Skip to content
Commercial · 1 building · 58 unitsRERA P52100024639

Olive Orchard

Deedo IDDP-PUN-3QM3

Its promised completion date, Jul 2026, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 29% of its units are booked.

Wakad, Pune 411057 · by Anandtara Properties

Delivery4 mo past duePromised Jul 2026 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales29% booked17 of 58 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Jul 2026, has passed and MahaRERA does not show it completed

  • This projectRegistered 24 Feb 2020, completion promised 31 Jul 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100024639
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002463924 Feb 202031 Jul 202631 Jul 2026Anandtara PropertiesProject page
Documents111

1 document held by Deedo, 110 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan of Properties-converted.pdf · uploaded 18 Feb 2020Source

Legal

  • Declaration Form BSuhas Affidavit Wakad.pdf · uploaded 17 Feb 2020Source
  • Legal Title reportTitle search.pdf · uploaded 18 Feb 2020Source
  • Declaration Form Bform B.pdf · uploaded 30 Jul 2024Source
  • Declaration Form BFORM B AFFIDAVIT.pdf · uploaded 10 Oct 2024Source
  • Declaration Form BFORM B AFFIDAVIT.pdf · uploaded 16 Dec 2024Source

Migrated

  • 1 Details of encumbrancesDetails of Encrumbranses.pdf · uploaded 17 Feb 2020Source
Show all 111 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)layout wakad (2).pdf · uploaded 17 Feb 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentN A Order Wakad.pdf · uploaded 17 Feb 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement of Wakad.pdf · uploaded 17 Feb 2020Source
  • 1 Declaration in FORM BSuhas Affidavit Wakad.pdf · uploaded 17 Feb 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certificate wakad.pdf · uploaded 17 Feb 2020Source
  • 1 PAN CardPan of Properties-converted.pdf · uploaded 18 Feb 2020Source
  • 1 Copy of the legal title reportTitle search.pdf · uploaded 18 Feb 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate wakad.pdf · uploaded 18 Feb 2020Source
  • 1 Proforma of Allotment letterDraft Agreement-converted.pdf · uploaded 18 Feb 2020Source
  • 1 Declaration about Commencement CertificateDeclaration of Commence Olive.pdf · uploaded 22 Nov 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Quality Assurance 2021_compressed.pdf · uploaded 4 Dec 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Engineer Quality Assurance 2021_compressed (1).pdf · uploaded 4 Dec 2021Source
  • 2 Copy of Layout Approval (in case of layout)re layout.pdf · uploaded 26 May 2023Source
  • 1 Proforma of Agreement for saleProfarma agr of sale.pdf · uploaded 26 May 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentREVISED SANTIONED PLAN WITH HIGH LIGHTS.pdf · uploaded 29 Nov 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentREVISED CC.pdf · uploaded 29 Nov 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 dec 2023.pdf · uploaded 1 Dec 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 nov 023.pdf · uploaded 7 Dec 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM_1_Wakad.pdf · uploaded 14 Dec 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2A.pdf · uploaded 14 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)form 5.pdf · uploaded 14 Dec 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentrevised latest cc 31 oct 2023_compressed.pdf · uploaded 29 Dec 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 4 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 PDF.pdf · uploaded 5 Jan 2024Source
  • 1 Disclosure of sold/ booked inventoryBOOKED AND SOLD INV.pdf · uploaded 5 Jan 2024Source
  • 2 Declaration in FORM Bform B.pdf · uploaded 30 Jul 2024Source
  • 1 Declaration in FORM BFORM B AFFIDAVIT.pdf · uploaded 10 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 latest.pdf · uploaded 10 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 latest.pdf · uploaded 10 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 latest.pdf · uploaded 10 Oct 2024Source
  • 1 CERSAI detailsreport of cersai.pdf · uploaded 10 Oct 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)format A bank declaration.pdf · uploaded 10 Oct 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsS interst in other real estate.pdf · uploaded 10 Oct 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsSuhas Sir interest in other real estate.pdf · uploaded 10 Oct 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsShs interst in other real estate.pdf · uploaded 10 Oct 2024Source
  • 4 Disclosure of Interest in Other Real Estate Organizationssachin sir interst in other real estate.pdf · uploaded 10 Oct 2024Source
  • 5 Disclosure of Interest in Other Real Estate Organizationsdada interst in other real estate.pdf · uploaded 10 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 octomber.pdf · uploaded 28 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 oct.pdf · uploaded 28 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 oct.pdf · uploaded 28 Oct 2024Source
  • 1 a Details of encumbrances concerned to Finance1 Details of encumbrances.pdf · uploaded 25 Nov 2024Source
  • 1 Copy of Layout Approval (in case of layout)FIRST LAYOUT with highlights.pdf · uploaded 25 Nov 2024Source
  • 2 Copy of Layout Approval (in case of layout)SECOND A PARKING LAYOUT.pdf · uploaded 25 Nov 2024Source
  • 3 Copy of Layout Approval (in case of layout)THIRD C BLDG.pdf · uploaded 25 Nov 2024Source
  • 4 Copy of Layout Approval (in case of layout)FOURTH C BLDG.pdf · uploaded 25 Nov 2024Source
  • 5 Copy of Layout Approval (in case of layout)FIFTH C-BLDG.pdf · uploaded 25 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 25 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 25 Nov 2024Source
  • 1 Declaration about Commencement Certificateformat D.pdf · uploaded 25 Nov 2024Source
  • 1 b Details of encumbrances concerned to Legal1 Details of encumbrances.pdf · uploaded 25 Nov 2024Source
  • 2 Declaration in FORM BFORM B AFFIDAVIT.pdf · uploaded 16 Dec 2024Source
  • 1 Disclosure of sold/ booked inventoryBOOKED AND SOLD INV.pdf · uploaded 16 Dec 2024Source
  • 2 CERSAI detailsreport of cersai.pdf · uploaded 16 Dec 2024Source
  • 2 Declaration about all RERA Designated Bank Accounts (Format A)format A bank declaration.pdf · uploaded 16 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)form 5 latest.pdf · uploaded 16 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A.pdf · uploaded 16 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 latest.pdf · uploaded 16 Dec 2024Source
  • Form 1form 1 dec 2024.pdf · uploaded 8 Nov 2025Source
  • Form 2Form_2 DEC Q3 2024.pdf · uploaded 8 Nov 2025Source
  • Form 3Dec 024 Q 3_compressed.pdf · uploaded 8 Nov 2025Source
  • Disclosure of Sold and Booked InventoryBOOK AND SOLD DEC 2024.pdf · uploaded 8 Nov 2025Source
  • Form 1form 1 march 2025.pdf · uploaded 8 Nov 2025Source
  • Form 2Form 2 MARCH Q4-2025.pdf · uploaded 8 Nov 2025Source
  • Form 3March 2025 Q 4 of 2024_compressed.pdf · uploaded 8 Nov 2025Source
  • Disclosure of Sold and Booked Inventorybook and sold march 2025.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 1form 1 sept 2025.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 2Form 2 SEPT Q2 2025.pdf · uploaded 8 Nov 2025Source
  • Withdrawal Update Form 3Sept 2025 Q 2.pdf · uploaded 8 Nov 2025Source
  • Form 1form 1.pdf · uploaded 12 Dec 2025Source
  • Form 2form 2.pdf · uploaded 12 Dec 2025Source
  • Form 3form 3.pdf · uploaded 12 Dec 2025Source
  • Disclosure of Sold and Booked InventoryBOOK AND SOLD.pdf · uploaded 12 Dec 2025Source
  • Withdrawal Update Form 1form 1 June 2025.pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 1form 1 sept 2025.pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 1form 1 olive orchard.pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 1form 1 olive orchard.pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 3form 3 (1).pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 3form 3 (1).pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 3form 3 olive orchard.pdf · uploaded 27 May 2026Source
  • Withdrawal Update Form 3form 3 olive orchard.pdf · uploaded 27 May 2026Source
  • Form 5 (FY 2025-2026)form 5 year 2024 and 2025.pdf · uploaded 27 May 2026Source

Technical

  • Documentlayout wakad (2).pdf · uploaded 17 Feb 2020Source
  • DocumentN A Order Wakad.pdf · uploaded 17 Feb 2020Source
  • Documentre layout.pdf · uploaded 26 May 2023Source
  • DocumentREVISED SANTIONED PLAN WITH HIGH LIGHTS.pdf · uploaded 29 Nov 2023Source
  • DocumentFIRST LAYOUT with highlights.pdf · uploaded 25 Nov 2024Source
  • DocumentSECOND A PARKING LAYOUT.pdf · uploaded 25 Nov 2024Source
  • DocumentTHIRD C BLDG.pdf · uploaded 25 Nov 2024Source
  • DocumentFOURTH C BLDG.pdf · uploaded 25 Nov 2024Source
  • DocumentFIFTH C-BLDG.pdf · uploaded 25 Nov 2024Source

Technical (Architect)

  • Documentform 1 latest.pdf · uploaded 10 Oct 2024Source
  • Documentform 1 octomber.pdf · uploaded 28 Oct 2024Source
  • Documentform 1.pdf · uploaded 23 Jul 2026Source

Technical (Engineer)

  • DocumentFORM 2 latest.pdf · uploaded 10 Oct 2024Source
  • Documentform 2 oct.pdf · uploaded 28 Oct 2024Source
  • Documentform 2.pdf · uploaded 27 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 126/2

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Unit types
Office space, Shop, —58 units in all
Address
126/2, Ganesh Nagar, Kala Khadar ChowkPIN 411057
Village
Wakad, Mulshi taluka
Land area for this project
2,900 sq m (31,215 sq ft)
Permissible built-up area
9,787 sq m (1,05,348 sq ft)
Sanctioned built-up area
4,569 sq m (49,184 sq ft)
Recreational open space
610 sq m (6,566 sq ft)
Designated bank account
87
Developed in phases
No

Survey, CTS, gat or plot numbers

126/2

Land as published on MahaRERA's project page

126/2

Boundaries

North
Boundry Of Mouje Tathavade Gao
South
24 mtr wide DP Road
East
Boundry Thergao
West
S No 126 Hissa No 1

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking58 units

17 of 58 units booked (29%), as the promoter reported to MahaRERA

Office space · 4 unitsShop · 53 units— · 1 unit
TypeCarpet areaUnitsBooked
Office space34.76 sq m · 374 sq ft31
Office space54.82 sq m · 590 sq ft10
Shop18.47 sq m · 199 sq ft10
Shop19.5 sq m · 210 sq ft10
Shop20.3 sq m · 219 sq ft10
Shop34.19 sq m · 368 sq ft31
Shop34.42 sq m · 370 sq ft11
Shop34.56 sq m · 372 sq ft11
Show all 27 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop34.93 sq m · 376 sq ft30
Shop34.93 sq m · 376 sq ft11
Shop34.94 sq m · 376 sq ft22
Shop36.64 sq m · 394 sq ft10
Shop39.1 sq m · 421 sq ft10
Shop39.35 sq m · 424 sq ft31
Shop39.5 sq m · 425 sq ft124
Shop39.86 sq m · 429 sq ft22
Shop41.17 sq m · 443 sq ft22
Shop41.86 sq m · 451 sq ft20
Shop52.69 sq m · 567 sq ft31
Shop52.88 sq m · 569 sq ft30
Shop52.97 sq m · 570 sq ft30
Shop53.93 sq m · 580 sq ft10
Shop56.44 sq m · 608 sq ft10
Shop56.88 sq m · 612 sq ft30
Shop58.68 sq m · 632 sq ft10
Shop62.23 sq m · 670 sq ft10
—708.2 sq m · 7,623 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr Vikas Achalkar—
Chartered accountantParas—
Chartered accountantP C Vijapure—
EngineerSuhas A Gaikwad—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology