Skip to content
Residential / Group Housing · 4 buildings · 80 unitsRERA P52100027893

Centria R Building - Casa

Deedo IDDP-PUN-D96Y

MahaRERA shows it completed, after its date was pushed back 6 months; no MahaRERA orders on record; 100% of its units are booked.

Undri, Pune 411060 · Property rates in Undri · by Ankit Enterprises

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 6 mo extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked80 of 80 units · as the promoter reported to MahaRERAPrice₹7,200 /sq ft4.2% above Undri · 21 registered sales

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 6 months

  • This projectRegistered 14 Jan 2021, completion promised 30 Jun 2024, revised to 29 Dec 2024.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

All 126 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Jul 2026Not on recordRental—View Rental, Jul 2026
Jun 2026Not on recordRental—View Rental, Jun 2026
Apr 2026Not on recordRental—View Rental, Apr 2026
Apr 2026Not on recordRental—View Rental, Apr 2026
Apr 2026Not on recordRental—View Rental, Apr 2026
Apr 2026Not on recordRental—View Rental, Apr 2026
Apr 2026Unit 401Other1,138 sq ftView Other, Apr 2026
Apr 2026Not on recordRental—View Rental, Apr 2026
Mar 2026Main building · 4Rental—View Rental, Mar 2026
Feb 2026Unit 401Primary sale1,138 sq ftView Primary sale, Feb 2026

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100027893
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002789314 Jan 202130 Jun 202429 Dec 2024Ankit EnterprisesProject page
Documents91

3 documents held by Deedo, 88 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN.pdf · uploaded 24 Dec 2020Source
  • Other – FinanceAnkit R Building Casa.pdf · uploaded 29 Sep 2022Source

Legal

  • Legal Title reporttitle search certificate.pdf · uploaded 23 Dec 2020Source
  • Declaration Form BAffidavit 2 Ankit.pdf · uploaded 24 Dec 2020Source
  • Declaration Form BAffidavit 2 Ankit.pdf · uploaded 24 Dec 2020Source
Show all 91 documentsShow fewer documents

Legal

  • Declaration Form BForm B- Affidavit- Promoter- Centra R Building Casa- RERA extension.pdf · uploaded 6 Aug 2024Source

Migrated

  • 1 Copy of the legal title reporttitle search certificate.pdf · uploaded 23 Dec 2020Source
  • 1 Details of encumbrancesankit encumbrances details.pdf · uploaded 23 Dec 2020Source
  • 1 Copy of Layout Approval (in case of layout)layout1.pdf · uploaded 23 Dec 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentlayout1.pdf · uploaded 23 Dec 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentcoomencement certificate.pdf · uploaded 23 Dec 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed form 3.pdf · uploaded 23 Dec 2020Source
  • 1 Proforma of Allotment letterAFS - casa.pdf · uploaded 23 Dec 2020Source
  • 1 PAN CardPAN.pdf · uploaded 24 Dec 2020Source
  • 1 Declaration in FORM BAffidavit 2 Ankit.pdf · uploaded 24 Dec 2020Source
  • 2 Declaration in FORM BAffidavit 2 Ankit.pdf · uploaded 24 Dec 2020Source
  • 2 Proforma of Allotment letter29-06-2021-FINAL-Draft-AFS- Centria-Bldg- R- CASA-HILLS DALES Phase III - Copy.pdf · uploaded 30 Jun 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Centria R Signed Form 5.pdf · uploaded 30 Sep 2021Source
  • 1 CERSAI detailsAnkit Enterprises.pdf · uploaded 7 Jan 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Centria BUILDING CASA.pdf · uploaded 7 Jan 2022Source
  • 1 Disclosure of sold/ booked inventoryCentria R Casa.pdf · uploaded 15 Jan 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Bldg R 07-01-22.pdf · uploaded 18 Jan 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Centria R.pdf · uploaded 20 Jan 2022Source
  • 2 CERSAI detailsAnkit Enterprises.pdf · uploaded 6 Apr 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Centria R.pdf · uploaded 7 Apr 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2_Centria R.pdf · uploaded 8 Apr 2022Source
  • 2 Disclosure of sold/ booked inventoryInventory Declaration Centria R Building Casa.pdf · uploaded 12 Apr 2022Source
  • 3 Proforma of Allotment letterAFS R Building.pdf · uploaded 26 May 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Cer Centria Case - Rbuilding.pdf · uploaded 4 Jul 2022Source
  • 3 CERSAI detailsCERSAI_Search_Report_200241268081_For_Debtor_Based_Search_02_07_2022_12_39_57_146.pdf · uploaded 4 Jul 2022Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Centria Form 3_compressed.pdf · uploaded 5 Jul 2022Source
  • 3 Disclosure of sold/ booked inventoryInventory Declaration Centria R Building.pdf · uploaded 7 Jul 2022Source
  • 4 Proforma of Allotment letterUpdated AFS.pdf · uploaded 18 Jul 2022Source
  • 1 Other – FinanceAnkit R Building Casa.pdf · uploaded 29 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Ankit R Building Casa.pdf · uploaded 30 Sep 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ankit Q2 arch certi.pdf · uploaded 6 Oct 2022Source
  • 4 CERSAI detailsCERSAI_Search_Report_200249955191_For_Debtor_Based_Search_17_10_2022_17_10_03_567.pdf · uploaded 18 Oct 2022Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Centria R Bld- From 3 (1).pdf · uploaded 19 Oct 2022Source
  • 4 Disclosure of sold/ booked inventoryAnkit Enterprise Centria R Building.pdf · uploaded 20 Oct 2022Source
  • 1 Proforma of Agreement for saleAFS 11112022.pdf · uploaded 11 Nov 2022Source
  • 2 Proforma of Agreement for saleAFS.pdf · uploaded 2 Dec 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer - Centria R.pdf · uploaded 17 Jan 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA - centria R.pdf · uploaded 17 Jan 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect - Casa R.pdf · uploaded 18 Jan 2023Source
  • 5 CERSAI detailsCersai.pdf · uploaded 18 Jan 2023Source
  • 5 Disclosure of sold/ booked inventoryAnkit Enterprises Centria.pdf · uploaded 19 Jan 2023Source
  • 3 Proforma of Agreement for saleAFS Centria R 22022023.pdf · uploaded 23 Feb 2023Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Intimation about formation of association and Index 2.pdf · uploaded 28 Feb 2023Source
  • 6 CERSAI detailsCERSAI_Search_Report_200266192103_For_Debtor_Based_Search_15_04_2023_17_08_02_187.pdf · uploaded 15 Apr 2023Source
  • 6 Disclosure of sold/ booked inventoryCentria.pdf · uploaded 19 Apr 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Centria R building.pdf · uploaded 20 Apr 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Centria R.pdf · uploaded 20 Apr 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Centria R - form 3.pdf · uploaded 20 Apr 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Centria R.pdf · uploaded 18 Jul 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ankit Enterprises - Centria R building.pdf · uploaded 20 Jul 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Centria R.pdf · uploaded 20 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)CENTRIA R.pdf · uploaded 29 Sep 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Centria R.pdf · uploaded 19 Oct 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Centria - Form2.pdf · uploaded 20 Oct 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Centria -R.pdf · uploaded 20 Oct 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Centria R.pdf · uploaded 18 Jan 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Centria-R.pdf · uploaded 18 Jan 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Centria-R.pdf · uploaded 18 Jan 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Centria-R signed form-2.pdf · uploaded 19 Apr 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Centria R.pdf · uploaded 19 Apr 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Centria R.pdf · uploaded 20 Jul 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Centria-R.pdf · uploaded 20 Jul 2024Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Centria-R.pdf · uploaded 20 Jul 2024Source
  • 3 Declaration in FORM BForm B- Affidavit- Promoter- Centra R Building Casa- RERA extension.pdf · uploaded 6 Aug 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A - Centria R - FY23.pdf · uploaded 6 Aug 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A - Centria R - FY24.pdf · uploaded 6 Aug 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of other interest.pdf · uploaded 6 Aug 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)bank declaration.pdf · uploaded 6 Aug 2024Source
  • 7 Disclosure of sold/ booked inventoryinventory declaration Jun 24.pdf · uploaded 7 Aug 2024View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A - Centria R - FY23.pdf · uploaded 8 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A - Centria R - FY24.pdf · uploaded 8 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)CENTRIA FORM 5.pdf · uploaded 9 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Centria-R.pdf · uploaded 17 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Centria-R.pdf · uploaded 17 Oct 2024Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC R building.pdf · uploaded 31 Dec 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 - centria R.pdf · uploaded 6 Jan 2025Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentR-Building Completion Centria.pdf · uploaded 24 Feb 2025Source
  • Occupational CertificateR-Building Completion Centria.pdf · uploaded 10 Aug 2026Source

Technical

  • Documentlayout1.pdf · uploaded 23 Dec 2020Source
  • Documentlayout1.pdf · uploaded 23 Dec 2020Source

Technical (Architect)

  • DocumentCentria R.pdf · uploaded 20 Jul 2024Source

Technical (Engineer)

  • DocumentForm-2 Centria-R.pdf · uploaded 20 Jul 2024Source
  • DocumentForm-2 Centria-R.pdf · uploaded 17 Oct 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 13P, 14P

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
3BHK80 units in all
Address
13P, 14P, 15P, 19P, Undri, UndriPIN 411060
Village
Undri, Haveli taluka
Land area for this project
835 sq m (8,992 sq ft)
Permissible built-up area
10,358 sq m (1,11,491 sq ft)
Sanctioned built-up area
9,560 sq m (1,02,901 sq ft)
Designated bank account
85
Developed in phases
Yes
Also registered as
सेंट्रिया आर बिल्डिंग कासा, Sentriya Ar Bilding-Kasa, Shendkar Building, सेंट्रिया आर बिल्डिंग - कासा या स्किममधील आर, Sentriya Ar Bilding - Kasa” Ya Skimamadhil “Ar, Sentriya R Building-Kasa, Sentriya R Building - Kasa” Ya Skimamadhil “R

Survey, CTS, gat or plot numbers

13P14P15P19P

Land as published on MahaRERA's project page

13P, 14P, 15P, 19P

Boundaries

North
Survey No 11P
South
Survey No 15P and 16P
East
Survey No 19P
West
15 m wide road with s no 8P

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking80 units

80 of 80 units booked (100%), as the promoter reported to MahaRERA

3BHK · 80 units
BuildingTypeCarpet areaUnitsBooked
Casa3BHK98.89 sq m · 1,064 sq ft22
Casa3BHK102.25 sq m · 1,101 sq ft22
Casa3BHK105.33 sq m · 1,134 sq ft1111
Casa3BHK105.54 sq m · 1,136 sq ft99
Casa3BHK105.64 sq m · 1,137 sq ft11
Casa3BHK105.72 sq m · 1,138 sq ft1010
Casa3BHK105.75 sq m · 1,138 sq ft1111
Casa3BHK105.85 sq m · 1,139 sq ft1212
Show all 19 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Casa3BHK105.95 sq m · 1,140 sq ft1212
Casa3BHK106.03 sq m · 1,141 sq ft11
Casa3BHK106.06 sq m · 1,142 sq ft11
Casa3BHK106.15 sq m · 1,143 sq ft11
Casa3BHK106.26 sq m · 1,144 sq ft11
Casa 13th Floor3BHK105.33 sq m · 1,134 sq ft11
Casa 13th Floor3BHK105.54 sq m · 1,136 sq ft11
Casa 13th Floor3BHK105.72 sq m · 1,138 sq ft11
Casa 13th Floor3BHK105.75 sq m · 1,138 sq ft11
Casa 13th Floor3BHK105.85 sq m · 1,139 sq ft11
Casa 13th Floor3BHK105.95 sq m · 1,140 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectReza Kabul Architects Pvt Ltd—
Chartered accountantCA Nikita Bajaj—
Chartered accountantVidhi S Shah & Associates Chartered Accountants—
EngineerNandlal Bhole—

Source: MahaRERA project page. Contact details are not shown.

Centria R Building - Casa in numbers

Registered deals, summarised

Deedo has 126 registered documents at Centria R Building - Casa, from Feb 2019 to Jul 2026: 21 sales, 26 leave and licence agreements, 47 mortgages. The median registered sale since Feb 2019 works out to about ₹7,200 per sq ft, at a median of ₹82 L a deal; 0% of sales were resales.

What is the price per sq ft at Centria R Building - Casa?
The median registered sale since Feb 2019 works out to about ₹7,200 per sq ft, at a median of ₹82 L a deal; 0% of sales were resales.
How many properties have been sold at Centria R Building - Casa?
21 sales are registered at Centria R Building - Casa.
Are properties at Centria R Building - Casa rented out?
Yes: 26 leave and licence agreements are registered at Centria R Building - Casa, at a median rent since Feb 2019 of about ₹15,000 a month with a deposit of about ₹20,000.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Centria R Building - Casa by Deedo, last updated with deals registered in Jul 2026.

Latest deal · Rental · Jul 2026

Under ₹10k / month

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology