4 projects under 4 MahaRERA registrations, registered 2019–2026. 25% have a completion date extended beyond the one promised.

Locality
4RERA projects
4Registrations
1Completion still due3 past their completion date
12 monthsMedian extension beyond promised date25% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20191
20200
20211
20220
20231
20240
20250
20261

Projects in Shrivardhan ®

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
AvenueSSilver Homes EnterprisesPC127000260057929 May 202629 May 2029—Not yet due0
Sagar ViharCore DevelopersP5200005242725 Aug 202331 Mar 202531 Mar 2026Extended 12 mo0
Shams ComplexSalman Khalilurrahman MullaP5200003144023 Oct 20213 Sep 2023—Promised date passed0
Kundan Darshan ApartmentAmarkumar Javerchand JainP5200001944230 Jan 201930 Jun 2023—Promised date passed0

Other localities in Shrivardhan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Amarkumar Javerchand Jain1 project
  2. Core Developers1 project
  3. Salman Khalilurrahman Mulla1 project
  4. Silver Homes Enterprises1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology