Estella
Deedo IDDP-RAI-VCK3Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 0% of its units are booked.
New Panvel, Raigarh 410206 · by A-Space
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 10 Oct 2024, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000077550
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000077550 | 10 Oct 2024 | 31 Dec 2028 | 30 Apr 2029 | A-Space | Project page |
Documents173
1 document held by Deedo, 172 filings listed on MahaRERA's project page
Finance
Show all 173 documentsShow fewer documents
Legal
- Declaration Form BForm B- Promoter.pdf · uploaded 8 Jul 2024Source
- Declaration Form BForm B- Promoter.pdf · uploaded 8 Jul 2024Source
- Declaration Form BForm B- Promoter.pdf · uploaded 8 Jul 2024Source
- Legal Title reportShort Title_Estella_A-Space_11072024_11zon.pdf · uploaded 24 Jul 2024Source
- Legal Title reportShort Title_Estella_A-Space_11072024_11zon.pdf · uploaded 24 Jul 2024Source
- Legal Title reportShort Title_Estella_A-Space_11072024_11zon.pdf · uploaded 24 Jul 2024Source
Migrated
- 1 PAN CardA-Space_E-PAN_08072022 (1)_unlocked.pdf · uploaded 6 Jul 2024Source
- 1 a Details of encumbrances concerned to FinanceNo Encumbrance- Finance.pdf · uploaded 6 Jul 2024Source
- 2 a Details of encumbrances concerned to FinanceNo Encumbrance- Legal.pdf · uploaded 6 Jul 2024Source
- 1 Other – LegalA-Space Lease Deed.pdf · uploaded 6 Jul 2024Source
- 1 CERSAI detailsCersai Dec.pdf · uploaded 6 Jul 2024Source
- 1 b Details of encumbrances concerned to LegalNo Encumbrance- Finance.pdf · uploaded 6 Jul 2024Source
- 2 b Details of encumbrances concerned to LegalNo Encumbrance- Legal.pdf · uploaded 6 Jul 2024Source
- 1 PAN CardA-Space_E-PAN_08072022 (1)_unlocked.pdf · uploaded 6 Jul 2024Source
- 1 a Details of encumbrances concerned to FinanceNo Encumbrance- Finance.pdf · uploaded 6 Jul 2024Source
- 2 a Details of encumbrances concerned to FinanceNo Encumbrance- Legal.pdf · uploaded 6 Jul 2024Source
- 1 Other – LegalA-Space Lease Deed.pdf · uploaded 6 Jul 2024Source
- 1 CERSAI detailsCersai Dec.pdf · uploaded 6 Jul 2024Source
- 1 b Details of encumbrances concerned to LegalNo Encumbrance- Finance.pdf · uploaded 6 Jul 2024Source
- 2 b Details of encumbrances concerned to LegalNo Encumbrance- Legal.pdf · uploaded 6 Jul 2024Source
- 1 PAN CardA-Space_E-PAN_08072022 (1)_unlocked.pdf · uploaded 6 Jul 2024Source
- 1 a Details of encumbrances concerned to FinanceNo Encumbrance- Finance.pdf · uploaded 6 Jul 2024Source
- 2 a Details of encumbrances concerned to FinanceNo Encumbrance- Legal.pdf · uploaded 6 Jul 2024Source
- 1 Other – LegalA-Space Lease Deed.pdf · uploaded 6 Jul 2024Source
- 1 CERSAI detailsCersai Dec.pdf · uploaded 6 Jul 2024Source
- 1 b Details of encumbrances concerned to LegalNo Encumbrance- Finance.pdf · uploaded 6 Jul 2024Source
- 2 b Details of encumbrances concerned to LegalNo Encumbrance- Legal.pdf · uploaded 6 Jul 2024Source
- 1 Declaration in FORM BForm B- Promoter.pdf · uploaded 8 Jul 2024Source
- 1 Declaration in FORM BForm B- Promoter.pdf · uploaded 8 Jul 2024Source
- 1 Declaration in FORM BForm B- Promoter.pdf · uploaded 8 Jul 2024Source
- 1 Copy of the legal title reportShort Title_Estella_A-Space_11072024_11zon.pdf · uploaded 24 Jul 2024Source
- 1 Copy of the legal title reportShort Title_Estella_A-Space_11072024_11zon.pdf · uploaded 24 Jul 2024Source
- 1 Copy of the legal title reportShort Title_Estella_A-Space_11072024_11zon.pdf · uploaded 24 Jul 2024Source
- 1 Proforma of Allotment letterAllotment Letter_Deviation_Estella_A-Space_11072024.pdf · uploaded 2 Aug 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Scan2024-08-02_111829.pdf · uploaded 2 Aug 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A- Estella.pdf · uploaded 2 Aug 2024Source
- 1 Deviation Report with respect to Allotment letterDeviation Report of Al.pdf · uploaded 2 Aug 2024Source
- 1 Other – Technical1 Other – Technical (53).pdf · uploaded 2 Aug 2024Source
- 1 Deviation Report with respect to model copy of AgreementCCF_000082.pdf · uploaded 2 Aug 2024Source
- 1 Proforma of Agreement for saleAFS_Estella_A-Space_05082024.pdf · uploaded 2 Aug 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A- Estella.pdf · uploaded 2 Aug 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)A space.pdf · uploaded 2 Aug 2024Source
- 1 Disclosure for secured/unsecured finance availed for the project1 Disclosure for secured_unsecured finance availed for the project (11).pdf · uploaded 2 Aug 2024Source
- 1 Proforma of Allotment letterAllotment Letter_Deviation_Estella_A-Space_11072024.pdf · uploaded 2 Aug 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Scan2024-08-02_111829.pdf · uploaded 2 Aug 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A- Estella.pdf · uploaded 2 Aug 2024Source
- 1 Deviation Report with respect to Allotment letterDeviation Report of Al.pdf · uploaded 2 Aug 2024Source
- 1 Other – Technical1 Other – Technical (53).pdf · uploaded 2 Aug 2024Source
- 1 Deviation Report with respect to model copy of AgreementCCF_000082.pdf · uploaded 2 Aug 2024Source
- 1 Proforma of Agreement for saleAFS_Estella_A-Space_05082024.pdf · uploaded 2 Aug 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A- Estella.pdf · uploaded 2 Aug 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)A space.pdf · uploaded 2 Aug 2024Source
- 1 Disclosure for secured/unsecured finance availed for the project1 Disclosure for secured_unsecured finance availed for the project (11).pdf · uploaded 2 Aug 2024Source
- 1 Proforma of Allotment letterAllotment Letter_Deviation_Estella_A-Space_11072024.pdf · uploaded 2 Aug 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Scan2024-08-02_111829.pdf · uploaded 2 Aug 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A- Estella.pdf · uploaded 2 Aug 2024Source
- 1 Deviation Report with respect to Allotment letterDeviation Report of Al.pdf · uploaded 2 Aug 2024Source
- 1 Other – Technical1 Other – Technical (53).pdf · uploaded 2 Aug 2024Source
- 1 Deviation Report with respect to model copy of AgreementCCF_000082.pdf · uploaded 2 Aug 2024Source
- 1 Proforma of Agreement for saleAFS_Estella_A-Space_05082024.pdf · uploaded 2 Aug 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A- Estella.pdf · uploaded 2 Aug 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)A space.pdf · uploaded 2 Aug 2024Source
- 1 Disclosure for secured/unsecured finance availed for the project1 Disclosure for secured_unsecured finance availed for the project (11).pdf · uploaded 2 Aug 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 5 Oct 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 5 Oct 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 5 Oct 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 5 Oct 2024Source
- 1 Copy of Layout Approval (in case of layout)Layout Approval.pdf · uploaded 6 Oct 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval- Page 1.pdf · uploaded 6 Oct 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval- Page 2.pdf · uploaded 6 Oct 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval- Page 3.pdf · uploaded 6 Oct 2024Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 6 Oct 2024Source
- 1 Copy of Layout Approval (in case of layout)Layout Approval.pdf · uploaded 6 Oct 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval- Page 1.pdf · uploaded 6 Oct 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval- Page 2.pdf · uploaded 6 Oct 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval- Page 3.pdf · uploaded 6 Oct 2024Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 6 Oct 2024Source
- 1 Copy of Layout Approval (in case of layout)Layout Approval.pdf · uploaded 6 Oct 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval- Page 1.pdf · uploaded 6 Oct 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval- Page 2.pdf · uploaded 6 Oct 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval- Page 3.pdf · uploaded 6 Oct 2024Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 6 Oct 2024Source
- 1 Copy of Layout Approval (in case of layout)Layout Approval.pdf · uploaded 6 Oct 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval- Page 1.pdf · uploaded 6 Oct 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval- Page 2.pdf · uploaded 6 Oct 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval- Page 3.pdf · uploaded 6 Oct 2024Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 6 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Estella as on Dec 2024.pdf · uploaded 21 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Estella as on Dec 2024.pdf · uploaded 21 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Estella as on Dec 2024.pdf · uploaded 21 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Estella as on Dec 2024.pdf · uploaded 21 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Estella as on Dec 2024.pdf · uploaded 21 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Estella as on Dec 2024.pdf · uploaded 21 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Estella as on Dec 2024.pdf · uploaded 5 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Estella as on Dec 2024.pdf · uploaded 5 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Estella as on Dec 2024.pdf · uploaded 5 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Estella as on 31-03-2025.pdf · uploaded 20 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Estella as on March 2025.pdf · uploaded 20 Apr 2025Source
- 1 PAN Card1 PAN Card (2).pdf · uploaded 21 May 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (3).pdf · uploaded 21 May 2025Source
- Form 1Form 1 - Estella as on June 2025.pdf · uploaded 20 Jul 2025Source
- Form 2Form 2 - Estella as on June 2025.pdf · uploaded 20 Jul 2025Source
- Form 3Form 3 - Estella as on June 2025.pdf · uploaded 20 Jul 2025Source
- Disclosure of Sold and Booked InventoryCircular 29 - Estella as on June 2025.pdf · uploaded 20 Jul 2025Source
- Withdrawal Update Form 1Form 1 - Estella as on June 2025.pdf · uploaded 31 Jul 2025Source
- Withdrawal Update Form 2Form 2 - Estella as on June 2025.pdf · uploaded 31 Jul 2025Source
- Withdrawal Update Form 3Form 3 - Estella as on June 2025.pdf · uploaded 31 Jul 2025Source
- Withdrawal Update Form 1Form 1 - Estella as on Sep 2025.pdf · uploaded 20 Oct 2025Source
- Withdrawal Update Form 2Form 2 - Estella as on Sept 2025.pdf · uploaded 20 Oct 2025Source
- Withdrawal Update Form 3Form 3 - Estella as on Sept 2025.pdf · uploaded 20 Oct 2025Source
- Withdrawal Update Form 1Form 1 - Estella as on Sept 2025.pdf · uploaded 6 Nov 2025Source
- Withdrawal Update Form 2Form 2 - Estella as on Sept 2025.pdf · uploaded 6 Nov 2025Source
- Withdrawal Update Form 3Form 3 - Estella as on Sept 2025.pdf · uploaded 6 Nov 2025Source
- Form 2A (FY 2024-2025)Form 2A (FY 2024 - 25) - Estella.pdf · uploaded 9 Dec 2025Source
- Form 5 (FY 2024-2025)Form 5 (FY 2024- 25) - Estella.pdf · uploaded 9 Dec 2025Source
- Withdrawal Update Form 1Form 1 - Estella as on Dec 2025.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Form 2 - Estella as on Dec 2025.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Form 3 - Estella as on Dec 2025.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1Form 1 - Estella as on March 2026.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Form 2 - Estella as on March 2026.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Form 3 - Estella as on March 2026.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 1Form 1 - Estella as on June 2026.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 1Form 1 - Estella as on June 2026.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Form 2 - Estella as on March 2026.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Form 2 - Estella as on June 2026.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form 3 - Estella as on June 2026.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form 3 - Estella as on June 2026.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 1Form 1 - Estella as on June 2026.pdf · uploaded 31 Aug 2026Source
