Residential / Group Housing · 1 building · 148 unitsRERA PR1270002500190

World Tower

Deedo IDDP-RAI-902W

Completion was pushed back 4 months, to Sep 2029; no MahaRERA orders on record; 7% of its units are booked.

Dapoli, Raigarh 410206 · by Infragate Constructions LLP

DeliveryExtended 4 moPromised May 2029 · now due Sep 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales7% booked11 of 148 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Sep 2029

  • This projectRegistered 3 Jul 2025, completion promised 31 May 2029, revised to 30 Sep 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1270002500190
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR12700025001903 Jul 202531 May 202930 Sep 2029Infragate Constructions LLPProject page
Documents29

1 document held by Deedo, 28 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card - Firm.pdf · uploaded 12 Jun 2025Source

Legal

  • OthersAnnexure A - Disclosure of Interest.pdf · uploaded 14 Jun 2025Source
  • Declaration Form BForm B - Promoter.pdf · uploaded 17 Jun 2025Source
  • OthersAgreement to Lease.pdf · uploaded 20 Jun 2025Source
  • OthersTripartite Agreement.pdf · uploaded 20 Jun 2025Source
  • Declaration Form BShort title_World Tower_Infragate Constructions LLP_20062025.pdf · uploaded 20 Jun 2025Source
  • Declaration Form BTripartite Agreement.pdf · uploaded 20 Jun 2025Source
Show all 29 documentsShow fewer documents

Migrated

  • Withdrawal Update Form 1Form 1 - World Tower as on Dec 2025.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 1Form 1 - World Tower as on Dec 2025.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 1Form 1 - World Tower as on March 2026.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 2Form 2 - World Tower as on March 2026.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 2Form 2 - World Tower as on March 2026.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 2Form 2 - World Tower as on March 2026.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 3Form 3 - World Tower as on Sep 2025.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 3Form 3 - World Tower as on Dec 2025.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 3Form 3 - World Tower as on March 2026.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 1RERA-Form-1 420-03- PUSHPAK-30-06-2026.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2World_Tower_Form2_Q1_2026-27_20-07-2026_13-13.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3World_Tower_Form3_Q1_2026-27_14-07-2026_13-23_doc1.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 1RERA-Form-1 420-03- PUSHPAK-30-06-2026.pdf · uploaded 20 Aug 2026Source
  • Withdrawal Update Form 2World_Tower_Form2_Q1_2026-27_20-07-2026_13-13.pdf · uploaded 20 Aug 2026Source
  • Withdrawal Update Form 3World_Tower_Form3_Q1_2026-27_14-07-2026_13-23_doc1.pdf · uploaded 20 Aug 2026Source

Technical

  • DocumentApproved Plan - Pg 1.pdf · uploaded 13 Jun 2025Source
  • DocumentApproved Plan - Pgs 2 - 4.pdf · uploaded 13 Jun 2025Source
  • DocumentApproved Plan - Pgs 5 - 6.pdf · uploaded 13 Jun 2025Source
  • DocumentAnnexure A - Order No 50.pdf · uploaded 20 Jun 2025Source

Technical (Architect)

  • DocumentRERA-Form-1 420-03- PUSHPAK-30-06-2026.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentWorld_Tower_Form2_Q1_2026-27_20-07-2026_13-13.pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No. 420, Sector 3

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—148 units in all
Address
PushpakPIN 410206
Village
Dapoli, Panvel taluka
Land area for this project
2,040 sq m (21,954 sq ft)
Permissible built-up area
8,281 sq m (89,135 sq ft)
Sanctioned built-up area
8,211 sq m (88,379 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No. 420Sector 3

Land as published on MahaRERA's project page

Plot No. 420, Sector 3

Boundaries

North
Plot No 454,455 and 456
South
15M Wide Road
East
Plot No 421
West
Plot No 419

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking148 units

148 units registered

— · 148 units
TypeCarpet areaUnits
——148

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Other projects in Dapoli

All 143 projects in Dapoli · Compare World Tower with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology