Its promised completion date, Mar 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Pen Rural, Raigarh 402107 · by Tulsi Krupa Developers

Delivery1 yr 8 mo past duePromised Mar 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 18 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Mar 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 21 Apr 2023, completion promised 31 Mar 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000050595
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200005059521 Apr 202331 Mar 202531 Mar 2025Tulsi Krupa DevelopersProject page
Documents41

2 documents held by Deedo, 39 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN Cardpancard.pdf · uploaded 20 Feb 2023Source

Legal

  • Legal Title reportAdobe Scan 07 Apr 2023 (2).pdf · uploaded 7 Apr 2023Source
  • Declaration Form BDocScanner 18 Apr 2023 4-38 pm_compressed.pdf · uploaded 18 Apr 2023Source

Migrated

  • 1 PAN Cardpancard.pdf · uploaded 20 Feb 2023Source
  • 1 Building Plan Approval / NA Order for plotted development1 Copy of Layout Approval (in case of layout).pdf · uploaded 20 Feb 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentREV CC LETTER.pdf · uploaded 20 Feb 2023Source
Show all 41 documentsShow fewer documents

Migrated

  • 1 Proforma of Agreement for saleMODEL DRAFT RERA AGREEMENT.pdf · uploaded 21 Feb 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)RCC certificate .pdf · uploaded 24 Feb 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA FORM 3_compressed.pdf · uploaded 8 Mar 2023Source
  • 1 Copy of Layout Approval (in case of layout)FINAL LAYOUT.pdf · uploaded 14 Mar 2023Source
  • 1 a Details of encumbrances concerned to Finance1 a Details of encumbrances concerned to Finance (1).pdf · uploaded 16 Mar 2023Source
  • 1 b Details of encumbrances concerned to Legal1 a Details of encumbrances concerned to Finance (1).pdf · uploaded 16 Mar 2023Source
  • 1 Declaration about Commencement Certificate1 Declaration about Commencement Certificate.pdf · uploaded 16 Mar 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 16 Mar 2023Source
  • 1 Disclosure of Interest in Other Real Estate Organizations1 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 16 Mar 2023Source
  • 1 Proforma of Allotment letter1 Proforma of Allotment letter.pdf · uploaded 16 Mar 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same.pdf · uploaded 16 Mar 2023Source
  • 1 Deviation Report with respect to Allotment letter1 Deviation Report with respect to Allotment letter.pdf · uploaded 16 Mar 2023Source
  • 1 Deviation Report with respect to model copy of Agreement1 Deviation Report with respect to model copy of Agreement.pdf · uploaded 16 Mar 2023Source
  • 1 CERSAI detailsFINAL CERSAI.pdf · uploaded 29 Mar 2023Source
  • 1 Copy of the legal title reportAdobe Scan 07 Apr 2023 (2).pdf · uploaded 7 Apr 2023Source
  • 1 Declaration in FORM BDocScanner 18 Apr 2023 4-38 pm_compressed.pdf · uploaded 18 Apr 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate Q1.pdf · uploaded 19 Jan 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Q2.pdf · uploaded 19 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Q1.pdf · uploaded 19 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Q2.pdf · uploaded 19 Jan 2024Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD UNSOLD INVENTORY .pdf · uploaded 19 Jan 2024View
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE Q1.pdf · uploaded 19 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE Q2.pdf · uploaded 19 Jan 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q3 Ar Certificate .pdf · uploaded 26 Apr 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q4 Ar Certificate .pdf · uploaded 26 Apr 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3 RCC ENG CERTIFICATE .pdf · uploaded 26 Apr 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4 RCC ENG CERTIFICATE .pdf · uploaded 26 Apr 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q3 CA CERTIFICATE _compressed.pdf · uploaded 26 Apr 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q4 CA CERTIFICATE _compressed.pdf · uploaded 26 Apr 2024Source

Technical

  • Document1 Copy of Layout Approval (in case of layout).pdf · uploaded 20 Feb 2023Source
  • DocumentFINAL LAYOUT.pdf · uploaded 14 Mar 2023Source

Technical (Architect)

  • DocumentQ4 Ar Certificate .pdf · uploaded 26 Apr 2024Source

Technical (Engineer)

  • DocumentQ4 RCC ENG CERTIFICATE .pdf · uploaded 26 Apr 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 109/4C PLOT NO. 1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK18 units in all
Address
109/4c Plot No. 1, Near Ashok Mahadik Marathi School, Devnagri Society, PenPIN 402107
Village
Pen Rural, Pen taluka
Land area for this project
351 sq m (3,779 sq ft)
Permissible built-up area
785 sq m (8,448 sq ft)
Sanctioned built-up area
785 sq m (8,448 sq ft)
Designated bank account
35
Developed in phases
No

Survey, CTS, gat or plot numbers

109/4C PLOT NO. 1

Land as published on MahaRERA's project page

109/4C PLOT NO. 1

Boundaries

North
Sadiccha Bungalow
South
Jagdamba Residency
East
Joshi Bungalow
West
Ashok Mahadik Marathi School

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking18 units

0 of 18 units booked (0%), as the promoter reported to MahaRERA

1BHK · 16 units1RK · 2 units
TypeCarpet areaUnitsBooked
1BHK34.02 sq m · 366 sq ft50
1BHK35.18 sq m · 379 sq ft50
1BHK36.04 sq m · 388 sq ft60
1RK24.29 sq m · 261 sq ft10
1RK26.06 sq m · 281 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNakoda Architects—
Chartered accountantV V Rane & Co—
EngineerManohar Patil & Associates—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Pen Rural

All 17 projects in Pen Rural · Compare Tulsi Bapdev Arcade with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology