Residential / Group Housing · 1 building · 12 unitsRERA P52100014695

Neelambari

Deedo IDDP-PUN-V5ZT

MahaRERA shows it completed; no MahaRERA orders on record; 100% of its units are booked.

Wakad, Pune 411057 · by Namrata Construction

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked12 of 12 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 26 Dec 2017, completion promised 31 Dec 2019.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100014695
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001469526 Dec 201731 Dec 201931 Dec 2019Namrata ConstructionProject page
Documents32

1 document held by Deedo, 31 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan copy.pdf · uploaded 9 Dec 2017Source

Legal

  • Declaration Form BDeclaration Ravindra Namde.pdf · uploaded 12 Dec 2017Source
  • Legal Title reportSearch and Title Report.pdf · uploaded 13 Dec 2017Source
  • OtherNeelambari Completion Certificate.pdf · uploaded 28 Mar 2019Source

Migrated

  • 1 PAN CardPan copy.pdf · uploaded 9 Dec 2017Source
  • 1 Declaration in FORM BDeclaration Ravindra Namde.pdf · uploaded 12 Dec 2017Source
  • 1 Copy of the legal title reportSearch and Title Report.pdf · uploaded 13 Dec 2017Source
Show all 32 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 13 Dec 2017Source
  • 1 Building Plan Approval (IOD)Building Plan.pdf · uploaded 13 Dec 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement.pdf · uploaded 13 Dec 2017Source
  • 1 Certificates of CA (Form 3)CA certificate Neelambari.pdf · uploaded 13 Dec 2017Source
  • 1 Details of encumbrancesEncumbrances.pdf · uploaded 14 Dec 2017Source
  • 1 Proforma of Allotment letterDraft Agreement.pdf · uploaded 15 Dec 2017Source
  • 2 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 24 Apr 2018Source
  • 2 Building Plan Approval (IOD)Building plan 5th and 6th floor sanction.pdf · uploaded 24 Apr 2018Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommincement 5th and 6 th floor sanction.pdf · uploaded 24 Apr 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect letter.pdf · uploaded 24 Apr 2018Source
  • 2 Certificates of CA (Form 3)7402_Namrata Const_Rera Cert neelambari.pdf · uploaded 2 Oct 2018Source
  • 3 Certificates of CA (Form 3)CA Certificate Form -3.pdf · uploaded 15 Dec 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Certificate Of Architect.pdf · uploaded 19 Dec 2018Source
  • 1 Certificates of CA (Form 5)NEELAMBARI FORM 5.pdf · uploaded 20 Dec 2018Source
  • 4 Certificates of CA (Form 3)CA Certificate Neelambai (Reffer Tally Data Upto 14-01-2019).pdf · uploaded 19 Jan 2019Source
  • 1 OtherNeelambari Completion Certificate.pdf · uploaded 28 Mar 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentNeelambari Completion Certificate.pdf · uploaded 30 Jun 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form -4 (10-07-20).pdf · uploaded 10 Jul 2020Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Reg Certificate.pdf · uploaded 20 Sep 2021Source

Technical

  • DocumentLayout.pdf · uploaded 13 Dec 2017Source
  • DocumentBuilding Plan.pdf · uploaded 13 Dec 2017Source
  • Documentlayout.pdf · uploaded 24 Apr 2018Source
  • DocumentBuilding plan 5th and 6th floor sanction.pdf · uploaded 24 Apr 2018Source

Technical (Architect)

  • DocumentCertificate Of Architect.pdf · uploaded 19 Dec 2018Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S NO 127

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK12 units in all
Address
S No 127, Chaudhari Park Road, WakadPIN 411057
Village
Wakad, Mulshi taluka
Land area for this project
600 sq m (6,458 sq ft)
Permissible built-up area
841 sq m (9,050 sq ft)
Sanctioned built-up area
509 sq m (5,481 sq ft)
Developed in phases
No

Survey, CTS, gat or plot numbers

S NO 127

Land as published on MahaRERA's project page

S NO 127

Boundaries

North
7 5 Mtr Road
South
Pvt Plot No B28 B29
East
Pvt Plot No B16
West
12 Mtr Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking12 units

12 of 12 units booked (100%), as the promoter reported to MahaRERA

2BHK · 12 units
TypeCarpet areaUnitsBooked
2BHK53.18 sq m · 572 sq ft11
2BHK53.3 sq m · 574 sq ft11
2BHK55.44 sq m · 597 sq ft55
2BHK55.55 sq m · 598 sq ft55

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGautam Shah—
EngineerAjit Gijare & Associates—
OtherDeva Enterprises—
OtherEagle Electricals—
OtherKunal Construction—
OtherR S Construction—
OtherSamarth Waterproofing Company—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology