Queen Apartment
Deedo IDDP-RAI-FDESCompletion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 0% of its units are booked.
Mudre Khurd, Raigarh 410201 · by Universal Developer
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2030
- This projectRegistered 27 Apr 2026, completion promised 31 Dec 2029, revised to 30 Apr 2030.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPM1270002600264
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PM1270002600264 | 27 Apr 2026 | 31 Dec 2029 | 30 Apr 2030 | Universal Developer | Project page |
Documents37
1 document held by Deedo, 36 filings listed on MahaRERA's project page
Finance
- PAN CardUniversal Developer- Pancard.pdf · uploaded 25 Feb 2026Source
- GSTIN DocumentGST Certificate.pdf · uploaded 16 Mar 2026Source
- OthersPast Experince Declaration.pdf · uploaded 17 Mar 2026Source
- OthersEncumbrance Finance.pdf · uploaded 30 Mar 2026Source
- OthersCERSAI.pdf · uploaded 30 Mar 2026Source
- OthersDeclaration of Finance.pdf · uploaded 30 Mar 2026Source
- OthersDeclaration Regarding Not Selling Final.pdf · uploaded 31 Mar 2026Source
Show all 37 documentsShow fewer documents
Finance
- OthersDeclaration Regarding not selling units Corrected.pdf · uploaded 14 Apr 2026Source
Legal
- Declaration Form BForm B- Promoter.pdf · uploaded 27 Feb 2026Source
- Declaration Form BKARJAT 7-12.pdf · uploaded 27 Feb 2026Source
- OthersPast Experince Declaration.pdf · uploaded 17 Mar 2026Source
- OthersEncumbrance Legal.pdf · uploaded 30 Mar 2026Source
- Declaration Form BTitle Certificate Final 30326.pdf · uploaded 30 Mar 2026Source
- OthersIndex II.pdf · uploaded 31 Mar 2026Source
- OthersPartnership deed.pdf · uploaded 31 Mar 2026Source
- OthersUniversal deed of constitution_11zon.pdf · uploaded 31 Mar 2026Source
- OthersAll Partner DIN.pdf · uploaded 14 Apr 2026Source
- OthersPan Card Change EINDRA Realtor to Uinersal Developer.pdf · uploaded 14 Apr 2026Source
- Others7-12 for Survey No 7B plot No 9 and 13.pdf · uploaded 14 Apr 2026Source
Planning Authority
- DocumentCert_RB_588060_180Ov5pNSign.pdf · uploaded 25 Feb 2026Source
- Document1767597269_CCRUM-25-ENTRY-143321_R1.html · uploaded 25 Feb 2026Source
- Document1767597269_CCRUM-25-ENTRY-143321_R1.pdf_8_98DSE_Sign.pdfSign.pdf · uploaded 25 Feb 2026Source
- DocumentHJFEqsCLjWOrder.pdf · uploaded 25 Feb 2026Source
- DocumentBoad8bMCDBSATBARA.pdf · uploaded 25 Feb 2026Source
- DocumentHJFEqsCLjWOLD_APPROVAL.pdf · uploaded 25 Feb 2026Source
Technical
- DocumentUNIVERSAL DEVELOPER PLAN.pdf · uploaded 25 Feb 2026Source
- DocumentUNIVERSAL DEVELOPER PLAN.pdf · uploaded 25 Feb 2026Source
- OthersForm 2.pdf · uploaded 17 Mar 2026Source
- OthersPast Experince Declaration.pdf · uploaded 17 Mar 2026Source
- OthersForm 1.pdf · uploaded 17 Mar 2026Source
- DocumentPlot Area Declaration Order 50.pdf · uploaded 30 Mar 2026Source
- OthersDIN Declaration.pdf · uploaded 30 Mar 2026Source
- OthersCC Declaration.pdf · uploaded 30 Mar 2026Source
- OthersPartnership deed.pdf · uploaded 31 Mar 2026Source
- OthersUniversal deed of constitution_11zon.pdf · uploaded 31 Mar 2026Source
- OthersAll Partner DIN.pdf · uploaded 14 Apr 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 13, Plot no- 9
As registered with MahaRERA and published on its project page
- Project type
- Mixed
- Status on MahaRERA
- Certificate Signed
- Unit types
- —53 units in all
- Address
- Street- 9.00, Mudre KhurdPIN 410201
- Village
- Mudre Khurd, Karjat taluka
- Location
- 18.91605, 73.32297
- Land area for this project
- 955 sq m (10,280 sq ft)
- Permissible built-up area
- 2,603 sq m (28,020 sq ft)
- Sanctioned built-up area
- 2,603 sq m (28,018 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 212
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
plot_no - city_survey_gut_no SURVEY NO. 7B PLOT NO. 9 AND 13 final_plot_no - sector_no - mauje MUDRE KHURD road_street 9.00 society -
Boundaries
- North
- 3.00MT Wide Driveway
- South
- 9.00MT Wide Road
- East
- 9.00MT Wide Road
- West
- 9.00MT Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking53 units
53 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 53 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Other projects in Mudre Khurd
- Gayatri Krupa HeightsRERA PM1270002601117
All 2 projects in Mudre Khurd · Compare Queen Apartment with another project