Red Stone

Deedo IDDP-PUN-2YRR

MahaRERA shows it completed; no MahaRERA orders on record.

Takave Bk., Pune 412106 · by Vastu Developers

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 17 Apr 2023, completion promised 31 Jul 2024.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.
Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100050485
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005048517 Apr 202331 Jul 202431 Jul 2024Vastu DevelopersProject page
Documents39

1 document held by Deedo, 38 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card.pdf · uploaded 19 Jan 2023Source

Legal

  • Declaration Form BForm B.pdf · uploaded 24 Feb 2023Source
  • Legal Title reportTitle Search Report Annexure.pdf · uploaded 24 Mar 2023Source
  • Legal Title reportP_Maval_Takave Budruk_Title and Search Report_Signed SCAN Copy (1).pdf · uploaded 24 Mar 2023Source

Migrated

  • 1 PAN CardPAN Card.pdf · uploaded 19 Jan 2023Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Certificate.pdf · uploaded 24 Feb 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Certificate.pdf · uploaded 24 Feb 2023Source
Show all 39 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 24 Feb 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 24 Feb 2023Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 24 Feb 2023Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 24 Feb 2023Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 24 Feb 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Account Details.pdf · uploaded 24 Feb 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report - Allotment Letter.pdf · uploaded 24 Feb 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report - Agreement.pdf · uploaded 24 Feb 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentNA Order.pdf · uploaded 8 Mar 2023Source
  • 1 CERSAI detailsCERSAI Report.pdf · uploaded 8 Mar 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 8 Mar 2023Source
  • 1 Proforma of Agreement for saleSample Agreement.pdf · uploaded 8 Mar 2023Source
  • 1 Copy of the legal title reportTitle Search Report Annexure.pdf · uploaded 24 Mar 2023Source
  • 2 Copy of the legal title reportP_Maval_Takave Budruk_Title and Search Report_Signed SCAN Copy (1).pdf · uploaded 24 Mar 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest.pdf · uploaded 4 Apr 2023Source
  • 2 Proforma of Agreement for saleP_Maval_Takave Budruk_Gat No_598_600_A to S_RERA_English_Final.pdf · uploaded 25 Jul 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 June 2023.pdf · uploaded 16 Jan 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 September 2023.pdf · uploaded 16 Jan 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 December 2023.pdf · uploaded 16 Jan 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 June 2023.pdf · uploaded 16 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 September 2023.pdf · uploaded 16 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 December 2023.pdf · uploaded 16 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 June 2023.pdf · uploaded 16 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 September 2023.pdf · uploaded 16 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 December 2023.pdf · uploaded 16 Jan 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate.pdf · uploaded 4 May 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 6 Jun 2024Source

Technical

  • DocumentLayout.pdf · uploaded 24 Feb 2023Source
  • DocumentNA Order.pdf · uploaded 8 Mar 2023Source

Technical (Architect)

  • DocumentForm 1 December 2023.pdf · uploaded 16 Jan 2024Source

Technical (Engineer)

  • DocumentForm 2 December 2023.pdf · uploaded 16 Jan 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 598(P), Gat No 600(P)

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Certificate Signed
Address
Gat No 600(P) and 598(P), Takave Budruk, MavalPIN 412106
Village
Takave Bk., Mawal taluka
Land area for this project
11,400 sq m (1,22,708 sq ft)
Permissible built-up area
8,721 sq m (93,872 sq ft)
Sanctioned built-up area
8,721 sq m (93,872 sq ft)
Recreational open space
1,140 sq m (12,271 sq ft)
Designated bank account
82
Developed in phases
No

Survey, CTS, gat or plot numbers

598(P)Gat No 600(P)

Land as published on MahaRERA's project page

Gat No 600(P) and 598(P)

Boundaries

North
Boundary of Village Ghonshet
South
Gat No 598 599 and 609
East
Gat No 600 Part
West
Gat No 596 and 597

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectV P Godhbharle—
Chartered accountantRaviraj & Company—
EngineerSachin Patil—

Source: MahaRERA project page. Contact details are not shown.