Residential / Group Housing · 4 buildings · 69 unitsRERA PR1270002500197

Krishna Nagari

Deedo IDDP-RAI-SPSC

Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 39% of its units are booked.

Dapoli, Raigarh 410206 · by Radhe Krishna Developers

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales39% booked27 of 69 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 3 Jul 2025, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1270002500197
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR12700025001973 Jul 202531 Dec 202830 Apr 2029Radhe Krishna DevelopersProject page
Documents38

1 document held by Deedo, 37 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Card12 PAN Radhe Krishna Developers.pdf · uploaded 24 May 2025Source
  • Others15 cersai.pdf · uploaded 12 Jun 2025Source
  • Others17 sold unsold.pdf · uploaded 12 Jun 2025Source
  • Others19 Land Declaration.pdf · uploaded 12 Jun 2025Source
  • Others1 Financial Encumbrances.pdf · uploaded 23 Jun 2025Source

Legal

  • Declaration Form BTitle Search - RKD final.pdf · uploaded 24 May 2025Source
  • Declaration Form BForm B - Promoter Final.pdf · uploaded 24 May 2025Source
Show all 38 documentsShow fewer documents

Legal

  • Declaration Form B4 Tripartite Agreement_11zon.pdf · uploaded 24 May 2025Source
  • Othersother real JVB.pdf · uploaded 12 Jun 2025Source
  • Othersother real NPN.pdf · uploaded 12 Jun 2025Source
  • Othersother real SBP.pdf · uploaded 12 Jun 2025Source
  • Others13 Legal Encumbrances.pdf · uploaded 12 Jun 2025Source
  • Others4 lease deed_11zon.pdf · uploaded 24 Jun 2025Source

Migrated

  • Withdrawal Update Form 1FORM 1.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 3Form3 Q2 25-26 for upload.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 3Form3 Q2 25-26 for upload.pdf · uploaded 4 Nov 2025Source
  • Withdrawal Update Form 1Form 1- 49-8-PUSHPAK RERA.pdf · uploaded 22 Jan 2026Source
  • Withdrawal Update Form 2Form 2 - RKD.pdf · uploaded 22 Jan 2026Source
  • Withdrawal Update Form 3Form3 FY 25-26 Q3.pdf · uploaded 22 Jan 2026Source
  • Form 2A (FY 2025-2026)Form 2A - RKD.pdf · uploaded 5 May 2026Source
  • Withdrawal Update Form 1Form 1 signed.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 2RERA FORM 2_31ST MARCH 2026.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 3Form3 CA Certificate FY 25-26 Q4 to upload.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 1Form 1 49-8-PUSHPAK RERA.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 2Form 2 RKD signed.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 3Form3 FY 26-27 Q1signed.pdf · uploaded 17 Jul 2026Source
  • Form 5 (FY 2025-2026)Form 5 - Radhe Krishna Developers signed.pdf · uploaded 26 Sep 2026Source

Technical

  • Others17 sold unsold.pdf · uploaded 31 May 2025Source
  • Document2 CC DRG.pdf · uploaded 12 Jun 2025Source
  • Others14 declaration about CC.pdf · uploaded 12 Jun 2025Source
  • Others21 CC Verification email RKD.pdf · uploaded 12 Jun 2025Source
  • Document3 Annexure A.pdf · uploaded 23 Jun 2025Source

Technical (Architect)

  • DocumentForm 1 49-8-PUSHPAK RERA.pdf · uploaded 17 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2 RKD signed.pdf · uploaded 17 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot number 49, sector 8

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—70 units in all
Address
plot 49, sector 8, Pushpak Node, Dapoli, PanvelPIN 410206
Village
Dapoli, Panvel taluka
Land area for this project
780 sq m (8,392 sq ft)
Permissible built-up area
2,801 sq m (30,154 sq ft)
Sanctioned built-up area
2,801 sq m (30,154 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
109
Developed in phases
Yes

Survey, CTS, gat or plot numbers

Plot number 49sector 8

Land as published on MahaRERA's project page

Plot number 49, sector 8, Pushpak Node, Dapoli, Panvel

Boundaries

North
Plot No. 48
South
Plot No. 50
East
Plot No. 55 & 56
West
11 Mtr Wide road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking70 units

70 units registered

— · 70 units
BuildingTypeCarpet areaUnits
Wing A——42
Wing B——28

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAtul Patel—
Chartered accountantAshok Upadhye—
Chartered accountantDeepesh Ashwin Shah—
EngineerBharatkumar Bhavan Patel—
EngineerRadhika Choudhary—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Dapoli

All 143 projects in Dapoli · Compare Krishna Nagari with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology