Sudarshan
Deedo IDDP-RAI-NKG4Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 17% of its units are booked.
Bokadvira, Raigarh 400702 · by Preetam Chandrahas Gupta
Buying a flat here?
See every deed registered on it.
Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 8 Dec 2022, completion promised 30 Dec 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000048064
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000048064 | 8 Dec 2022 | 30 Dec 2025 | 30 Dec 2025 | preetam chandrahas gupta | Project page |
Documents49
1 document held by Deedo, 48 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card.pdf · uploaded 27 Jun 2022Source
Legal
Migrated
- 1 PAN Cardpan card.pdf · uploaded 27 Jun 2022Source
- 1 Copy of Layout Approval (in case of layout)CC Drawing_compressed (2).pdf · uploaded 27 Jun 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentCC Drawing_compressed (2).pdf · uploaded 27 Jun 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCC Letter_compressed.pdf · uploaded 27 Jun 2022Source
Show all 49 documentsShow fewer documents
Migrated
- 1 Deviation Report with respect to Allotment letterdeviation-allotment (1).pdf · uploaded 2 Aug 2022Source
- 1 Declaration about Commencement Certificatedeclaration about comm cert (2).pdf · uploaded 7 Nov 2022Source
- 1 Proforma of Allotment letterALLOTMENT DRAFT NEW (2).pdf · uploaded 7 Nov 2022Source
- 1 Deviation Report with respect to model copy of Agreementdeviation-draft sale (1).pdf · uploaded 7 Nov 2022Source
- 1 Copy of the legal title reportTITLE REPORT 1.pdf · uploaded 9 Nov 2022Source
- 1 a Details of encumbrances concerned to FinanceNo Emcurmbrances Legal and Finance.pdf · uploaded 10 Nov 2022Source
- 1 b Details of encumbrances concerned to LegalNo Emcurmbrances Legal and Finance.pdf · uploaded 10 Nov 2022Source
- 1 Declaration in FORM BFORM B NEW.pdf · uploaded 10 Nov 2022Source
- 1 CERSAI detailsCERSAI Search Report.pdf · uploaded 10 Nov 2022Source
- 1 Proforma of Agreement for saleAFS.pdf · uploaded 10 Nov 2022Source
- 2 a Details of encumbrances concerned to FinanceNO EMCRUMBRANCES FINANCE NEW 17-11-2022.pdf · uploaded 17 Nov 2022Source
- 2 b Details of encumbrances concerned to LegalNO EMCRUMBRANCES FINANCE NEW 17-11-2022.pdf · uploaded 17 Nov 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK ACCOUNT DECL NEW.pdf · uploaded 17 Nov 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 NEW.pdf · uploaded 19 Nov 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - converted.pdf · uploaded 20 Feb 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - converted.pdf · uploaded 20 Feb 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - converted.pdf · uploaded 20 Feb 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - converted.pdf · uploaded 20 Feb 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - converted.pdf · uploaded 20 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Feb 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Feb 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - converted.pdf · uploaded 20 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - converted.pdf · uploaded 20 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - converted.pdf · uploaded 20 Feb 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - converted.pdf · uploaded 20 Feb 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - converted.pdf · uploaded 20 Feb 2025Source
Technical
Technical (Architect)
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel PLOT NO 82 SECTOR 59
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK6 units in all
- Address
- Plot No 82 Sector 59, Plot 82 Sector 59, DronagiriPIN 400702
- Village
- Bokadvira, Uran taluka
- Land area for this project
- 350 sq m (3,765 sq ft)
- Permissible built-up area
- 385 sq m (4,141 sq ft)
- Sanctioned built-up area
- 385 sq m (4,141 sq ft)
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
PLOT NO 82 SECTOR 59
Boundaries
- North
- Plot 81
- South
- Plot 75
- East
- 9 M Road Plot 83
- West
- Plot 77
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking6 units
1 of 6 units booked (17%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 36.8 sq m · 396 sq ft | 4 | 1 |
| 2BHK | 50 sq m · 538 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | S K Associates | — |
| Chartered accountant | Ca Devyani Shejwal | — |
| Engineer | B S Sukhthankar | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Bokadvira
- Hari Om MangalamRERA PR1270002501291
- Ashtavinayak Co op Hsg Society LtdRERA PM1270002501169
- Villa UptownRERA PM1270002500494
- Sky LarkRERA P52000080870
- Shagun Avenue 7RERA PM1270002500284
- Vaishali HeightsRERA PM1270002500191
- Shiv OnenessRERA P52000080640
- Surana ResidencyRERA PR1270002500080
All 114 projects in Bokadvira · Compare Sudarshan with another project