Niranjan

Certificate Signed

Adoshi, Raigarh 410203 |Promoter: Niranjan Investments Private Limited

10 Aug 2021Registered with MahaRERA
31 Dec 2026Promised completion
30 Apr 2027Revised completionPushed back 4 months
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Certificate Signed
Address
NI14 NI15, Dasturi Gram Road, AdoshiPIN 410203
Designated bank account
154
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.76008, 73.33181
Niranjan is at latitude 18.76008, longitude 73.33181.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
10 Aug 2021
Promised
31 Dec 2026
Revised
30 Apr 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200003024410 Aug 202131 Dec 202630 Apr 2027Niranjan Investments Private LimitedProject page

Documents

1 document held by Deedo, 79 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card.pdf · uploaded 1 Aug 2021Source

Legal

  • Legal Title reportTC with Letter.pdf · uploaded 1 Aug 2021Source
  • Declaration Form BNiranjan Affidavit Form B.pdf · uploaded 1 Aug 2021Source

Migrated

  • 1 PAN CardPAN Card.pdf · uploaded 1 Aug 2021Source
  • 1 Copy of the legal title reportTC with Letter.pdf · uploaded 1 Aug 2021Source
  • 1 Details of encumbrancesNiranjan Encumbrance (1).pdf · uploaded 1 Aug 2021Source
  • 1 Copy of Layout Approval (in case of layout)Niranjan Self Declaration (1).pdf · uploaded 1 Aug 2021Source
Show all 80 documentsShow fewer documents

Migrated

  • 2 Copy of Layout Approval (in case of layout)Niranajan Investment Layout.pdf · uploaded 1 Aug 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentN A Order.pdf · uploaded 1 Aug 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentN A Order.pdf · uploaded 1 Aug 2021Source
  • 1 Declaration about Commencement CertificateNiranjan Form D (1).pdf · uploaded 1 Aug 2021Source
  • 1 Declaration in FORM BNiranjan Affidavit Form B.pdf · uploaded 1 Aug 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Niranjan 4A Arch Cert.pdf · uploaded 1 Aug 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)EC Niranjan 4A (2).pdf · uploaded 1 Aug 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Niranjan CA Cer.pdf · uploaded 1 Aug 2021Source
  • 1 Proforma of Allotment letterNiranjan_Doc.pdf · uploaded 1 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52000030244 NIRANJAN.pdf · uploaded 6 Jan 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC CER NIRANJAN SEP 202300027320240117154427.pdf · uploaded 17 Jan 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC CER NIRANJAN DECEMBER 2300026120240117144835.pdf · uploaded 17 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG CER NIRANJAN SEPTEMBER 202300026320240117145236.pdf · uploaded 17 Jan 2024Source
  • 1 Disclosure of sold/ booked inventoryDISCOLSURE 2023 NIRANJAN00024720240117125110.pdf · uploaded 17 Jan 2024Source
  • 2 Disclosure of sold/ booked inventoryDISCOLSURE NIRANJAN00023920240117123036.pdf · uploaded 17 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)10-CA Certificate Niranjan Part4A April to Sep 2023.pdf · uploaded 17 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)18-CA Certificate Niranjan Part4A DEC.pdf · uploaded 17 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Niranjan Investment Pvt Ltd.pdf · uploaded 17 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG CER NIRANJAN 2024.pdf · uploaded 19 Jan 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Niranjan ARC CER March 2024.pdf · uploaded 17 Apr 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Niranjan ENG CER March 2024.pdf · uploaded 17 Apr 2024Source
  • 3 Disclosure of sold/ booked inventorydiscolsure niranjan.pdf · uploaded 17 Apr 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)07-CA Certificate Niranjan Part4A MAR 2024.pdf · uploaded 17 Apr 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC CER NIRANJAN.pdf · uploaded 18 Jul 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG - CER NIRANJAN.pdf · uploaded 18 Jul 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)ENG - CER NIRANJAN.pdf · uploaded 18 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC-CER NIRANJAN.pdf · uploaded 17 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Niranjan.pdf · uploaded 17 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG-CER NIRANJAN.pdf · uploaded 17 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryDiscolsure NIRANJAN.pdf · uploaded 17 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Niranjan investment pvt ltd.pdf · uploaded 17 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC CER NIRANJAN.pdf · uploaded 17 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CER NIRANJAN.pdf · uploaded 17 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG CER NIRANJAN.pdf · uploaded 17 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryDISCOLSURE NIRANJAN.pdf · uploaded 17 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARC CER NIRANJAN.pdf · uploaded 21 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 CA Certificate Niranjan.pdf · uploaded 21 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENG CER NIRANJAN.pdf · uploaded 21 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryDISCOLSURE NIRANJAN.pdf · uploaded 21 Apr 2025Source
  • Form 1ARC CER NIRANJAN.pdf · uploaded 17 Jul 2025Source
  • Form 2ENG CER NIRANJAN.pdf · uploaded 17 Jul 2025Source
  • Form 3CA CER FORM 3 NIRANJAN.pdf · uploaded 17 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDISCOLSURE NIRANJAN.pdf · uploaded 17 Jul 2025Source
  • Form 1ARC CER NIRANJAN.pdf · uploaded 15 Oct 2025Source
  • Form 2ENG CER NIRANJAN.pdf · uploaded 15 Oct 2025Source
  • Form 3CA CER NIRANJAN.pdf · uploaded 15 Oct 2025Source
  • Disclosure of Sold and Booked InventoryDISCOLSURE NIRANJAN.pdf · uploaded 15 Oct 2025Source
  • Form 1ARC CER NIRANJAN.pdf · uploaded 16 Jan 2026Source
  • Form 2ENG CER NIRANJAN.pdf · uploaded 16 Jan 2026Source
  • Form 3FORM 3 CA Cert Niranjan.pdf · uploaded 16 Jan 2026Source
  • Disclosure of Sold and Booked InventoryDISC SOLD UNSOLD NIRANJAN.pdf · uploaded 16 Jan 2026Source
  • Form 1ARC CER NIRANJAN.pdf · uploaded 17 Apr 2026Source
  • Form 2ENG CER NIRANJAN.pdf · uploaded 17 Apr 2026Source
  • Form 3FORM 3 Niranjan.pdf · uploaded 17 Apr 2026Source
  • Disclosure of Sold and Booked InventoryDISC SOLD -UNSOLD NIRANJAN.pdf · uploaded 17 Apr 2026Source
  • Form 1ARC CER NIRANJAN.pdf · uploaded 16 Jul 2026Source
  • Form 2ENG CER NIRANJAN.pdf · uploaded 16 Jul 2026Source
  • Form 3Form-3 CA Certificate NIRANJAN.pdf · uploaded 16 Jul 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD NIRANJAN.pdf · uploaded 16 Jul 2026Source
  • Form 5 (FY 2025-2026)Signed form 5 Niranjan.pdf · uploaded 14 Aug 2026Source
  • Form 2A (FY 2025-2026)FORM-2 NIRANJAN.pdf · uploaded 6 Oct 2026Source

Technical

  • DocumentNiranjan Self Declaration (1).pdf · uploaded 1 Aug 2021Source
  • DocumentNiranajan Investment Layout.pdf · uploaded 1 Aug 2021Source
  • DocumentN A Order.pdf · uploaded 1 Aug 2021Source

Technical (Architect)

  • DocumentARC CER NIRANJAN.pdf · uploaded 18 Jul 2024Source
  • DocumentARC-CER NIRANJAN.pdf · uploaded 17 Oct 2024Source
  • DocumentARC CER NIRANJAN.pdf · uploaded 17 Jan 2025Source
  • DocumentARC CER NIRANJAN.pdf · uploaded 21 Apr 2025Source

Technical (Engineer)

  • DocumentENG - CER NIRANJAN.pdf · uploaded 18 Jul 2024Source
  • DocumentENG-CER NIRANJAN.pdf · uploaded 17 Oct 2024Source
  • DocumentENG CER NIRANJAN.pdf · uploaded 17 Jan 2025Source
  • DocumentENG CER NIRANJAN.pdf · uploaded 21 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Adoshi, Khalapur taluka

Survey, CTS, gat or plot numbers

NI14 NI15

Boundaries

North
Adoshi Water Fall
South
Chavani Village
East
Dukes Nose
West
Khopoli-Pali Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSwaroop Revankar—
Chartered accountantManoj Shah—
EngineerAmod Ranjan—
EngineerSanjiv Chaudhari—
Registered real estate agentHiranandani Communities LLP—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology