Skip to content
Residential / Group Housing · 1 building · 16 unitsRERA P52000046452

Savitri Arcade

Deedo IDDP-RAI-8Q2B

Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Dapoli, Raigarh 410206 · by Savitri Builders and Developer

Delivery11 mo past duePromised Dec 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 16 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 4 Aug 2022, completion promised 31 Dec 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000046452
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P520000464524 Aug 202231 Dec 202531 Dec 2025Savitri Builders and DeveloperProject page
Documents27

1 document held by Deedo, 26 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPancard Savitri.pdf · uploaded 31 May 2022Source

Legal

  • Declaration Form BForm B Savitri _compressed.pdf · uploaded 3 Jun 2022Source
  • Legal Title reportTitle_Scan_compressed (1).pdf · uploaded 7 Jun 2022Source

Migrated

  • 1 PAN CardPancard Savitri.pdf · uploaded 31 May 2022Source
  • 1 Declaration about Commencement CertificateCC Declaration Savitri .pdf · uploaded 3 Jun 2022Source
  • 1 Declaration in FORM BForm B Savitri _compressed.pdf · uploaded 3 Jun 2022Source
  • 1 Copy of the legal title reportTitle_Scan_compressed (1).pdf · uploaded 7 Jun 2022Source
Show all 27 documentsShow fewer documents

Migrated

  • 1 CERSAI detailsCERSAI_Search_Report_200239063716_For_Asset_Based_Search_07_06_2022_18_26_32_102.pdf · uploaded 7 Jun 2022Source
  • 1 Copy of Layout Approval (in case of layout)Plan.pdf · uploaded 1 Jul 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan.pdf · uploaded 1 Jul 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 1 Jul 2022Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance -Dues -Savitri.pdf · uploaded 19 Jul 2022Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance -Litigations -Savitri.pdf · uploaded 19 Jul 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation -Allotment.pdf · uploaded 19 Jul 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)organized (7)_compressed.pdf · uploaded 20 Jul 2022Source
  • 1 Proforma of Allotment letterAFS_SAVITRI ARCADE _20-07-2022.pdf · uploaded 20 Jul 2022Source
  • 2 Proforma of Allotment letterAllotment Letter _ Savitri Arcade_20-07-2022.pdf · uploaded 20 Jul 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report Savitri 20072022.pdf · uploaded 20 Jul 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A - Seperate Bank Account Details.pdf · uploaded 29 Jul 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Savitri Arcade as on 31-03-2024.pdf · uploaded 6 Dec 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Savitri Arcade as on March 2024.pdf · uploaded 6 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 - Savitri Arcade for FY 2022-23.pdf · uploaded 6 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - Savitri Arcade for FY 2023-24.pdf · uploaded 6 Dec 2024Source

Technical

  • DocumentPlan.pdf · uploaded 1 Jul 2022Source
  • DocumentPlan.pdf · uploaded 1 Jul 2022Source

Technical (Engineer)

  • DocumentForm 2 - Savitri Arcade as on March 2024.pdf · uploaded 6 Dec 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No. 127

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK16 units in all
Address
Plot No.- 127, Sector -3, Pushpak NodePIN 410206
Village
Dapoli, Panvel taluka
Land area for this project
288 sq m (3,102 sq ft)
Permissible built-up area
922 sq m (9,926 sq ft)
Sanctioned built-up area
358 sq m (3,852 sq ft)
Designated bank account
212
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No. 127

Land as published on MahaRERA's project page

Plot No.- 127

Boundaries

North
9 Mtr Wide Road
South
Plot No-138
East
Plot No -128
West
Plot No -126

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking16 units

0 of 16 units booked (0%), as the promoter reported to MahaRERA

1BHK · 8 units2BHK · 8 units
TypeCarpet areaUnitsBooked
1BHK30.79 sq m · 331 sq ft80
2BHK39.74 sq m · 428 sq ft80

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVastuyog Architects—
Chartered accountantR B Singh & Associates—
EngineerRam Marathe—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Dapoli

All 143 projects in Dapoli · Compare Savitri Arcade with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology