Skip to content
Residential / Group Housing · 1 building · 24 unitsRERA P52100028512

Aria

Deedo IDDP-PUN-7CTW

Its promised completion date, Jun 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.

Talegaon Dabhade (R), Pune 410507 · by Om Associates · 50% of its projects kept the RERA date

Delivery3 yrs 5 mo past duePromised Jun 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked24 of 24 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Jun 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 8 Mar 2021, completion promised 30 Jun 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100028512
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000285128 Mar 202130 Jun 202330 Jun 2023Om AssociatesProject page
Documents32

1 document held by Deedo, 31 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 4 Mar 2021Source

Legal

  • Declaration Form BDECLRATION.pdf · uploaded 24 Feb 2021Source
  • Legal Title reportSearch Report FINAL.pdf · uploaded 4 Mar 2021Source

Migrated

  • 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 24 Feb 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentPLAN.pdf · uploaded 24 Feb 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentcommencement.pdf · uploaded 24 Feb 2021Source
  • 1 Declaration in FORM BDECLRATION.pdf · uploaded 24 Feb 2021Source
Show all 32 documentsShow fewer documents

Migrated

  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect.pdf · uploaded 24 Feb 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineers_compressed.pdf · uploaded 24 Feb 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM NO 3 F.pdf · uploaded 24 Feb 2021Source
  • 1 Proforma of Allotment letterAGREEMENT DRAFT.pdf · uploaded 24 Feb 2021Source
  • 2 Proforma of Allotment letterPOSSESSION LETTER.pdf · uploaded 24 Feb 2021Source
  • 1 PAN CardPAN.pdf · uploaded 4 Mar 2021Source
  • 1 Copy of the legal title reportSearch Report FINAL.pdf · uploaded 4 Mar 2021Source
  • 1 Details of encumbrancesENCMB FINAL.pdf · uploaded 4 Mar 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARIA C ARCHITECT 30-9-21.pdf · uploaded 4 Oct 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ARIA C ENGG-30-9-21.pdf · uploaded 4 Oct 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARIA C ARCHT CERT MARCH 21.pdf · uploaded 18 Feb 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARIA C ARCHT CERT MARCH 22.pdf · uploaded 18 Feb 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ARIA C ENG CERT MARCH 21.pdf · uploaded 18 Feb 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)ARIA C ENGG CERT MARCH 22.pdf · uploaded 18 Feb 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FROM 3 MARC 21 ARIA C.pdf · uploaded 18 Feb 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FROM 3 MARC 22 ARIA C.pdf · uploaded 18 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FROM 5 MARC 21 ARIA C.pdf · uploaded 18 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FROM 5 MARC 22 ARIA C.pdf · uploaded 18 Feb 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2-2022.pdf · uploaded 20 Feb 2023Source
  • 1 Proforma of Agreement for saleDECLRATION.pdf · uploaded 24 Feb 2024Source

Technical

  • DocumentLAYOUT.pdf · uploaded 24 Feb 2021Source
  • DocumentPLAN.pdf · uploaded 24 Feb 2021Source

Technical (Architect)

  • DocumentARIA C ARCHT CERT MARCH 22.pdf · uploaded 18 Feb 2023Source

Technical (Engineer)

  • DocumentFORM-2-2022.pdf · uploaded 20 Feb 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO 2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop24 units in all
Address
Plot No 2, Takle Vasti, Talegaon DabhadePIN 410507
Village
Talegaon Dabhade (M Cl), Mawal taluka
Land area for this project
1,000 sq m (10,767 sq ft)
Permissible built-up area
1,000 sq m (10,767 sq ft)
Sanctioned built-up area
1,000 sq m (10,767 sq ft)
Designated bank account
109
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO 2

Land as published on MahaRERA's project page

PLOT NO 2

Boundaries

North
12 M Colony Road
South
386 2property Of Ramesh Takle
East
12 M Colony Road
West
Open Space

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking24 units

24 of 24 units booked (100%), as the promoter reported to MahaRERA

1BHK · 16 units2BHK · 4 unitsShop · 4 units
TypeCarpet areaUnitsBooked
1BHK39.2 sq m · 422 sq ft44
1BHK39.39 sq m · 424 sq ft44
1BHK40.13 sq m · 432 sq ft88
2BHK52.4 sq m · 564 sq ft22
2BHK53.05 sq m · 571 sq ft22
Shop17.38 sq m · 187 sq ft22
Shop17.84 sq m · 192 sq ft11
Shop19.79 sq m · 213 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAjay Patil—
Chartered accountantSwanand Vinayak Agashe—
Engineerajay patil—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology