Krishnakunj Phase 2
Deedo IDDP-PUN-VVHZCompletion was pushed back 4 months, to Sep 2028; no MahaRERA orders on record; 100% of its units are booked.
Shindvane, Pune 412202 · by Heera Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Sep 2028
- This projectRegistered 10 Oct 2025, completion promised 31 May 2028, revised to 30 Sep 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100081010
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100081010 | 10 Oct 2025 | 31 May 2028 | 30 Sep 2028 | Heera Devlopers | Project page |
Documents54
2 documents held by Deedo, 52 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN Card1 PAN Card (6).pdf · uploaded 3 Mar 2025Source
Legal
- Legal Title report1 Copy of the legal title report (34) (1).pdf · uploaded 3 Mar 2025Source
- Declaration Form BForm B (1).pdf · uploaded 3 Mar 2025Source
- Other – LegalSale Deed_compressed.pdf · uploaded 16 Apr 2025Source
- Legal Title reportCamScanner 08-11-2025 _compressed_compressed-8-24.pdf · uploaded 12 Aug 2025Source
- Other – Legalशिंदवणे_865_Satbara (4).pdf · uploaded 15 Sep 2025Source
Show all 54 documentsShow fewer documents
Legal
- Other – Legalशिंदवणे_866_3_1_Satbara.pdf · uploaded 15 Sep 2025Source
Migrated
- 1 PAN Card1 PAN Card (6).pdf · uploaded 3 Mar 2025Source
- 1 Copy of the legal title report1 Copy of the legal title report (34) (1).pdf · uploaded 3 Mar 2025Source
- 1 Copy of Layout Approval (in case of layout)scan1681_compressed.pdf · uploaded 3 Mar 2025Source
- 1 Proforma of Allotment letter1 Proforma of Allotment letter (7) (1).pdf · uploaded 3 Mar 2025Source
- 1 Declaration in FORM BForm B (1).pdf · uploaded 3 Mar 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 (5).pdf · uploaded 3 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)IMG_0001 (1)_compressed (1).pdf · uploaded 3 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Krushnakunj.pdf · uploaded 3 Mar 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentnew cc.pdf · uploaded 3 Mar 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentscan1681_compressed.pdf · uploaded 3 Mar 2025Source
- 1 Declaration about Commencement Certificate1 Declaration about Commencement Certificate (20) (2).pdf · uploaded 3 Mar 2025Source
- 1 CERSAI detailsCersai (1).pdf · uploaded 3 Mar 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A-Bank.pdf · uploaded 3 Mar 2025Source
- 1 Deviation Report with respect to Allotment letter1 Deviation Report with respect to Allotment letter (6) (1).pdf · uploaded 3 Mar 2025Source
- 1 Other – Technical5 (65) (1).pdf · uploaded 3 Mar 2025Source
- 1 Deviation Report with respect to model copy of Agreement1 Deviation Report with respect to model copy of Agreement (6) (1).pdf · uploaded 3 Mar 2025Source
- 1 Proforma of Agreement for saleAFS-Plotting.pdf · uploaded 3 Mar 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A-Amit H.pdf · uploaded 3 Mar 2025Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 3 Mar 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Heera Developer (1).pdf · uploaded 3 Mar 2025Source
- 1 Disclosure for secured/unsecured finance availed for the project1 Disclosure for secured_unsecured finance availed for the project (3) (1).pdf · uploaded 3 Mar 2025Source
- 1 Other – LegalSale Deed_compressed.pdf · uploaded 16 Apr 2025Source
- 2 Commencement Certificates / NA Order for plotted developmentEmail - Heera Developer CC.pdf · uploaded 7 Aug 2025Source
- 2 Copy of the legal title reportCamScanner 08-11-2025 _compressed_compressed-8-24.pdf · uploaded 12 Aug 2025Source
- 1 a Details of encumbrances concerned to Finance1 a Details of encumbrances concerned to Finance (19) (1).pdf · uploaded 12 Aug 2025Source
- 1 b Details of encumbrances concerned to Legal1 a Details of encumbrances concerned to Finance (19) (1).pdf · uploaded 12 Aug 2025Source
- 2 a Details of encumbrances concerned to Finance3 a Details of encumbrances concerned to Finance.pdf · uploaded 15 Sep 2025Source
- 2 Other – Legalशिंदवणे_865_Satbara (4).pdf · uploaded 15 Sep 2025Source
- 3 Other – Legalशिंदवणे_866_3_1_Satbara.pdf · uploaded 15 Sep 2025Source
- 2 b Details of encumbrances concerned to Legal3 a Details of encumbrances concerned to Finance.pdf · uploaded 15 Sep 2025Source
- Form 1866.pdf · uploaded 20 Jan 2026Source
- Form 2Form 2- Phase 2 1.pdf · uploaded 20 Jan 2026Source
- Form 3F3-PHASE-2 (1).pdf · uploaded 20 Jan 2026Source
- Disclosure of Sold and Booked Inventory866.pdf · uploaded 20 Jan 2026View
- Withdrawal Update Form 1ARCHITECT CERTIFICATE SHINDWANE PHASE-2 (2).pdf · uploaded 21 Apr 2026Source
- Withdrawal Update Form 2F2 Heera Dev Phase 2 PLOT.pdf · uploaded 21 Apr 2026Source
- Withdrawal Update Form 3F3-HEERA DEVELOPERS (2).pdf · uploaded 21 Apr 2026Source
- Withdrawal Update Form 1Architect Certificate Village - Shidavane Tal - Haveli Gat No - 865(P).pdf · uploaded 16 Jul 2026Source
- Withdrawal Update Form 2Withdrawal Application Form2 (37) (1).pdf · uploaded 16 Jul 2026Source
- Withdrawal Update Form 3F 3 - HEERA DEVLOPERS (1).pdf · uploaded 16 Jul 2026Source
Technical
Technical (Architect)
- DocumentArchitect Certificate Village - Shidavane Tal - Haveli Gat No - 865(P).pdf · uploaded 16 Jul 2026Source
Technical (Engineer)
- DocumentWithdrawal Application Form2 (37) (1).pdf · uploaded 16 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 866/3/1 (P), Gat no 865 (P)
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- Gat no 865 (P), 866/3/1 (P), Shindvane, ShindwanePIN 412202
- Village
- Shindvane, Haveli taluka
- Location
- 18.42747, 74.12706
- Land area for this project
- 18,853 sq m (2,02,932 sq ft)
- Permissible built-up area
- 0 sq m (0 sq ft)
- Sanctioned built-up area
- 0 sq m (0 sq ft)
- Recreational open space
- 4,382 sq m (47,166 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Gat no 865 (P), 866/3/1 (P)
Boundaries
- North
- By Gairan Gaothan and Road
- South
- By remaining property out of Gat no 865
- East
- By nala
- West
- By Property owned by present Gat no 866 3
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Rao Arch | — |
| Chartered accountant | CA Pravin Pise and Associates | — |
| Engineer | Rutuja Jagdale | — |
Source: MahaRERA project page. Contact details are not shown.