Sadguru Universal
Deedo IDDP-RAI-4MT9MahaRERA shows it completed; no MahaRERA orders on record; 67% of its units are booked.
Motha Khanda, Raigarh 410206 · by Sadguru Infraprojects I Pvt Ltd
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 18 Aug 2017, completion promised 30 Dec 2022.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000008358
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000008358 | 18 Aug 2017 | 30 Dec 2022 | 30 Dec 2022 | Sadguru Infraprojects I Pvt Ltd | Project page |
Documents65
1 document held by Deedo, 64 filings listed on MahaRERA's project page
Finance
- PAN CardPAN SADGURU INFRAPROJECTS I PVT LTD.pdf · uploaded 28 Jul 2017Source
Legal
- Legal Title reportTITLE REPORT_ ADV SUNIL GARG.pdf · uploaded 28 Jul 2017Source
- Declaration Form BLalit V Patodia_Declaration Scan Copy 1.pdf · uploaded 28 Jul 2017Source
- Other – LegalCIDCO Society Letter Univeral.pdf · uploaded 17 Jul 2024Source
- Other – LegalSociety Order.pdf · uploaded 17 Jul 2024Source
Show all 65 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesencumbrances_Certificate.pdf · uploaded 28 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)Scan-1.pdf · uploaded 28 Jul 2017Source
- 1 Building Plan Approval (IOD)Scan-1.pdf · uploaded 28 Jul 2017Source
- 2 Building Plan Approval (IOD)Scan-2.pdf · uploaded 28 Jul 2017Source
- 3 Building Plan Approval (IOD)Scan-3.pdf · uploaded 28 Jul 2017Source
- 4 Building Plan Approval (IOD)Scan-4.pdf · uploaded 28 Jul 2017Source
- 5 Building Plan Approval (IOD)Scan-5.pdf · uploaded 28 Jul 2017Source
- 6 Building Plan Approval (IOD)Scan-6.pdf · uploaded 28 Jul 2017Source
- 7 Building Plan Approval (IOD)Scan-7.pdf · uploaded 28 Jul 2017Source
- 8 Building Plan Approval (IOD)Scan-8.pdf · uploaded 28 Jul 2017Source
- 9 Building Plan Approval (IOD)Scan-9.pdf · uploaded 28 Jul 2017Source
- 10 Building Plan Approval (IOD)Scan-10.pdf · uploaded 28 Jul 2017Source
- 11 Building Plan Approval (IOD)Scan-11.pdf · uploaded 28 Jul 2017Source
- 12 Building Plan Approval (IOD)Scan-12.pdf · uploaded 28 Jul 2017Source
- 1 Declaration in FORM BLalit V Patodia_Declaration Scan Copy 1.pdf · uploaded 28 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Satish Ahuja_RERA_Certificate-min.pdf · uploaded 28 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Anish S Utekar_RERA-.pdf · uploaded 28 Jul 2017Source
- 1 Certificates of CA (Form 3)FORM-3.pdf · uploaded 28 Jul 2017Source
- 1 Proforma of Allotment letterSADGURU INFRA PROJECTS - SADGURU UNIVERSAL---AOS_RERA_DRAFT.pdf · uploaded 28 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentSadguru Universal_CC Scan copy.PDF · uploaded 16 Jan 2018Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate 03012018.pdf · uploaded 16 Jan 2018Source
- 2 Certificates of CA (Form 3)FORM-3 (2).pdf · uploaded 16 Jan 2018Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM-1.pdf · uploaded 25 Aug 2018Source
- 3 Certificates of CA (Form 3)FORM-3 17718.pdf · uploaded 25 Aug 2018Source
- 1 Certificates of CA (Form 5)Sadguru Universal.pdf · uploaded 15 Oct 2018Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)S U RERA CERTIFICET NO 04 31122018.pdf · uploaded 14 Jan 2019Source
- 4 Certificates of CA (Form 3)S U CA RERA FORM3.pdf · uploaded 14 Jan 2019Source
- 2 Certificates of CA (Form 5)Sadguru Universe.pdf · uploaded 1 Oct 2019Source
- 3 Certificates of CA (Form 5)Sadguru Universe.pdf · uploaded 1 Oct 2019Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM-1.pdf · uploaded 22 Jan 2020Source
- 5 Certificates of CA (Form 3)Form 3 15122019.pdf · uploaded 25 Jan 2020Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentSadguru Universal Work Completion Certificate.pdf · uploaded 6 Jul 2020Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentSadguru Universal O C.pdf · uploaded 6 Jul 2020Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A Engineers's Quality Assurance Certificate Universal.pdf · uploaded 29 Aug 2020Source
- 6 Certificates of CA (Form 3)FORM 3 CA SADGURU UNIVERSAL 2020-08-29 (2).pdf · uploaded 29 Aug 2020Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4 SU.pdf · uploaded 29 Aug 2020Source
- 4 Certificates of CA (Form 5)FORM 5 CA CERTIFICATE.pdf · uploaded 31 Aug 2020Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Gruhnirman.pdf · uploaded 17 Jul 2024Source
- 2 Status of Formation of Legal Entity (Society/Co Op etc.)Premises.pdf · uploaded 17 Jul 2024Source
- 1 Status of ConveyanceStatus of Conveyance.pdf · uploaded 17 Jul 2024Source
- 1 Other – LegalCIDCO Society Letter Univeral.pdf · uploaded 17 Jul 2024Source
- 2 Other – LegalSociety Order.pdf · uploaded 17 Jul 2024Source
Technical
- DocumentScan-11.pdf · uploaded 28 Jul 2017Source
- DocumentScan-12.pdf · uploaded 28 Jul 2017Source
- DocumentScan-10.pdf · uploaded 28 Jul 2017Source
- DocumentScan-6.pdf · uploaded 28 Jul 2017Source
- DocumentScan-7.pdf · uploaded 28 Jul 2017Source
- DocumentScan-8.pdf · uploaded 28 Jul 2017Source
- DocumentScan-9.pdf · uploaded 28 Jul 2017Source
- DocumentScan-4.pdf · uploaded 28 Jul 2017Source
- DocumentScan-2.pdf · uploaded 28 Jul 2017Source
- DocumentScan-3.pdf · uploaded 28 Jul 2017Source
- DocumentScan-5.pdf · uploaded 28 Jul 2017Source
- DocumentScan-1.pdf · uploaded 28 Jul 2017Source
- DocumentScan-1.pdf · uploaded 28 Jul 2017Source
Technical (Architect)
- DocumentS U RERA CERTIFICET NO 04 31122018.pdf · uploaded 14 Jan 2019Source
Technical (Engineer)
- DocumentAnish S Utekar_RERA-.pdf · uploaded 28 Jul 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT NO19, SECTOR17
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1 BHK, 1 RK, 2 BHK, Shop112 units in all
- Address
- PLOT NO-19, SECTOR-17, NEW PANVEL W, Khanda Colony, Sector -17, New Panvel (W)PIN 410206
- Village
- Motha Khanda, Panvel taluka
- Location
- 19.00915, 73.10561
- Land area for this project
- 2,587 sq m (27,846 sq ft)
- Permissible built-up area
- 3,879 sq m (41,756 sq ft)
- Sanctioned built-up area
- 3,879 sq m (41,756 sq ft)
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO-19, SECTOR-17, NEW PANVEL W
Boundaries
- North
- Road Width 20 Mts
- South
- Plot No -17 And 18 And 20
- East
- Road Width 30 Mts
- West
- Road Width 15 Mts
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking112 units
75 of 112 units booked (67%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 21.46 sq m · 231 sq ft | 5 | 4 |
| 1 BHK | 22.01 sq m · 237 sq ft | 1 | 1 |
| 1 BHK | 22.69 sq m · 244 sq ft | 2 | 2 |
| 1 BHK | 23.74 sq m · 256 sq ft | 1 | 1 |
| 1 BHK | 23.94 sq m · 258 sq ft | 9 | 9 |
| 1 BHK | 24.74 sq m · 266 sq ft | 1 | 1 |
| 1 BHK | 26.74 sq m · 288 sq ft | 1 | 0 |
| 1 BHK | 28.85 sq m · 311 sq ft | 1 | 0 |
Show all 45 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 29.65 sq m · 319 sq ft | 6 | 3 |
| 1 BHK | 29.79 sq m · 321 sq ft | 8 | 7 |
| 1 BHK | 29.94 sq m · 322 sq ft | 1 | 1 |
| 1 RK | 17.25 sq m · 186 sq ft | 1 | 1 |
| 1 RK | 20.59 sq m · 222 sq ft | 1 | 1 |
| 2 BHK | 37.65 sq m · 405 sq ft | 1 | 0 |
| 2 BHK | 37.75 sq m · 406 sq ft | 1 | 1 |
| 2 BHK | 37.84 sq m · 407 sq ft | 5 | 2 |
| 2 BHK | 38.21 sq m · 411 sq ft | 1 | 1 |
| 2 BHK | 38.75 sq m · 417 sq ft | 11 | 7 |
| 2 BHK | 38.86 sq m · 418 sq ft | 1 | 0 |
| 2 BHK | 39.39 sq m · 424 sq ft | 18 | 11 |
| 2 BHK | 40.26 sq m · 433 sq ft | 1 | 1 |
| 2 BHK | 40.88 sq m · 440 sq ft | 2 | 2 |
| 2 BHK | 42.14 sq m · 454 sq ft | 4 | 4 |
| 2 BHK | 44.04 sq m · 474 sq ft | 1 | 1 |
| 2 BHK | 44.1 sq m · 475 sq ft | 4 | 2 |
| Shop | 9.71 sq m · 105 sq ft | 5 | 4 |
| Shop | 9.85 sq m · 106 sq ft | 1 | 0 |
| Shop | 12.32 sq m · 133 sq ft | 1 | 1 |
| Shop | 22.52 sq m · 242 sq ft | 1 | 1 |
| Shop | 26.05 sq m · 280 sq ft | 1 | 0 |
| Shop | 26.25 sq m · 283 sq ft | 1 | 1 |
| Shop | 26.91 sq m · 290 sq ft | 1 | 0 |
| Shop | 26.94 sq m · 290 sq ft | 1 | 0 |
| Shop | 27.21 sq m · 293 sq ft | 1 | 0 |
| Shop | 27.53 sq m · 296 sq ft | 1 | 0 |
| Shop | 27.87 sq m · 300 sq ft | 1 | 0 |
| Shop | 28.18 sq m · 303 sq ft | 1 | 0 |
| Shop | 28.22 sq m · 304 sq ft | 1 | 0 |
| Shop | 30.27 sq m · 326 sq ft | 1 | 1 |
| Shop | 31.57 sq m · 340 sq ft | 1 | 0 |
| Shop | 32.66 sq m · 352 sq ft | 1 | 1 |
| Shop | 36.11 sq m · 389 sq ft | 1 | 0 |
| Shop | 38.37 sq m · 413 sq ft | 1 | 1 |
| Shop | 38.68 sq m · 416 sq ft | 1 | 1 |
| Shop | 52.74 sq m · 568 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Satish Ahuja | — |
| Engineer | Epicons Consultants Pvt Ltd | — |
| Other | Upen Construction | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Motha Khanda
- Future ExoticaRERA P52000021000
All 2 projects in Motha Khanda · Compare Sadguru Universal with another project