdf · uploaded 20 Jun 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 20 Jun 2023Source
Show all 71 documentsShow fewer documents

Migrated

  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 20 Jun 2023Source
  • 1 CERSAI detailscersai.pdf · uploaded 20 Jun 2023Source
  • 1 Proforma of Allotment letterallotment letter.pdf · uploaded 20 Jun 2023Source
  • 1 Proforma of Agreement for saleAgreement for sale.pdf · uploaded 20 Jun 2023Source
  • 1 Deviation Report with respect to Allotment letterno deviation from allotment letter.pdf · uploaded 20 Jun 2023Source
  • 1 Deviation Report with respect to model copy of Agreementno deviation from agreement for sale.pdf · uploaded 20 Jun 2023Source
  • 1 a Details of encumbrances concerned to Financeencumbrances related to finance.pdf · uploaded 27 Jun 2023Source
  • 2 a Details of encumbrances concerned to Financeencumbrances related to legal.pdf · uploaded 27 Jun 2023Source
  • 1 b Details of encumbrances concerned to Legalencumbrances related to finance.pdf · uploaded 27 Jun 2023Source
  • 2 b Details of encumbrances concerned to Legalencumbrances related to legal.pdf · uploaded 27 Jun 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentplan.pdf · uploaded 27 Jun 2023Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 4 Jul 2023Source
  • 1 Copy of Layout Approval (in case of layout)1 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 10 Jul 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 20 Jul 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameAura Separate Bank details.pdf · uploaded 20 Jul 2023Source
  • 1 Copy of the legal title reportsearch and title.pdf · uploaded 28 Jul 2023Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsdisclosure of interest (1).pdf · uploaded 28 Jul 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Mar 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Mar 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Mar 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Mar 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 14 Mar 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 14 Mar 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 14 Mar 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 14 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 14 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Mar 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Mar 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 14 Mar 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Mar 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold_ booked.pdf · uploaded 14 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 23-24.pdf · uploaded 14 Mar 2025Source
  • Form 1FORM 1 - JUNE 2025 sign.pdf · uploaded 16 Mar 2026Source
  • Form 2Form 2 30-06-2025 sign.pdf · uploaded 16 Mar 2026Source
  • Form 3Form 3 30-06-2025 sign.pdf · uploaded 16 Mar 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of sold_booked 30-6-2025.pdf · uploaded 16 Mar 2026Source
  • Form 1FORM 1 - SEP 2025 sign.pdf · uploaded 16 Mar 2026Source
  • Form 2Form 2 30-09-2025 sign.pdf · uploaded 16 Mar 2026Source
  • Form 3Form 3 30-09-2025 sign.pdf · uploaded 16 Mar 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of sold_booked 30-9-2025.pdf · uploaded 16 Mar 2026Source
  • Form 1FORM 1 - DEC 2025 sign.pdf · uploaded 16 Mar 2026Source
  • Form 2Form 2 31-12-2025 sign.pdf · uploaded 16 Mar 2026Source
  • Form 3Form 3 31-12-2025 sign.pdf · uploaded 16 Mar 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of sold_booked 31-12-2025.pdf · uploaded 16 Mar 2026Source
  • Withdrawal Update Form 1FORM 1 - DEC 2025 sign.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 2Form 2 31-12-2025 sign.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 3Form 3 31-12-2025 sign.pdf · uploaded 23 Jun 2026Source

Technical

  • Documentplan.pdf · uploaded 27 Jun 2023Source
  • Document1 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 10 Jul 2023Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 14 Mar 2025Source
  • DocumentForm 1.pdf · uploaded 14 Mar 2025Source
  • DocumentForm 1.pdf · uploaded 14 Mar 2025Source
  • DocumentForm 1.pdf · uploaded 14 Mar 2025Source
  • DocumentForm 1.pdf · uploaded 14 Mar 2025Source
  • DocumentFORM 1 - DEC 2025 sign.pdf · uploaded 23 Jun 2026Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 14 Mar 2025Source
  • DocumentForm 2.pdf · uploaded 14 Mar 2025Source
  • Documentform 2.pdf · uploaded 14 Mar 2025Source
  • DocumentForm 2.pdf · uploaded 14 Mar 2025Source
  • DocumentForm 2.pdf · uploaded 14 Mar 2025Source
  • DocumentForm 2 31-12-2025 sign.pdf · uploaded 23 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 198

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 5BHK & more13 units in all
Address
198, Sector 24, PushpakPIN 410206
Village
Ulawe, Panvel taluka
Land area for this project
230 sq m (2,474 sq ft)
Permissible built-up area
550 sq m (5,921 sq ft)
Sanctioned built-up area
550 sq m (5,921 sq ft)
Designated bank account
148
Developed in phases
No

Survey, CTS, gat or plot numbers

198

Land as published on MahaRERA's project page

198

Boundaries

North
Plot No 209 And 210
South
9 M Wide Road
East
Plot No 199
West
Plot No 197

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking13 units

6 of 13 units booked (46%), as the promoter reported to MahaRERA

1BHK · 6 units1RK · 6 units5BHK & more · 1 unit
TypeCarpet areaUnitsBooked
1BHK30.27 sq m · 326 sq ft42
1BHK30.49 sq m · 328 sq ft22
1RK20.62 sq m · 222 sq ft20
1RK26.44 sq m · 285 sq ft42
5BHK & more108.6 sq m · 1,169 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAnil H Sakaria—
Chartered accountantAnjali Ithkulla—
EngineerHemant Sharad Shinde—
EngineerStrucon Consulting Engineers—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Ulawe

All 697 projects in Ulawe · Compare Galaxy Aura with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology