Aryan Park

Deedo IDDP-RAI-W5J6

Completion was pushed back 2 years and 6 months to Dec 2024, and that date has passed too; no MahaRERA orders on record; 35% of its units are booked.

Mamdapur, Raigarh 410201 · by Ayushkranti Builders & Developers Pvt Ltd

Delivery4 yrs 5 mo latePromised Jun 2022 · revised Dec 2024 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales35% booked9 of 26 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 2 years and 6 months to Dec 2024, and that date has passed too

  • This projectRegistered 30 Sep 2020, completion promised 30 Jun 2022, revised to 31 Dec 2024, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000026534
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200002653430 Sep 202030 Jun 202231 Dec 2024Ayushkranti Builders & Developers Pvt LtdProject page
Documents72

3 documents held by Deedo, 69 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardCOMPANY PAN CARD.pdf · uploaded 26 Sep 2020Source

Legal

  • OtherLAND AGREEMENT.pdf · uploaded 26 Sep 2020Source
  • OtherBOARD RESOLUTION.pdf · uploaded 26 Sep 2020Source
  • OtherKRANTI LAL SINGH PAN.pdf · uploaded 26 Sep 2020Source
  • OtherKRANTI LAL SINGH AADHAR.pdf · uploaded 26 Sep 2020Source
Show all 72 documentsShow fewer documents

Legal

  • OtherCERTIFICATES OF INCORPORATION.pdf · uploaded 26 Sep 2020Source
  • OtherDEVELOPMENT AGREEMENT.pdf · uploaded 26 Sep 2020Source
  • OtherASHWIN PAN.pdf · uploaded 26 Sep 2020Source
  • OtherASHWIN AADHAR.pdf · uploaded 26 Sep 2020Source
  • Legal Title reportSEARCH REPORT.pdf · uploaded 26 Sep 2020Source
  • Declaration Form BFORM B KRANTILAL SINGH.pdf · uploaded 26 Sep 2020Source
  • Declaration Form BAdobe Scan Aug 10, 2023.pdf · uploaded 10 Aug 2023Source

Migrated

  • 1 PAN CardCOMPANY PAN CARD.pdf · uploaded 26 Sep 2020Source
  • 1 Copy of the legal title reportSEARCH REPORT.pdf · uploaded 26 Sep 2020Source
  • 1 Details of encumbrancesENCUMBRANES KRANTI.pdf · uploaded 26 Sep 2020Source
  • 2 Details of encumbrancesENCUMBRANCES JAVED.pdf · uploaded 26 Sep 2020Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT 1.pdf · uploaded 26 Sep 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentNA ORDER.pdf · uploaded 26 Sep 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 26 Sep 2020Source
  • 1 Declaration in FORM BFORM B KRANTILAL SINGH.pdf · uploaded 26 Sep 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 26 Sep 2020Source
  • 1 Proforma of Allotment letterDRAFT AGREEMENT.pdf · uploaded 26 Sep 2020Source
  • 1 OtherLAND AGREEMENT.pdf · uploaded 26 Sep 2020Source
  • 2 OtherBOARD RESOLUTION.pdf · uploaded 26 Sep 2020Source
  • 3 OtherKRANTI LAL SINGH PAN.pdf · uploaded 26 Sep 2020Source
  • 4 OtherKRANTI LAL SINGH AADHAR.pdf · uploaded 26 Sep 2020Source
  • 5 OtherCERTIFICATES OF INCORPORATION.pdf · uploaded 26 Sep 2020Source
  • 6 OtherDEVELOPMENT AGREEMENT.pdf · uploaded 26 Sep 2020Source
  • 7 OtherASHWIN PAN.pdf · uploaded 26 Sep 2020Source
  • 8 OtherASHWIN AADHAR.pdf · uploaded 26 Sep 2020Source
  • 1 b Details of encumbrances concerned to LegalENCRAMBCE OF LEGAL.pdf · uploaded 6 Oct 2022Source
  • 1 Declaration about Commencement CertificateCOOMEMENT CERTIFICATE.pdf · uploaded 6 Oct 2022Source
  • 1 CERSAI detailscersai.pdf · uploaded 6 Oct 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 2019 2020.pdf · uploaded 6 Oct 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 2020 2021.pdf · uploaded 6 Oct 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK DETAIL.pdf · uploaded 6 Oct 2022Source
  • 1 Deviation Report with respect to Allotment letterDEVIAITION OF ALLOTMENT LETTER.pdf · uploaded 6 Oct 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION OF AGREEMNET PLAN.pdf · uploaded 6 Oct 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Aayush kranti - Architect Certificate .pdf · uploaded 8 Oct 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATES FINAL_compressed.pdf · uploaded 4 Nov 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)QUALITY ASSURANCE CERTIFICATE - 2020 - 2021.pdf · uploaded 15 Nov 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)QUALITY ASSURANCE CERTIFICATE - 2021- 2022.pdf · uploaded 15 Nov 2022Source
  • 1 Disclosure of sold/ booked inventorySOLD - BOOKED INVENTORY.pdf · uploaded 15 Nov 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE - AYUSHKRANTI.pdf · uploaded 26 Jul 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE 75 - AYUSHKRANTI BUILDERS.pdf · uploaded 26 Jul 2023Source
  • 2 Disclosure of sold/ booked inventoryAryan park booked inventory.pdf · uploaded 8 Aug 2023View
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 8 Aug 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5.pdf · uploaded 8 Aug 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A kranti Singh.pdf · uploaded 9 Aug 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Ashwinkumar singh.pdf · uploaded 9 Aug 2023Source
  • 2 Declaration in FORM BAdobe Scan Aug 10, 2023.pdf · uploaded 10 Aug 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)CERTIFICATE ARCHITECT.pdf · uploaded 10 Aug 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)CERTIFICATE ENGINEER.pdf · uploaded 10 Aug 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA FORM 3.pdf · uploaded 10 Aug 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentScannerGo_1692256623378.pdf · uploaded 17 Aug 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentScannerGo_1692256623378.pdf · uploaded 17 Aug 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentAayush kranti zp order.pdf · uploaded 17 Aug 2023Source
  • 2 Declaration about Commencement CertificateAyush kranti.pdf · uploaded 17 Aug 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITET.pdf · uploaded 17 Aug 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER.pdf · uploaded 17 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)ENGINEER.pdf · uploaded 17 Aug 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA FORM 3.pdf · uploaded 17 Aug 2023Source
  • 1 Proforma of Agreement for saleAGREEMENT PLAN.pdf · uploaded 17 Aug 2023Source

Technical

  • DocumentNA ORDER.pdf · uploaded 26 Sep 2020Source
  • DocumentLAYOUT 1.pdf · uploaded 26 Sep 2020Source
  • DocumentScannerGo_1692256623378.pdf · uploaded 17 Aug 2023Source
  • DocumentScannerGo_1692256623378.pdf · uploaded 17 Aug 2023Source

Technical (Architect)

  • DocumentARCHITET.pdf · uploaded 17 Aug 2023Source

Technical (Engineer)

  • DocumentENGINEER.pdf · uploaded 17 Aug 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO 37, S NO 175

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, Shop26 units in all
Address
Plot No 37, S No 175, Plot No 37, KarjatPIN 410201
Village
Mamdapur, Karjat taluka
Land area for this project
460 sq m (4,951 sq ft)
Permissible built-up area
547 sq m (5,888 sq ft)
Sanctioned built-up area
547 sq m (5,888 sq ft)
Designated bank account
87
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO 37S NO 175

Land as published on MahaRERA's project page

PLOT NO 37,S NO 175

Boundaries

North
Layout Road
South
Plot No 37
East
Plot No 32
West
Layout Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking26 units

9 of 26 units booked (35%), as the promoter reported to MahaRERA

1BHK · 19 unitsShop · 7 units
TypeCarpet areaUnitsBooked
1BHK27.95 sq m · 301 sq ft41
1BHK28.92 sq m · 311 sq ft32
1BHK28.95 sq m · 312 sq ft42
1BHK29.73 sq m · 320 sq ft41
1BHK29.98 sq m · 323 sq ft41
Shop6.75 sq m · 73 sq ft11
Shop7.97 sq m · 86 sq ft10
Shop8.34 sq m · 90 sq ft10
Show all 12 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop8.88 sq m · 96 sq ft11
Shop9.04 sq m · 97 sq ft10
Shop10.93 sq m · 118 sq ft10
Shop11.49 sq m · 124 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPioneer Architect—
ArchitectThe Design India Group—
Chartered accountantGnc And Associates—
EngineerRam Marathe—
OtherDharam Prakash Jaiswal—

Source: MahaRERA project page. Contact details are not shown.