- Withdrawal Update Form 2Form 2 - Estella as on June 2026.pdf · uploaded 31 Aug 2026Source
- Withdrawal Update Form 3Form 3 - Estella as on June 2026.pdf · uploaded 31 Aug 2026Source
Technical
- Other – Technical1 Other – Technical (53).pdf · uploaded 2 Aug 2024Source
- Other – Technical1 Other – Technical (53).pdf · uploaded 2 Aug 2024Source
- Other – Technical1 Other – Technical (53).pdf · uploaded 2 Aug 2024Source
- DocumentLayout Approval.pdf · uploaded 6 Oct 2024Source
- DocumentLayout Approval.pdf · uploaded 6 Oct 2024Source
- DocumentLayout Approval.pdf · uploaded 6 Oct 2024Source
- DocumentLayout Approval.pdf · uploaded 6 Oct 2024Source
- DocumentBuilding Plan Approval- Page 3.pdf · uploaded 6 Oct 2024Source
- DocumentBuilding Plan Approval- Page 2.pdf · uploaded 6 Oct 2024Source
- DocumentBuilding Plan Approval- Page 1.pdf · uploaded 6 Oct 2024Source
- DocumentBuilding Plan Approval- Page 3.pdf · uploaded 6 Oct 2024Source
- DocumentBuilding Plan Approval- Page 2.pdf · uploaded 6 Oct 2024Source
- DocumentBuilding Plan Approval- Page 1.pdf · uploaded 6 Oct 2024Source
- DocumentBuilding Plan Approval- Page 3.pdf · uploaded 6 Oct 2024Source
- DocumentBuilding Plan Approval- Page 2.pdf · uploaded 6 Oct 2024Source
- DocumentBuilding Plan Approval- Page 1.pdf · uploaded 6 Oct 2024Source
- DocumentBuilding Plan Approval- Page 1.pdf · uploaded 6 Oct 2024Source
- DocumentBuilding Plan Approval- Page 2.pdf · uploaded 6 Oct 2024Source
- DocumentBuilding Plan Approval- Page 3.pdf · uploaded 6 Oct 2024Source
- DocumentPlan.pdf · uploaded 1 Aug 2025Source
- DocumentPlan.pdf · uploaded 1 Aug 2025Source
- Document1-4 - Marked.pdf · uploaded 5 Aug 2025Source
- Document2-4.pdf · uploaded 5 Aug 2025Source
- Document3-4.pdf · uploaded 5 Aug 2025Source
- Document4-4.pdf · uploaded 5 Aug 2025Source
- DocumentPlan.pdf · uploaded 20 Apr 2026Source
- DocumentCC.pdf · uploaded 20 Apr 2026Source
Technical (Architect)
- DocumentForm 1 - Estella as on Dec 2024.pdf · uploaded 5 Feb 2025Source
- DocumentForm 1 - Estella as on Dec 2024.pdf · uploaded 5 Feb 2025Source
- Document1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (3).pdf · uploaded 21 May 2025Source
- DocumentForm 1 - Estella as on June 2026.pdf · uploaded 20 Jul 2026Source
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot No.- 47, Sector-5A
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK16 units in all
- Address
- Plot No.- 47, Sector-5A, Sector No- 5A, New PanvelPIN 410206
- Village
- New Panvel, Panvel taluka
- Location
- 19.00614, 73.11724
- Land area for this project
- 1,181 sq m (12,714 sq ft)
- Permissible built-up area
- 3,496 sq m (37,633 sq ft)
- Sanctioned built-up area
- 3,019 sq m (32,496 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 220
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot No.- 47, Sector-5A
Boundaries
- North
- Plot No- 46
- South
- 8M Wide Road
- East
- 11M Wide Road
- West
- Plot No-45
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking16 units
0 of 16 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 52.16 sq m · 561 sq ft | 5 | 0 |
| 2BHK | 53.62 sq m · 577 sq ft | 1 | 0 |
| 2BHK | 53.82 sq m · 579 sq ft | 2 | 0 |
| 2BHK | 54.48 sq m · 586 sq ft | 3 | 0 |
| 3BHK | 69.73 sq m · 751 sq ft | 3 | 0 |
| 3BHK | 70.88 sq m · 763 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Engineer | Vikash Gini | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in New Panvel
- Bhagwati AuraRERA PM1270002602548
- Century NexusRERA PM1270002601979
- Mallika CHS Redevelopment (Scarlett Rise)RERA PR1271012600940
- Aniruddha Lk CrownRERA PM1270002600773
- Gami MiravaRERA PR1270002600408
- 4d AvinyaRERA PM1270002502930
- Capital OneRERA PC1270002502827
- Neelkanth LaxmiRERA PR1270002502727
All 76 projects in New Panvel · Compare Estella with another project