Completion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 57% of its units are booked.

Bhokarpada, Raigarh 410221 · by Persipina Developers Private Limited · 100% of its projects kept the RERA date

DeliveryExtended 4 moPromised Dec 2029 · now due Apr 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales57% booked17 of 30 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2030

  • This projectRegistered 2 Feb 2024, completion promised 31 Dec 2029, revised to 30 Apr 2030.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000054616
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P520000546162 Feb 202431 Dec 202930 Apr 2030Persipina Developers Private LimitedProject page
Documents111

1 document held by Deedo, 110 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card PDPL.pdf · uploaded 25 Jan 2024Source

Legal

  • Legal Title reportTitle RZ 02 24_1_2 16 Nov 2023 Rev.pdf · uploaded 25 Jan 2024Source
  • Declaration Form BAffadivat Form B MARIGOLD.pdf · uploaded 29 Jan 2024Source
  • Other – Legal24-1-2 RZ 02.pdf · uploaded 31 Jan 2024Source
  • Other – LegalBOARD RESOLUTION PDPL 5TH DEC 2023.pdf · uploaded 31 Jan 2024Source

Migrated

  • 1 PAN CardPAN Card PDPL.pdf · uploaded 25 Jan 2024Source
  • 1 Copy of the legal title reportTitle RZ 02 24_1_2 16 Nov 2023 Rev.pdf · uploaded 25 Jan 2024Source
Show all 111 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentRZ-02 Amended CC 25-01-2024.pdf · uploaded 25 Jan 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC CER MARIGOLD.pdf · uploaded 25 Jan 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Cert MARIGOLD.pdf · uploaded 25 Jan 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT A MARIGOLD separate account.pdf · uploaded 25 Jan 2024Source
  • 1 Other – TechnicalGolden willows_Development plan layout_23-01-2024.pdf · uploaded 25 Jan 2024Source
  • 1 Copy of Layout Approval (in case of layout)BUILDING FOOTPRINT AND PARKING DEMARCATION.pdf · uploaded 27 Jan 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentTYPICAL AND REFUGE FLOOR PLAN BUILT UP AREA DEMARCATION.pdf · uploaded 27 Jan 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentSTILT OVERALL LAYOUT.pdf · uploaded 27 Jan 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentPODIUM 2 TERRACE FLOOR PLAN BLDG FOOTPRINT.pdf · uploaded 27 Jan 2024Source
  • 4 Building Plan Approval / NA Order for plotted developmentGROUND PODIUM1 FLOOR PLAN BLDG FOOTPRINT.pdf · uploaded 27 Jan 2024Source
  • 5 Building Plan Approval / NA Order for plotted developmentP1 OVERALL LAYOUT.pdf · uploaded 27 Jan 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentSECTIONS.pdf · uploaded 27 Jan 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentP2 OVERALL LAYOUT.pdf · uploaded 27 Jan 2024Source
  • 1 a Details of encumbrances concerned to FinanceMarigold finanace final.pdf · uploaded 28 Jan 2024Source
  • 2 a Details of encumbrances concerned to FinanceLegal marigold final.pdf · uploaded 28 Jan 2024Source
  • 1 b Details of encumbrances concerned to LegalMarigold finanace final.pdf · uploaded 28 Jan 2024Source
  • 2 b Details of encumbrances concerned to LegalLegal marigold final.pdf · uploaded 28 Jan 2024Source
  • 1 Declaration in FORM BAffadivat Form B MARIGOLD.pdf · uploaded 29 Jan 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)MARIGOLD CERTIFICATE.pdf · uploaded 30 Jan 2024Source
  • 1 Declaration about Commencement CertificateFORMAT D MARIGOLD.pdf · uploaded 31 Jan 2024Source
  • 1 Proforma of Allotment letterAllotment Letter on Letter Head PDPL 310124.pdf · uploaded 31 Jan 2024Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION REPORT OF ALLOTMENT LETTER 31-1-24.pdf · uploaded 31 Jan 2024Source
  • 1 Other – LegalBOARD RESOLUTION PDPL 5TH DEC 2023.pdf · uploaded 31 Jan 2024Source
  • 2 Other – Legal24-1-2 RZ 02.pdf · uploaded 31 Jan 2024Source
  • 2 Other – TechnicalPLOT DECLARATION - MARIGOLD.pdf · uploaded 31 Jan 2024Source
  • 3 Other – TechnicalDECLARATION MARIGOLD.pdf · uploaded 31 Jan 2024Source
  • 1 CERSAI detailsCERSAI DECLARATION MARIGOLD.pdf · uploaded 1 Feb 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Niranjan Hiranandani.pdf · uploaded 1 Feb 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Kamal Hiranandani.pdf · uploaded 1 Feb 2024Source
  • 1 Proforma of Agreement for saleMarigold - Draft Agreement - 31-01-2023.pdf · uploaded 1 Feb 2024Source
  • 1 Deviation Report with respect to model copy of AgreementMarigold Agreement.pdf · uploaded 1 Feb 2024Source
