Promised date passed9 floorsRERA P52100002264
A, Dreamcastle
Deedo IDDP-PUN-H5HK-AMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked99%82 of 83 · MahaRERA
Completion30 Jun 2019as registered
Units & parking in A
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 75 m² (807 sq.ft) | 3 | 3 |
| 2BHK | 75.6 m² (814 sq.ft) | 3 | 3 |
| 2BHK | 75.8 m² (816 sq.ft) | 3 | 3 |
| 2BHK | 75.9 m² (816 sq.ft) | 1 | 1 |
| 2BHK | 75.9 m² (817 sq.ft) | 3 | 3 |
| 2BHK | 76.6 m² (824 sq.ft) | 3 | 3 |
| 2BHK | 76.6 m² (824 sq.ft) | 1 | 1 |
| 2BHK | 76.7 m² (826 sq.ft) | 3 | 2 |
| 2BHK | 76.7 m² (826 sq.ft) | 1 | 1 |
| 2BHK | 76.8 m² (826 sq.ft) | 3 | 3 |
| 2BHK | 77.1 m² (830 sq.ft) | 3 | 3 |
| 2BHK | 77.2 m² (831 sq.ft) | 3 | 3 |
| 2BHK | 77.3 m² (832 sq.ft) | 1 | 1 |
| 2BHK | 77.3 m² (832 sq.ft) | 3 | 3 |
| 2BHK | 77.4 m² (833 sq.ft) | 3 | 3 |
| 2BHK | 77.4 m² (833 sq.ft) | 1 | 1 |
| 2BHK | 77.5 m² (834 sq.ft) | 3 | 3 |
| 2BHK | 77.5 m² (834 sq.ft) | 1 | 1 |
| 2BHK | 77.5 m² (834 sq.ft) | 1 | 1 |
| 2BHK | 77.6 m² (836 sq.ft) | 3 | 3 |
| 2BHK | 77.7 m² (837 sq.ft) | 3 | 3 |
| 2BHK | 77.8 m² (837 sq.ft) | 1 | 1 |
| 2BHK | 77.9 m² (838 sq.ft) | 3 | 3 |
| 2BHK | 78.8 m² (848 sq.ft) | 3 | 3 |
| 2BHK | 78.8 m² (848 sq.ft) | 3 | 3 |
| 2BHK | 79 m² (850 sq.ft) | 1 | 1 |
| 2BHK | 79.6 m² (857 sq.ft) | 3 | 3 |
| 2BHK | 79.8 m² (859 sq.ft) | 3 | 3 |
| 2BHK | 79.8 m² (859 sq.ft) | 1 | 1 |
| 2BHK | 80.7 m² (869 sq.ft) | 4 | 4 |
| 2BHK | 81.8 m² (880 sq.ft) | 4 | 4 |
| 2BHK | 83.2 m² (895 sq.ft) | 3 | 3 |
| 2BHK | 83.4 m² (898 sq.ft) | 1 | 1 |
| 2BHK | 84.2 m² (906 sq.ft) | 3 | 3 |
| 2BHK | 84.4 m² (908 sq.ft) | 1 | 1 |
As registered with MahaRERA
- RERA registration
- P52100002264 · registered 31 Jul 2017
- Promised completion
- 30 Jun 2019
- Revised completion
- 30 Jun 2019
- Sanctioned habitable floors
- 9
- Sanctioned floors (incl. basement, stilt, podium)
- 9
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-H5HK-A
Questions about A
When is A due for completion?
The MahaRERA registration promises 30 Jun 2019.
How many floors does A have?
9 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology