Ashtami, Raigarh
No MahaRERA registration here has an extended completion date on record.
RERA projects2
Registrations2
Completion still due11 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases0none on MahaRERA's lists
5 in 10 registrations run late here
2 MahaRERA registrations in Ashtami
1 not yet due1 past even the latest date
Projects in Ashtami
2 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Om ResidencyRajkumar Trimbak Karad | Due Mar 2029 | — | 83% |
| Mariyam ApartmentKhalid Abdul Kadir Beban | 3 yrs 10 mo late | — | 0% |
Nearby: other localities in Roha
Most active promoters
- Khalid Abdul Kadir Beban1 project
- Rajkumar Trimbak Karad1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology