SRK Platinum
Deedo IDDP-PUN-YSDKIts promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 13% of its units are booked.
Wakad, Pune 411057 · by S R K Buildcon
Buying a flat here?
See every deed registered on it.
Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 24 Feb 2023, completion promised 31 Dec 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100049778
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100049778 | 24 Feb 2023 | 31 Dec 2025 | 31 Dec 2025 | S R K Buildcon | Project page |
Documents91
2 documents held by Deedo, 89 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN CardBuildcon - Pan card.pdf · uploaded 14 Sep 2022Source
Legal
Show all 91 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportTriangular Rera search.pdf · uploaded 13 Sep 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 13 Sep 2022Source
- 1 PAN CardBuildcon - Pan card.pdf · uploaded 14 Sep 2022Source
- 1 a Details of encumbrances concerned to FinanceEncumbrances.pdf · uploaded 14 Sep 2022Source
- 1 b Details of encumbrances concerned to LegalEncumbrances.pdf · uploaded 14 Sep 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 21 Sep 2022Source
- 1 Declaration about Commencement CertificateDeclaration about Commencement.pdf · uploaded 21 Sep 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200247761711_For_Asset_Based_Search_21_09_2022_15_40_04_666.pdf · uploaded 21 Sep 2022Source
- 1 Proforma of Allotment letterMODEL FORM OF AL_compressed.pdf · uploaded 21 Sep 2022Source
- 1 Deviation Report with respect to model copy of AgreementDEVIATION - AFS.pdf · uploaded 21 Sep 2022Source
- 2 a Details of encumbrances concerned to Finance1 b Details of encumbrances concerned to Legal (1).pdf · uploaded 11 Jan 2023Source
- 2 b Details of encumbrances concerned to Legal1 b Details of encumbrances concerned to Legal (1).pdf · uploaded 11 Jan 2023Source
- 1 Building Plan Approval / NA Order for plotted development1 Copy of Layout Approval (in case of layout) (2) (1).pdf · uploaded 11 Jan 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)ilovepdf_merged (11).pdf · uploaded 11 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A- 1 (1) (1).pdf · uploaded 11 Jan 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A- 4 (1) (1).pdf · uploaded 11 Jan 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A- 2 (1) (1).pdf · uploaded 11 Jan 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A- 3 (1) (1).pdf · uploaded 11 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT A BANK.pdf · uploaded 11 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterDEVIATION - AL.pdf · uploaded 11 Jan 2023Source
- 1 Other – Technicalw2.pdf · uploaded 2 Feb 2023Source
- 2 Other – Technicalw3.pdf · uploaded 2 Feb 2023Source
- 3 Other – Technicalw1.pdf · uploaded 2 Feb 2023Source
- 2 Copy of Layout Approval (in case of layout)Sanctioned Layout.pdf · uploaded 13 Dec 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentBuilding Plan 1.pdf · uploaded 13 Dec 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentBuilding Plan 2.pdf · uploaded 13 Dec 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 13 Dec 2023Source
- 2 Declaration about Commencement Certificatedeclaration comm certificate.pdf · uploaded 13 Dec 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 13 Dec 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 13 Dec 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 13 Dec 2023Source
- 1 Disclosure of sold/ booked inventorydiscolsure of sold booked inventory.pdf · uploaded 13 Dec 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)DocScanner 16-Jan-2024 6-58 pm.pdf · uploaded 20 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 1 Mar 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 1 Mar 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 1 Mar 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 1 Mar 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 1 Mar 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 1 Mar 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 1 Mar 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 1 Mar 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 1 Mar 2024Source
- 2 Disclosure of sold/ booked inventoryMarch 23 Sold Unsold.pdf · uploaded 21 Mar 2024Source
- 3 Disclosure of sold/ booked inventoryJune 23 Sold Unsold.pdf · uploaded 21 Mar 2024Source
- 4 Disclosure of sold/ booked inventorySep 23 Sold Unsold.pdf · uploaded 21 Mar 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 March 23.pdf · uploaded 27 Mar 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 June 23.pdf · uploaded 27 Mar 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sep 23.pdf · uploaded 27 Mar 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dec 23.pdf · uploaded 27 Mar 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 March 23.pdf · uploaded 27 Mar 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sep 23.pdf · uploaded 27 Mar 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec 23.pdf · uploaded 27 Mar 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 22 Apr 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 June 2023.pdf · uploaded 22 Apr 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Sep 2023.pdf · uploaded 22 Apr 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Dec 2023.pdf · uploaded 22 Apr 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 March 2023.pdf · uploaded 22 Apr 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 June 2023.pdf · uploaded 22 Apr 2024Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sep 2023.pdf · uploaded 22 Apr 2024Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dec 2023.pdf · uploaded 22 Apr 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 22 Apr 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 March 2023.pdf · uploaded 22 Apr 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 June 2023.pdf · uploaded 22 Apr 2024Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sep 2023.pdf · uploaded 22 Apr 2024Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec 2023.pdf · uploaded 22 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 2022-2023.pdf · uploaded 22 Apr 2024Source
- 5 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 9 Jun 2024View
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 2022-2023.pdf · uploaded 9 Jun 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 15 Jun 2024Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 15 Jun 2024Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 15 Jun 2024Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 27 Jun 2024Source
- 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 27 Jun 2024Source
Technical
- Documentw1.pdf · uploaded 5 Sep 2022Source
- Document1 Copy of Layout Approval (in case of layout) (2) (1).pdf · uploaded 11 Jan 2023Source
- Other – Technicalw2.pdf · uploaded 2 Feb 2023Source
- Other – Technicalw3.pdf · uploaded 2 Feb 2023Source
- Other – Technicalw1.pdf · uploaded 2 Feb 2023Source
- DocumentSanctioned Layout.pdf · uploaded 13 Dec 2023Source
- DocumentBuilding Plan 1.pdf · uploaded 13 Dec 2023Source
- DocumentBuilding Plan 2.pdf · uploaded 13 Dec 2023Source
Technical (Architect)
- DocumentForm 1.pdf · uploaded 27 Jun 2024Source
Technical (Engineer)
- DocumentForm 2.pdf · uploaded 27 Jun 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 71/2 (P), Sr No 71
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK, Flat, Shop31 units in all
- Address
- Sr No 71, 71/2 (P), Wakad Hinjewadi Road, Wakad Hinjewadi RoadPIN 411057
- Village
- Wakad, Mulshi taluka
- Land area for this project
- 1,115 sq m (12,002 sq ft)
- Permissible built-up area
- 1,221 sq m (13,144 sq ft)
- Sanctioned built-up area
- 1,221 sq m (13,144 sq ft)
- Designated bank account
- 196
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Sr No 71, 71/2 (P)
Boundaries
- North
- 30mwideproposedDP Road
- South
- Adj no
- East
- Adj No
- West
- 5m Existing Road or 9m Proposed road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking31 units
4 of 31 units booked (13%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 58.93 sq m · 634 sq ft | 5 | 0 |
| 2BHK | 59.69 sq m · 642 sq ft | 1 | 0 |
| 2BHK | 64.4 sq m · 693 sq ft | 4 | 0 |
| 2BHK | 67.37 sq m · 725 sq ft | 1 | 0 |
| 2BHK | 70.04 sq m · 754 sq ft | 6 | 0 |
| 3BHK | 81.23 sq m · 874 sq ft | 5 | 0 |
| Flat | 113.46 sq m · 1,221 sq ft | 1 | 0 |
| Shop | 34.85 sq m · 375 sq ft | 1 | 0 |
Show all 15 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 41.57 sq m · 447 sq ft | 1 | 1 |
| Shop | 41.75 sq m · 449 sq ft | 1 | 1 |
| Shop | 43.51 sq m · 468 sq ft | 1 | 1 |
| Shop | 44.96 sq m · 484 sq ft | 1 | 0 |
| Shop | 47.55 sq m · 512 sq ft | 1 | 0 |
| Shop | 48.11 sq m · 518 sq ft | 1 | 0 |
| Shop | 51.95 sq m · 559 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Pramod D Shinde | — |
| Chartered accountant | Mahavir H Parakh | — |
| Engineer | Rahul Kapse | — |
Source: MahaRERA project page. Contact details are not shown.