Everest Phase 2

Deedo IDDP-PUN-2AG4

Completion was pushed back 4 months, to Sep 2027; no MahaRERA orders on record; 0% of its units are booked.

Wadagaon (Ct), Pune 412106 · by J P Construction

DeliveryExtended 4 moPromised May 2027 · now due Sep 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 62 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Sep 2027

  • This projectRegistered 16 Aug 2024, completion promised 31 May 2027, revised to 30 Sep 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100077451
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210007745116 Aug 202431 May 202730 Sep 2027J P ConstructionProject page
Documents58

1 document held by Deedo, 57 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card.pdf · uploaded 2 Jun 2024Source

Legal

  • Declaration Form BForm B JP construction_compressed.pdf · uploaded 2 Jun 2024Source
  • Other – LegalAnnexure A_compressed.pdf · uploaded 12 Jun 2024Source
  • Other – LegalPOA J P Construction to Santosh Pathade_compressed.pdf · uploaded 2 Jul 2024Source
  • Legal Title reportDocument 91_compressed.pdf · uploaded 17 Jul 2024Source
  • Other – LegalArchitect Form 1 compress.pdf · uploaded 31 Jul 2024Source

Migrated

  • 1 PAN CardPan Card.pdf · uploaded 2 Jun 2024Source
Show all 58 documentsShow fewer documents

Migrated

  • 1 a Details of encumbrances concerned to FinanceEncumbrances Certificate JP.pdf · uploaded 2 Jun 2024Source
  • 1 b Details of encumbrances concerned to LegalEncumbrances Certificate JP.pdf · uploaded 2 Jun 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentEVEREST PHASE 2 CC.pdf · uploaded 2 Jun 2024Source
  • 1 Declaration about Commencement CertificateFormat D J P construction.pdf · uploaded 2 Jun 2024Source
  • 1 Declaration in FORM BForm B JP construction_compressed.pdf · uploaded 2 Jun 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Everest Phase 2 Architects Certificate.pdf · uploaded 3 Jun 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Everest Phase 2 Engineer’s Certificate_compressed.pdf · uploaded 3 Jun 2024Source
  • 1 Deviation Report with respect to Allotment letterJP Allotment.pdf · uploaded 3 Jun 2024Source
  • 1 Deviation Report with respect to model copy of AgreementJ P Construction Deviation sale deed_compressed.pdf · uploaded 3 Jun 2024Source
  • 1 Copy of Layout Approval (in case of layout)Sanction Plan Scan_1446-01.pdf · uploaded 5 Jun 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentSanction Plan Scan_1446-01.pdf · uploaded 5 Jun 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentSanction Plan Scan_1446-02.pdf · uploaded 5 Jun 2024Source
  • 1 CERSAI detailsCERSAI_Search_Report_200310042595_For_Asset_Based_Search_12_06_2024_16_53_48_601.pdf · uploaded 12 Jun 2024Source
  • 1 Other – LegalAnnexure A_compressed.pdf · uploaded 12 Jun 2024Source
  • 1 Other – TechnicalGmail - Please Find AttachmEVEREST_RERA.pdf · uploaded 12 Jun 2024Source
  • 2 CERSAI detailsCersai declaration.pdf · uploaded 18 Jun 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Accounts Format A (1).pdf · uploaded 18 Jun 2024Source
  • 2 Other – TechnicalAdobe Scan 1 Nov 2023_240425_130012.pdf · uploaded 20 Jun 2024Source
  • 2 a Details of encumbrances concerned to FinanceJP Encumbrance Certificate revised.pdf · uploaded 2 Jul 2024Source
  • 2 b Details of encumbrances concerned to LegalJP Encumbrance Certificate revised.pdf · uploaded 2 Jul 2024Source
  • 2 Other – LegalPOA J P Construction to Santosh Pathade_compressed.pdf · uploaded 2 Jul 2024Source
  • 1 Copy of the legal title reportDocument 91_compressed.pdf · uploaded 17 Jul 2024Source
  • 1 Disclosure of Interest in Other Real Estate Organizationspathade Annexter.pdf · uploaded 17 Jul 2024Source
  • 2 Disclosure of Interest in Other Real Estate Organizationsjalit Annexer.pdf · uploaded 17 Jul 2024Source
  • 1 Proforma of Allotment letterAllotment Performa New format with Parking.pdf · uploaded 31 Jul 2024Source
  • 1 Proforma of Agreement for saleRERA DRAFT J P CONSTRUCTION EVEREST PHASE 2 with parking .pdf · uploaded 31 Jul 2024Source
  • 3 Other – LegalArchitect Form 1 compress.pdf · uploaded 31 Jul 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)JP Cont Form 3 Jun to Sep 2024.pdf · uploaded 5 Aug 2024Source
  • Form 1Form 2 Engg Sep 2024.pdf · uploaded 24 Jul 2025Source
  • Form 2Form 2 Engg Sep 2024.pdf · uploaded 24 Jul 2025Source
  • Form 3CA JP Cont Form 3 Jun to Sep 2024.pdf · uploaded 24 Jul 2025Source
  • Disclosure of Sold and Booked InventoryCA JP Cont Form 3 Jun to Sep 2024-6-7 unsold inventory.pdf · uploaded 24 Jul 2025Source
  • Form 1Form 1 Everest Phase 2 Dec 2024.pdf · uploaded 25 Jul 2025Source
  • Form 2Form 2 Engineers Dec 2024.pdf · uploaded 25 Jul 2025Source
  • Form 3JP Form 3 Dec 2024.pdf · uploaded 25 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure Sold unit 31122024.pdf · uploaded 25 Jul 2025Source
  • Form 1Form 1 Architect Everest 2 March 2025.pdf · uploaded 25 Jul 2025Source
  • Form 2Form 2 Engg Everest 2 March 2025.pdf · uploaded 25 Jul 2025Source
  • Form 3JC Form 3 March 2025.pdf · uploaded 25 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure Sold Unit 31032025.pdf · uploaded 25 Jul 2025Source
  • Withdrawal Update Form 1Form 1 Architect Letter EVEREST June 2025.pdf · uploaded 26 Jul 2025Source
  • Withdrawal Update Form 2Form 2 Enginners EVEREST 2 June 2025.pdf · uploaded 26 Jul 2025Source
  • Withdrawal Update Form 3JP Form 3 June 2025.pdf · uploaded 26 Jul 2025Source

Technical

  • DocumentSanction Plan Scan_1446-01.pdf · uploaded 5 Jun 2024Source
  • DocumentSanction Plan Scan_1446-01.pdf · uploaded 5 Jun 2024Source
  • DocumentSanction Plan Scan_1446-02.pdf · uploaded 5 Jun 2024Source
  • Other – TechnicalGmail - Please Find AttachmEVEREST_RERA.pdf · uploaded 12 Jun 2024Source
  • Other – TechnicalAdobe Scan 1 Nov 2023_240425_130012.pdf · uploaded 20 Jun 2024Source

Technical (Architect)

  • DocumentForm 1 Architect Letter EVEREST June 2025.pdf · uploaded 26 Jul 2025Source

Technical (Engineer)

  • DocumentForm 2 Enginners EVEREST 2 June 2025.pdf · uploaded 26 Jul 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO 35 36 37 SR NO 112/2A/2/1

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 4BHK, Alloted to landowner, Shop62 units in all
Address
Plot No 35 36 37 Sr No 112/2a/2/1, Nera Talegaon Chakan Rd, Vadgaon MavalPIN 412106
Village
Wadagaon (CT), Mawal taluka
Land area for this project
1,756 sq m (18,898 sq ft)
Permissible built-up area
3,878 sq m (41,747 sq ft)
Sanctioned built-up area
3,878 sq m (41,747 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO 35 36 37 SR NO 112/2A/2/1

Land as published on MahaRERA's project page

PLOT NO 35 36 37 SR NO 112/2A/2/1

Boundaries

North
Plot No 38
South
Plot No 34
East
9 Mtr Rd
West
Plot No 39

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking62 units

0 of 62 units booked (0%), as the promoter reported to MahaRERA

2BHK · 19 units4BHK · 4 unitsAlloted to landowner · 27 unitsShop · 12 units
TypeCarpet areaUnitsBooked
2BHK39.19 sq m · 422 sq ft20
2BHK50.03 sq m · 539 sq ft30
2BHK50.08 sq m · 539 sq ft20
2BHK50.2 sq m · 540 sq ft10
2BHK53.41 sq m · 575 sq ft20
2BHK53.91 sq m · 580 sq ft30
2BHK54.11 sq m · 582 sq ft20
2BHK56.72 sq m · 611 sq ft40
Show all 35 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
4BHK54.07 sq m · 582 sq ft40
Alloted to landowner39.19 sq m · 422 sq ft20
Alloted to landowner46.97 sq m · 506 sq ft40
Alloted to landowner50.03 sq m · 539 sq ft20
Alloted to landowner50.08 sq m · 539 sq ft30
Alloted to landowner50.2 sq m · 540 sq ft30
Alloted to landowner50.27 sq m · 541 sq ft20
Alloted to landowner53.41 sq m · 575 sq ft20
Alloted to landowner53.91 sq m · 580 sq ft20
Alloted to landowner54.07 sq m · 582 sq ft10
Alloted to landowner54.11 sq m · 582 sq ft20
Alloted to landowner56.72 sq m · 611 sq ft10
Alloted to landowner57.91 sq m · 623 sq ft10
Alloted to landowner61.05 sq m · 657 sq ft10
Alloted to landowner61.67 sq m · 664 sq ft10
Shop8.83 sq m · 95 sq ft10
Shop11.27 sq m · 121 sq ft10
Shop12.7 sq m · 137 sq ft10
Shop13.21 sq m · 142 sq ft10
Shop14.12 sq m · 152 sq ft10
Shop14.47 sq m · 156 sq ft10
Shop15.38 sq m · 166 sq ft10
Shop15.72 sq m · 169 sq ft10
Shop15.72 sq m · 169 sq ft10
Shop16.26 sq m · 175 sq ft10
Shop17.19 sq m · 185 sq ft10
Shop18.67 sq m · 201 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSaie Engineers Architects Ajay Patil—
Chartered accountantR M Dangi And Co R M Dangi—
Chartered accountantSachin Maruti Dimale—
EngineerSaie Engineers And Allied Designers Ajay Patil—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology