Promised date passed2 floorsRERA P52100004636
Unit A-21, Mont Vert Cresta
Deedo IDDP-PUN-PF2Z-21MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked100%1 of 1 · MahaRERA
Completion31 Dec 2019as registered
Units & parking in Unit A-21
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 4 BHK | 171.8 m² (1,849 sq.ft) | 1 | 1 |
As registered with MahaRERA
- RERA registration
- P52100004636 · registered 9 Aug 2017
- Promised completion
- 31 Dec 2019
- Revised completion
- 31 Dec 2019
- Sanctioned habitable floors
- 2
- Sanctioned floors (incl. basement, stilt, podium)
- 2
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-PF2Z-21
Questions about Unit A-21
When is Unit A-21 due for completion?
The MahaRERA registration promises 31 Dec 2019.
How many floors does Unit A-21 have?
2 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology