Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 33% of its units are booked.

Dapoli, Raigarh 410206 · by Veer Realty

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales33% booked20 of 61 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 4 Dec 2024, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000078304
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P520000783044 Dec 202431 Dec 202630 Apr 2027Veer RealtyProject page
Documents94

1 document held by Deedo, 93 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card- Veer Realty.pdf · uploaded 9 Nov 2024Source

Legal

  • Legal Title reportTitle Report (1)_11zon.pdf · uploaded 9 Nov 2024Source
  • Declaration Form BForm B (3)_11zon.pdf · uploaded 12 Nov 2024Source
  • Other – LegalPartnership deed veer realty new_11zon.pdf · uploaded 22 Nov 2024Source
  • Other – LegalOriginal TP 020524.pdf · uploaded 22 Nov 2024Source
  • Other – Legal081-160_11zon.pdf · uploaded 22 Nov 2024Source
  • Other – Legal001-080_11zon.pdf · uploaded 22 Nov 2024Source
Show all 94 documentsShow fewer documents

Legal

  • Other – LegalAgreement to lease dated 040722-61-117_11zon.pdf · uploaded 22 Nov 2024Source
  • Other – LegalAgreement to lease dated 040722-1-60_11zon.pdf · uploaded 22 Nov 2024Source

Migrated

  • 1 PAN CardPan Card- Veer Realty.pdf · uploaded 9 Nov 2024Source
  • 1 Copy of the legal title reportTitle Report (1)_11zon.pdf · uploaded 9 Nov 2024Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Letter-Finance.pdf · uploaded 9 Nov 2024Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Letter- Legal.pdf · uploaded 9 Nov 2024Source
  • 1 Proforma of Allotment letterRERA Allotment-shailesh-Veer Realty.pdf · uploaded 9 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Architect_11zon.pdf · uploaded 9 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_11zon.pdf · uploaded 9 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC CERTIFICATE.pdf · uploaded 9 Nov 2024Source
  • 1 CERSAI detailsCersai Declaration.pdf · uploaded 9 Nov 2024Source
  • 1 Deviation Report with respect to Allotment letterGetUserDocumentFileContent (1).pdf · uploaded 9 Nov 2024Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Letter-Finance.pdf · uploaded 9 Nov 2024Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Letter- Legal.pdf · uploaded 9 Nov 2024Source
  • 1 Other – Technical1 Other – Technical (70).pdf · uploaded 9 Nov 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation AFS (1)_11zon (1).pdf · uploaded 9 Nov 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure a merged_11zon (2).pdf · uploaded 9 Nov 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDiscloser for Secured unsecured loan.pdf · uploaded 9 Nov 2024Source
  • 1 Copy of Layout Approval (in case of layout)CC Drawinggggg.pdf · uploaded 11 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (12)_11zon.pdf · uploaded 11 Nov 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentCC Drawinggggg.pdf · uploaded 11 Nov 2024Source
  • 1 Declaration about Commencement CertificateFormat D (2).pdf · uploaded 11 Nov 2024Source
  • 1 Declaration in FORM BForm B (3)_11zon.pdf · uploaded 12 Nov 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A (3)_11zon.pdf · uploaded 12 Nov 2024Source
  • 1 Proforma of Agreement for saleAFS_Krishna Veer_Veer Realty_21112024 (1).pdf · uploaded 12 Nov 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B (2)_11zon.pdf · uploaded 12 Nov 2024Source
  • 3 Other – Legal001-080_11zon.pdf · uploaded 22 Nov 2024Source
  • 1 Other – LegalAgreement to lease dated 040722-1-60_11zon.pdf · uploaded 22 Nov 2024Source
  • 2 Other – LegalAgreement to lease dated 040722-61-117_11zon.pdf · uploaded 22 Nov 2024Source
  • 4 Other – Legal081-160_11zon.pdf · uploaded 22 Nov 2024Source
  • 5 Other – LegalOriginal TP 020524.pdf · uploaded 22 Nov 2024Source
  • 6 Other – LegalPartnership deed veer realty new_11zon.pdf · uploaded 22 Nov 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC Verification Mail- Krishna Veer-cropped.pdf · uploaded 25 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Krishna Veer as on December 2024.pdf · uploaded 6 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Krishna Veer as on Dec 2024.pdf · uploaded 15 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Krishna Veer as on Dec 2024 (SIGNED)_11zon.pdf · uploaded 15 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Krishna Veer as on Dec 2024.pdf · uploaded 15 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Krishna Veer as on Dec 2024 (SIGNED)_11zon.pdf · uploaded 15 Jan 2025Source
  • 1 Copy of Layout Approval (in case of layout)Plan - Krishna Veer 1.pdf · uploaded 2 Apr 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC - Krishna Veer.pdf · uploaded 2 Apr 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan - Krishna Veer 2.pdf · uploaded 2 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Krishna Veer as on March 2025.pdf · uploaded 3 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Krishna Veer as on March 2025.pdf · uploaded 5 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Krishna Veer as on March 2025.pdf · uploaded 5 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySold unsold Krishna Veer_compressed.pdf · uploaded 16 Apr 2025Source
  • Withdrawal Update Form 1Form 1 - Krishna Veer as on June 2025.pdf · uploaded 29 Jul 2025Source
  • Withdrawal Update Form 2Form 2 - Krishna Veer as on June 2025.pdf · uploaded 29 Jul 2025Source
  • Withdrawal Update Form 3Form 3 of Krishna Veer as on 30-06-2025.pdf · uploaded 29 Jul 2025Source
  • Withdrawal Update Form 1Form 1 - June 2025.pdf · uploaded 8 Sep 2025Source
  • Withdrawal Update Form 2Form 2 - Jun 2025_.pdf · uploaded 8 Sep 2025Source
  • Withdrawal Update Form 3Form 3 - Jun 2025_.pdf · uploaded 8 Sep 2025Source
  • Withdrawal Update Form 1Form 1 - Krishna Veer as on Sep 2025.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 2Form 2 - Krishna Veer as on Sep 2025.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 3Form 3 of Krishna Veer as on Sep 2025.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 1Form 1 - Krishna Veer as on Dec 2025.pdf · uploaded 6 Jan 2026Source
  • Withdrawal Update Form 2Form 2 - Krishna Veer as on Dec 2025.pdf · uploaded 6 Jan 2026Source
  • Withdrawal Update Form 3Form 3 - Krishna Veer as on Dec 2025.pdf · uploaded 6 Jan 2026Source
  • Form 5 (FY 2024-2025)Form 5 - Krishna Veer as on FY 24-25.pdf · uploaded 27 Feb 2026Source
  • Withdrawal Update Form 1Form 1 - Krishna Veer as on March 2026.pdf · uploaded 15 Apr 2026Source
  • Withdrawal Update Form 2Form 2 - Krishna Veer as on March 2026.pdf · uploaded 15 Apr 2026Source
  • Withdrawal Update Form 3Form 3 - Krishna Veer as on March 2026.pdf · uploaded 15 Apr 2026Source
  • Withdrawal Update Form 1Form 1 - Krishna Veer as on June 2026.pdf · uploaded 10 Jul 2026Source
  • Withdrawal Update Form 1Form 1 - Krishna Veer as on June 2026.pdf · uploaded 10 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Krishna Veer as on June 2026.pdf · uploaded 10 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Krishna Veer as on June 2026.pdf · uploaded 10 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Krishna Veer as on June 2026.pdf · uploaded 10 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Krishna Veer as on June 2026.pdf · uploaded 10 Jul 2026Source
  • Withdrawal Update Form 1Form 1 - Krishna Veer Sep 2026.pdf · uploaded 10 Oct 2026Source
  • Withdrawal Update Form 1Form 1 - Krishna Veer Sep 2026.pdf · uploaded 10 Oct 2026Source
  • Withdrawal Update Form 2Form 2 - Krishna Veer Sep 2026.pdf · uploaded 10 Oct 2026Source
  • Withdrawal Update Form 2Form 2 - Krishna Veer Sep 2026.pdf · uploaded 10 Oct 2026Source
  • Withdrawal Update Form 3Form 3 - Krishna Veer Sep 2026.pdf · uploaded 10 Oct 2026Source
  • Withdrawal Update Form 3Form 3 - Krishna Veer Sep 2026.pdf · uploaded 10 Oct 2026Source

Technical

  • Other – Technical1 Other – Technical (70).pdf · uploaded 9 Nov 2024Source
  • DocumentCC Drawinggggg.pdf · uploaded 11 Nov 2024Source
  • DocumentCC Drawinggggg.pdf · uploaded 11 Nov 2024Source
  • DocumentPlan - Krishna Veer 1.pdf · uploaded 2 Apr 2025Source
  • DocumentPlan - Krishna Veer 2.pdf · uploaded 2 Apr 2025Source
  • DocumentPlan - Krishna Veer 1 - Highlighted.pdf · uploaded 1 Jul 2025Source

Technical (Architect)

  • DocumentForm 1 - Krishna Veer as on December 2024.pdf · uploaded 6 Jan 2025Source
  • DocumentForm 1 - Krishna Veer as on March 2025.pdf · uploaded 3 Apr 2025Source
  • DocumentForm 1 - Krishna Veer Sep 2026.pdf · uploaded 10 Oct 2026Source

Technical (Engineer)

  • DocumentForm 2 - Krishna Veer as on Dec 2024.pdf · uploaded 15 Jan 2025Source
  • DocumentForm 2 - Krishna Veer as on Dec 2024 (SIGNED)_11zon.pdf · uploaded 15 Jan 2025Source
  • DocumentForm 2 - Krishna Veer as on March 2025.pdf · uploaded 5 Apr 2025Source
  • DocumentForm 2 - Krishna Veer Sep 2026.pdf · uploaded 10 Oct 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No- 81, Sector- 07

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, Shop61 units in all
Address
Plot No- 81, Sector- 07, Sector- 07, PushpakPIN 410206
Village
Dapoli, Panvel taluka
Land area for this project
709 sq m (7,632 sq ft)
Permissible built-up area
2,851 sq m (30,689 sq ft)
Sanctioned built-up area
2,847 sq m (30,645 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
105
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No- 81Sector- 07

Land as published on MahaRERA's project page

Plot No- 81, Sector- 07

Boundaries

North
Plot No- 86 and 87
South
15 Mtr Wide Road
East
Plot No- 80
West
Plot No- 82

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking61 units

20 of 61 units booked (33%), as the promoter reported to MahaRERA

1BHK · 56 unitsShop · 5 units
TypeCarpet areaUnitsBooked
1BHK24.5 sq m · 264 sq ft20
1BHK24.83 sq m · 267 sq ft21
1BHK25.68 sq m · 276 sq ft41
1BHK27.5 sq m · 296 sq ft105
1BHK28.11 sq m · 303 sq ft104
1BHK28.83 sq m · 310 sq ft121
1BHK30.49 sq m · 328 sq ft20
1BHK48.82 sq m · 525 sq ft145
Show all 11 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop19.08 sq m · 205 sq ft10
Shop26.24 sq m · 282 sq ft22
Shop27.65 sq m · 298 sq ft21

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Other projects in Dapoli

All 143 projects in Dapoli · Compare Krishna Veer with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology