Deedo IDDP-RAI-100WIts promised completion date, Mar 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Ulawe, Raigarh 410206 · by Manoj Kumar Singh · 25% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Its promised completion date, Mar 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 12 Dec 2019, completion promised 30 Mar 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000023357
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000023357 | 12 Dec 2019 | 30 Mar 2024 | 30 Mar 2024 | Manoj Kumar Singh | Project page |
Documents23
1 document held by Deedo, 22 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card.pdf · uploaded 21 Nov 2019Source
Legal
Migrated
- 1 Copy of the legal title reportTITLE CERETIFICATE.pdf · uploaded 12 Aug 2019Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)ca.pdf · uploaded 12 Aug 2019Source
- 1 Copy of Layout Approval (in case of layout)MYSCAN_20191022_0002 (2).PDF · uploaded 31 Oct 2019Source
- 1 Building Plan Approval / NA Order for plotted developmentMYSCAN_20191022_0002 (2).PDF · uploaded 31 Oct 2019Source
Show all 23 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentcc 452.pdf · uploaded 31 Oct 2019Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect.pdf · uploaded 2 Nov 2019Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engeener.pdf · uploaded 2 Nov 2019Source
- 1 Proforma of Allotment letterastha.pdf · uploaded 3 Nov 2019Source
- 1 PAN Cardpan card.pdf · uploaded 21 Nov 2019Source
- 2 Commencement Certificates / NA Order for plotted developmentcc.pdf · uploaded 21 Nov 2019Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)ca.pdf · uploaded 21 Nov 2019Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)no.pdf · uploaded 21 Nov 2019Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)payment shedule.pdf · uploaded 25 Nov 2019Source
- 1 Details of encumbrancesencumbrance.pdf · uploaded 9 Dec 2019Source
- 1 Declaration in FORM Bform b.pdf · uploaded 9 Dec 2019Source
Technical
Technical (Architect)
- Documentpayment shedule.pdf · uploaded 25 Nov 2019Source
Technical (Engineer)
- Documentengeener.pdf · uploaded 2 Nov 2019Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot No 452
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1RK13 units in all
- Address
- Plot No 452, sector 24, ulawe nodePIN 410206
- Village
- Ulawe, Panvel taluka
- Land area for this project
- 210 sq m (2,260 sq ft)
- Permissible built-up area
- 493 sq m (5,305 sq ft)
- Sanctioned built-up area
- 491 sq m (5,289 sq ft)
- Recreational open space
- 210 sq m (2,259 sq ft)
- Designated bank account
- 148
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot No 452
Boundaries
- North
- 11 mtr wide road
- South
- plot no 451
- East
- Plot no 478
- West
- 9 mtr wide road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking13 units
0 of 13 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1RK | 14.88 sq m · 160 sq ft | 1 | 0 |
| 1RK | 16.96 sq m · 183 sq ft | 1 | 0 |
| 1RK | 22.38 sq m · 241 sq ft | 3 | 0 |
| 1RK | 22.79 sq m · 245 sq ft | 3 | 0 |
| 1RK | 22.94 sq m · 247 sq ft | 3 | 0 |
| 1RK | 22.96 sq m · 247 sq ft | 1 | 0 |
| 1RK | 24.65 sq m · 265 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sheetal Architects | — |
| Chartered accountant | Nc Shah & Co | — |
| Engineer | B S Sukthankar & Associates | — |
| Other | Sanehi | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Ulawe
- Vertis SkyeRERA PM1270002602722
- Shivesh MahavirRERA PM1270002602135
- Reddy's Gurukrupa HeightsRERA PR1270002601976
- Wind CastleRERA PR1270002601802
- YashodhamRERA PM1270002601243
- Varniraj VivantRERA PM1270002601106
- Progressive AuraRERA PM1270002601038
- North OneRERA PM1270002600964
All 697 projects in Ulawe · Compare Aman Astha with another project