  • 2 Deviation Report with respect to model copy of AgreementMarigold Allotment letter Deveation Report.pdf · uploaded 1 Feb 2024Source
  • 2 Copy of Layout Approval (in case of layout)2 Copy of Layout Approval in case of layout.pdf · uploaded 2 Feb 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC CER MARIGOLD.pdf · uploaded 17 Apr 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA Engg CERTIFICATE - MARIGOLD.pdf · uploaded 17 Apr 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Quality Assurance Certificate -MARIGOLD BLDG.pdf · uploaded 17 Apr 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Marigold FORM 3 Certificate Mar 2024.pdf · uploaded 17 Apr 2024Source
  • 1 Disclosure of sold/ booked inventoryDISCOLSURE LAVENDER.pdf · uploaded 19 Apr 2024Source
  • 2 CERSAI detailsDISCOLSURE MARIGOLD.pdf · uploaded 19 Apr 2024Source
  • 2 Disclosure of sold/ booked inventoryDISCOLSURE MARIGOLD.pdf · uploaded 19 Apr 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDISCOLSURE MARIGOLD.pdf · uploaded 19 Apr 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT CERT - MARIGOLD.pdf · uploaded 18 Jul 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA Certificate - MARIGOLD.pdf · uploaded 18 Jul 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CER MARIGOLD.pdf · uploaded 18 Jul 2024Source
  • 3 Disclosure of sold/ booked inventoryMarigold -.pdf · uploaded 19 Jul 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC-CER MARIGOLD.pdf · uploaded 18 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA-CER MARIGOLD.pdf · uploaded 18 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA Engg Certificate - Marigold.pdf · uploaded 18 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryDISCOLSURE - MARIGOLD.pdf · uploaded 18 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Mar 2024 Marigold.pdf · uploaded 7 Nov 2024Source
  • 1 Deviation Report with respect to model copy of AgreementMARIGOLD DEVEIATION REPORT.pdf · uploaded 22 Nov 2024Source
  • 1 Proforma of Agreement for saleMarigold - Draft Agreement.pdf · uploaded 22 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC CER MAYFLOWER.pdf · uploaded 15 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC CER MARIGOLD.pdf · uploaded 15 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CER MARIGOLD.pdf · uploaded 15 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Cert MARIGOLD.pdf · uploaded 15 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryDISCOLSURE MARIGOLD.pdf · uploaded 15 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Marigold CA Cer.pdf · uploaded 8 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC -CER MARIGOLD.pdf · uploaded 16 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)MARIGOLD-Form 3.pdf · uploaded 16 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA Certificate - Eng Marigold.pdf · uploaded 16 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryMarigold.pdf · uploaded 16 Apr 2025Source
  • Form 1FORM 1 ARCHITECT MARIGOLD.pdf · uploaded 18 Jul 2025Source
  • Form 2FORM 2 ENG CERTIFICATE MARIGOLD.pdf · uploaded 18 Jul 2025Source
  • Form 3CA CER MARIGOLD.pdf · uploaded 18 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDISCOLSURE SOLD BOOKED MARIGOLD.pdf · uploaded 18 Jul 2025Source
  • Form 11 FORM ARC CERT MARIGOLD.pdf · uploaded 19 Oct 2025Source
  • Form 2Form 2 RERA Cert Marigold.pdf · uploaded 19 Oct 2025Source
  • Form 3Form 3 CA CER MARIGOLD.pdf · uploaded 19 Oct 2025Source
  • Disclosure of Sold and Booked InventoryDISCOLSURE MARIGOLD.pdf · uploaded 19 Oct 2025Source
  • Form 1Form 1 Arch Cer - Marigold.pdf · uploaded 9 Jan 2026Source
  • Form 2Form 2 Eng Cer - Marigold.pdf · uploaded 9 Jan 2026Source
  • Form 3Form 3 CA CER MARIGOLD.pdf · uploaded 9 Jan 2026Source
  • Disclosure of Sold and Booked InventoryDIS SOLD UNSOLD MARIGOLD.pdf · uploaded 9 Jan 2026Source
  • Form 1ARC CER MARIGOLD.pdf · uploaded 14 Apr 2026Source
  • Form 2ENG CER MARIGOLD.pdf · uploaded 14 Apr 2026Source
  • Form 3Form-3 Marigold Mar 2026.pdf · uploaded 14 Apr 2026Source
  • Disclosure of Sold and Booked InventoryDISCOLSURE MARIGOLD.pdf · uploaded 14 Apr 2026Source
  • Form 1FORM 1 ARCHITECT CERT MARIGOLD.pdf · uploaded 16 Jul 2026Source
  • Form 2Form 2 Eng Certi Marigold.pdf · uploaded 16 Jul 2026Source
  • Form 3FORM 3 CA CER MARIGOLD.pdf · uploaded 16 Jul 2026Source
  • Disclosure of Sold and Booked InventoryDisclosed of Sold and Unsold MARIGOLD.pdf · uploaded 16 Jul 2026Source

Technical

  • Other – TechnicalGolden willows_Development plan layout_23-01-2024.pdf · uploaded 25 Jan 2024Source
  • DocumentBUILDING FOOTPRINT AND PARKING DEMARCATION.pdf · uploaded 27 Jan 2024Source
  • DocumentTYPICAL AND REFUGE FLOOR PLAN BUILT UP AREA DEMARCATION.pdf · uploaded 27 Jan 2024Source
  • DocumentSTILT OVERALL LAYOUT.pdf · uploaded 27 Jan 2024Source
  • DocumentPODIUM 2 TERRACE FLOOR PLAN BLDG FOOTPRINT.pdf · uploaded 27 Jan 2024Source
  • DocumentGROUND PODIUM1 FLOOR PLAN BLDG FOOTPRINT.pdf · uploaded 27 Jan 2024Source
  • DocumentP1 OVERALL LAYOUT.pdf · uploaded 27 Jan 2024Source
  • DocumentSECTIONS.pdf · uploaded 27 Jan 2024Source
  • DocumentP2 OVERALL LAYOUT.pdf · uploaded 27 Jan 2024Source
  • Other – TechnicalPLOT DECLARATION - MARIGOLD.pdf · uploaded 31 Jan 2024Source
  • Other – TechnicalDECLARATION MARIGOLD.pdf · uploaded 31 Jan 2024Source
  • Document2 Copy of Layout Approval in case of layout.pdf · uploaded 2 Feb 2024Source

Technical (Architect)

  • DocumentFORM 1 ARCHITECT CERT - MARIGOLD.pdf · uploaded 18 Jul 2024Source
  • DocumentARC-CER MARIGOLD.pdf · uploaded 18 Oct 2024Source
  • DocumentARC CER MAYFLOWER.pdf · uploaded 15 Jan 2025Source
  • DocumentARC CER MARIGOLD.pdf · uploaded 15 Jan 2025Source
  • DocumentARC -CER MARIGOLD.pdf · uploaded 16 Apr 2025Source

Technical (Engineer)

  • DocumentRERA Certificate - MARIGOLD.pdf · uploaded 18 Jul 2024Source
  • DocumentRERA Engg Certificate - Marigold.pdf · uploaded 18 Oct 2024Source
  • DocumentEng Cert MARIGOLD.pdf · uploaded 15 Jan 2025Source
  • DocumentRERA Certificate - Eng Marigold.pdf · uploaded 16 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 58/1B (Part), 59 (Part)

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—30 units in all
Address
RZ-02, Gut no. 24/1/2 (Old Survey no. 58/1A (Part), 58/1B (Part), 59 (Part), 60/1 (Part), 60/2 (Part), 60/3, 60/4 (Part), 61/2 (Part), & 62/1 (Part), Old Mumbai Pune Highway, Village BhokarpadaPIN 410221
Village
Bhokarpada, Panvel taluka
Land area for this project
739 sq m (7,955 sq ft)
Permissible built-up area
24,766 sq m (2,66,580 sq ft)
Sanctioned built-up area
24,766 sq m (2,66,580 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

58/1B (Part)59 (Part)60/1 (Part)60/2 (Part)60/360/4 (Part)61/2 (Part)62/1 (Part)Gut no. 24/1/2 (Old Survey no. 58/1A (Part)RZ02

Land as published on MahaRERA's project page

RZ-02, Gut no. 24/1/2 (Old Survey no. 58/1A (Part), 58/1B (Part), 59 (Part), 60/1 (Part), 60/2 (Part),60/3, 60/4 (Part), 61/2 (Part), & 62/1 (Part)

Boundaries

North
Mayflower Builiding
South
Future Development
East
Internal Driveway
West
Lavender Building

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking30 units

30 units registered

— · 30 units
TypeCarpet areaUnits
——30

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals18

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGunisha Sanyal—
ArchitectGunisha Sethi Sanyal—
Chartered accountantArun P Vaz & Co—
Chartered accountantArun Vaz—
Chartered accountantManoj O. Shah & CO.—
Chartered accountantManoj O. Shah & CO. Shah—
Chartered accountantManoj Shah—
Chartered accountantRakesh Shah and Associates—
Show all 18 professionalsShow fewer professionals
RoleNameRegistration no.
EngineerPrashanth Nandulamattam—
Registered real estate agentAnmol Balaji Broking—
Registered real estate agentAshok Khetshi Shah—
Registered real estate agentHome Bazaar Services Pvt Ltd—
Registered real estate agentJasvinder Singh Lamba—
Registered real estate agentKapil Ramsharan Arora—
Registered real estate agentmadhusudanan muthodi puthankalam—
Registered real estate agentNitesh Jaikishan Changani—
Registered real estate agentPropertypistol Realty Private Limited—
Registered real estate agentVipinkumar Baburao Chavan—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology