RERA projects in Nagothane
11 projects under 11 MahaRERA registrations, registered 2017–2026. 73% have a completion date extended beyond the one promised.
Locality
11RERA projects
11Registrations
10Completion still due1 past their completion date
4 monthsMedian extension beyond promised date73% of registrations extended
0Regulatory casesnone on MahaRERA's lists
29Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 1 |
| 2023 | 0 |
| 2024 | 4 |
| 2025 | 2 |
| 2026 | 2 |
Projects in Nagothane
11 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vijayshree ApartmentRitesh Futarmal Doshi | PM1270002601733 | 1 Sep 2026 | 30 Sep 2027 | 30 Sep 2027 | Not yet due | 0 |
| Navkar DarshanPadmavati Builders And Developers | PM1270002503050 | 27 Mar 2026 | 31 Dec 2032 | 31 Dec 2032 | Not yet due | 0 |
| Shree Sadguru Krupa Mandavkar ComplexShree Ratnadeep Developers | PM1270002501891 | 26 Dec 2025 | 30 Jun 2027 | 30 Oct 2027 | Extended 4 mo | 0 |
| Om Sneh Prabha ComplexSanjay Ramchandra Dalavi | P52000078899 | 20 Jan 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Om ComplexSanjay Ramchandra Dalavi | P52000076814 | 28 Jun 2024 | 20 Feb 2029 | 20 Jun 2029 | Extended 4 mo | 0 |
| Bhide ResidencyGopikrishna Constrcution | P52000076740 | 25 Jun 2024 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Zuha ParkJaleel Ahmad Patel | P52000055926 | 29 Apr 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Man Saroj PlazaNilesh Mangilal Jain | P52000054278 | 15 Jan 2024 | 30 Jun 2027 | 30 Oct 2027 | Extended 4 mo | 0 |
| Amba ResidencyN R Builders And Developers | P52000032513 | 10 Jan 2022 | 31 Dec 2028 | 31 Dec 2028 | Not yet due | 0 |
| Shubh Laxmi Appartment Bld A Phase 1Shree Rajendra Developers | P52000027605 | 23 Dec 2020 | 30 Sep 2024 | 27 Sep 2025 | Extended 12 mo | 0 |
| Morya Home TownMorya Infraconstruct Private Limited | P52000007069 | 17 Aug 2017 | 30 Dec 2024 | 31 Dec 2027 | Extended 36 mo | 0 |
Other localities in Roha
Most active promoters
By projects registered here, as named on MahaRERA.
- Sanjay Ramchandra Dalavi2 projects
- Gopikrishna Constrcution1 project
- Jaleel Ahmad Patel1 project
- Morya Infraconstruct Private Limited1 project
- Nilesh Mangilal Jain1 project
- N R Builders And Developers1 project
- Padmavati Builders And Developers1 project
- Ritesh Futarmal Doshi1 project
- Shree Rajendra Developers1 project
- Shree Ratnadeep Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology