Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 49% of its units are booked.

Dapoli, Raigarh 410206 · by Dhriti Home Makers LLP

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales49% booked44 of 90 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 19 Nov 2025, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1270002501517
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM127000250151719 Nov 202531 Dec 202830 Apr 2029M/s. DHRITI HOME MAKERS LLPProject page
Documents28

1 document held by Deedo, 27 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD COMPANY.pdf · uploaded 18 Sep 2025Source
  • OthersPromoter's Declaration.pdf · uploaded 24 Oct 2025Source
  • Othersletter Form 3 clartification and Agreemnet of assigment.pdf · uploaded 3 Nov 2025Source

Legal

  • Declaration Form BLegal Title Report_F.pdf · uploaded 16 Sep 2025Source
  • Declaration Form BAGREEMENT TO LEASE_F.pdf · uploaded 16 Sep 2025Source
  • Declaration Form BForm b final.pdf · uploaded 24 Sep 2025Source
  • OthersPLOT 82 SEC 8 PUSHPAK TRIPARTITE AGREEMENT.pdf · uploaded 1 Oct 2025Source
Show all 28 documentsShow fewer documents

Legal

  • OthersPatnership deed.pdf · uploaded 1 Oct 2025Source
  • OthersAnnexure-A.pdf · uploaded 1 Oct 2025Source
  • OthersDisclosure.pdf · uploaded 1 Oct 2025Source

Migrated

  • Withdrawal Update Form 1Form1 Q3 25-26.pdf · uploaded 6 Feb 2026Source
  • Withdrawal Update Form 2Form2 Q3 25-26.pdf · uploaded 6 Feb 2026Source
  • Withdrawal Update Form 3Form3 Q3 25-26.pdf · uploaded 6 Feb 2026Source
  • Withdrawal Update Form 1Form 1 2025-2026 Q4.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 2Form 2 2025-2026 Q4.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 3Form 3 2025-2026 Q4.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 1Form 1 26-27 Q1.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2Form 2 Q1 26-27.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3Form 3 26-27 Q1.pdf · uploaded 20 Jul 2026Source

Technical

  • DocumentNA Order for Plotted Development.pdf · uploaded 16 Sep 2025Source
  • OthersFORM 1 s.pdf · uploaded 18 Sep 2025Source
  • OthersForm 2 RERA Plot 82 Sector 08 Pushpak Dapoli s.pdf · uploaded 18 Sep 2025Source
  • Documentlayout-1.pdf · uploaded 23 Sep 2025Source
  • Documentlayout-2.pdf · uploaded 23 Sep 2025Source
  • DocumentAnnexure A.pdf · uploaded 10 Oct 2025Source

Technical (Architect)

  • DocumentForm 1 26-27 Q1.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2 Q1 26-27.pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO-82, SECTOR-08

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—90 units in all
Address
Sector-08, Pushpak NodePIN 410206
Village
Dapoli, Panvel taluka
Land area for this project
919 sq m (9,896 sq ft)
Permissible built-up area
3,689 sq m (39,712 sq ft)
Sanctioned built-up area
3,689 sq m (39,712 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
109
Developed in phases
Yes

Survey, CTS, gat or plot numbers

PLOT NO-82SECTOR-08

Land as published on MahaRERA's project page

PLOT NO-82, SECTOR-08, PUSHPAK NODE, PANVEL, RAIGARH-410206

Boundaries

North
Plot No-83
South
Plot No-81
East
15 Mtr. Wide Road
West
Plot No-80

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking90 units

90 units registered

— · 90 units
BuildingTypeCarpet areaUnits
A-Wing——48
B-Wing——42

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAtul Patel—
EngineerSubramanya Rao—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Dapoli

All 143 projects in Dapoli · Compare Dhriti Aura with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology