Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 0% of its units are booked.

Deulwadi, Raigarh 410201 · by Willy Trade Private Limited

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 57 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 28 Mar 2025, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000079893
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200007989328 Mar 202531 Dec 202830 Apr 2029Willy Trade Private LimitedProject page
Documents60

1 document held by Deedo, 59 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardCompany Pan.pdf · uploaded 10 Mar 2025Source
  • Other – FinanceDeclaration regarding land cost zero.pdf · uploaded 10 Mar 2025Source

Legal

  • Legal Title reportTitle Report New 24-03-2025.pdf · uploaded 10 Mar 2025Source
  • Declaration Form BForm B Promoter 500rs.pdf · uploaded 10 Mar 2025Source
  • Other – LegalAFS Deviation Final 22-03-2025 CS.pdf · uploaded 21 Mar 2025Source

Migrated

  • 1 PAN CardCompany Pan.pdf · uploaded 10 Mar 2025Source
  • 1 Copy of the legal title reportTitle Report New 24-03-2025.pdf · uploaded 10 Mar 2025Source
Show all 60 documentsShow fewer documents

Migrated

  • 1 a Details of encumbrances concerned to FinanceEncumbrance Finance.pdf · uploaded 10 Mar 2025Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Legal.pdf · uploaded 10 Mar 2025Source
  • 1 Copy of Layout Approval (in case of layout)FINAL PLAN (1).pdf · uploaded 10 Mar 2025Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 10 Mar 2025Source
  • 1 Declaration in FORM BForm B Promoter 500rs.pdf · uploaded 10 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Final.pdf · uploaded 10 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Final.pdf · uploaded 10 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Final.pdf · uploaded 10 Mar 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentFINAL CC CERTIFICATE.pdf · uploaded 10 Mar 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentFINAL PLAN (1).pdf · uploaded 10 Mar 2025Source
  • 1 Declaration about Commencement CertificateCC Declaration.pdf · uploaded 10 Mar 2025Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 10 Mar 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A.pdf · uploaded 10 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterDeviation Allotment.pdf · uploaded 10 Mar 2025Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Finance.pdf · uploaded 10 Mar 2025Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Legal.pdf · uploaded 10 Mar 2025Source
  • 1 Other – FinanceDeclaration regarding land cost zero.pdf · uploaded 10 Mar 2025Source
  • 1 Other – TechnicalOrder 50.pdf · uploaded 10 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementAFS Deviation.pdf · uploaded 10 Mar 2025Source
  • 1 Proforma of Agreement for saleAFS Final 26-03-2025.pdf · uploaded 10 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDIN Kush.pdf · uploaded 10 Mar 2025Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDIN Rakshita.pdf · uploaded 10 Mar 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B .pdf · uploaded 10 Mar 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure of Secured Unsecured funds.pdf · uploaded 10 Mar 2025Source
  • 1 Other – LegalAFS Deviation Final 22-03-2025 CS.pdf · uploaded 21 Mar 2025Source
  • 2 Proforma of Agreement for saleAFS Deviation Final 22-03-2025 CS.pdf · uploaded 22 Mar 2025Source
  • Form 1Form 1 March 2025.pdf · uploaded 12 Sep 2025Source
  • Form 2Form 2 March 2025.pdf · uploaded 12 Sep 2025Source
  • Form 3Form 3 March 2025.pdf · uploaded 12 Sep 2025Source
  • Disclosure of Sold and Booked InventoryCIRCULAR 29 March 2025.pdf · uploaded 12 Sep 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 12 Sep 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 12 Sep 2025Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 12 Sep 2025Source
  • Form 5 (FY 2024-2025)FORM 5 FY 24-25 Final_Signed_250925_163939.pdf · uploaded 25 Sep 2025Source
  • Withdrawal Update Form 1Withdrawal Application Form1 As on September 2025.pdf · uploaded 13 Nov 2025Source
  • Withdrawal Update Form 2Withdrawal Application Form2 As on September 2025.pdf · uploaded 13 Nov 2025Source
  • Withdrawal Update Form 3Withdrawal Application Form3 Latest as on September 2025.pdf · uploaded 13 Nov 2025Source
  • Withdrawal Update Form 1Withdrawal Application Form1 as on December 2025.pdf · uploaded 11 Mar 2026Source
  • Withdrawal Update Form 2Withdrawal Application Form2 as on December 2025.pdf · uploaded 11 Mar 2026Source
  • Withdrawal Update Form 3Withdrawal Application Form3 as on December 2025.pdf · uploaded 11 Mar 2026Source
  • Withdrawal Update Form 1Form 1 March 2026.pdf · uploaded 31 May 2026Source
  • Withdrawal Update Form 2Form 2 March 2026.pdf · uploaded 31 May 2026Source
  • Withdrawal Update Form 3Form 3 March 2026.pdf · uploaded 31 May 2026Source
  • Withdrawal Update Form 1Mr Ram Bhathija -rera certificate_260729_224534.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2Withdrawal Application Form2_Bjatija_signed_260730_100149.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3Form 3 sign_260729_224603.pdf · uploaded 30 Jul 2026Source
  • Form 5 (FY 2025-2026)Form 5 willy FY 25-26-1_260918_111600_260921_110837.pdf · uploaded 21 Sep 2026Source

Technical

  • DocumentFINAL PLAN (1).pdf · uploaded 10 Mar 2025Source
  • DocumentFINAL PLAN (1).pdf · uploaded 10 Mar 2025Source
  • Other – TechnicalOrder 50.pdf · uploaded 10 Mar 2025Source

Technical (Architect)

  • DocumentMr Ram Bhathija -rera certificate_260729_224534.pdf · uploaded 30 Jul 2026Source

Technical (Engineer)

  • DocumentWithdrawal Application Form2_Bjatija_signed_260730_100149.pdf · uploaded 30 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No 4, S. No. 62

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1 BHK Landowner, 2BHK, 2 BHK Landowner, Shop, Shop Landowner57 units in all
Address
S. No. 62, Plot No 4, Deulwadi, Village Deulwadi at Taluka- Karjat, Dist- RaigadPIN 410201
Village
Deulwadi, Karjat taluka
Land area for this project
1,063 sq m (11,442 sq ft)
Permissible built-up area
2,390 sq m (25,726 sq ft)
Sanctioned built-up area
2,390 sq m (25,726 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No 4S. No. 62

Land as published on MahaRERA's project page

S. No. 62, Plot No 4

Boundaries

North
12 Meter Wide Road
South
9 Meter Wide Road
East
Adj Plot No 3
West
Adj Plot No 15

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking57 units

0 of 57 units booked (0%), as the promoter reported to MahaRERA

1BHK · 25 units1 BHK Landowner · 13 units2BHK · 8 units2 BHK Landowner · 6 unitsShop · 3 unitsShop Landowner · 2 units
TypeCarpet areaUnitsBooked
1BHK30.75 sq m · 331 sq ft160
1BHK31.83 sq m · 343 sq ft90
1 BHK Landowner30.75 sq m · 331 sq ft80
1 BHK Landowner31.83 sq m · 343 sq ft50
2BHK42.5 sq m · 457 sq ft80
2 BHK Landowner42.5 sq m · 457 sq ft60
Shop16.91 sq m · 182 sq ft30
Shop Landowner16.91 sq m · 182 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectElevation Designers and Planners Pvt Ltd—
Chartered accountantMeenali N Shah Chartered Accountants—
EngineerVastukalp—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Deulwadi

All 8 projects in Deulwadi · Compare Krishna Heritage with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology