Skip to content
Others · 2 buildings · 140 unitsRERA P52100078594

Jp Tower

Deedo IDDP-PUN-DHV3

Completion was pushed back 4 months, to Sep 2027; no MahaRERA orders on record; 4% of its units are booked.

Sasvad (M Cl), Pune 412301 · by Jp Buildcon

DeliveryExtended 4 moPromised May 2027 · now due Sep 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales4% booked5 of 140 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Sep 2027

  • This projectRegistered 27 Dec 2024, completion promised 31 May 2027, revised to 30 Sep 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100078594
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210007859427 Dec 202431 May 202730 Sep 2027Jp BuildconProject page
Documents73

1 document held by Deedo, 72 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN JP BUILDCON.pdf · uploaded 21 Jun 2024Source
  • Other – FinanceBANK DECLARATION LANDOWNER FINAL.pdf · uploaded 28 Nov 2024Source
  • Other – FinanceFINAL ASR NIL DECLARATION.pdf · uploaded 6 Dec 2024Source

Legal

  • Declaration Form BForm B JP Buidlcon.pdf · uploaded 24 Jun 2024Source
  • Legal Title reportTITILE REPORT_compressed.pdf · uploaded 23 Nov 2024Source
  • Other – LegalPages from HAKKASODPATRA(1).pdf · uploaded 6 Dec 2024Source
  • Other – LegalPages from HAKKASODPATRA.pdf · uploaded 6 Dec 2024Source
Show all 73 documentsShow fewer documents

Migrated

  • 1 PAN CardPAN JP BUILDCON.pdf · uploaded 21 Jun 2024Source
  • 1 Copy of Layout Approval (in case of layout)Signed plan.pdf · uploaded 21 Jun 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentSigned plan.pdf · uploaded 21 Jun 2024Source
  • 1 Declaration in FORM BForm B JP Buidlcon.pdf · uploaded 24 Jun 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentMerged CC and NOC.pdf · uploaded 24 Jun 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Signed.pdf · uploaded 18 Jul 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Signed.pdf · uploaded 18 Jul 2024Source
  • 1 Declaration about Commencement CertificateNo 08 Format D.pdf · uploaded 18 Jul 2024Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION REPORT OF AGREEMENT.pdf · uploaded 18 Oct 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT OF AGREEMENT.pdf · uploaded 18 Oct 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDISCLOSURE OF SECURED AND UNSECURED FINANCE.pdf · uploaded 18 Oct 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC CLARIFICATION.pdf · uploaded 7 Nov 2024Source
  • 1 a Details of encumbrances concerned to FinanceENCUMBRANCES DETAILS.pdf · uploaded 9 Nov 2024Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 9 Nov 2024Source
  • 1 CERSAI detailsCERSAI DETAILS.pdf · uploaded 9 Nov 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT A.pdf · uploaded 9 Nov 2024Source
  • 1 b Details of encumbrances concerned to LegalENCUMBRANCES DETAILS.pdf · uploaded 9 Nov 2024Source
  • 1 Other – TechnicalANNEXURE A.pdf · uploaded 9 Nov 2024Source
  • 1 Proforma of Agreement for saleAGREEMENT FOR SELL.pdf · uploaded 9 Nov 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST - VIKAS.pdf · uploaded 9 Nov 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST KAILASHKUMAR.pdf · uploaded 9 Nov 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST SHUBHANGI.pdf · uploaded 9 Nov 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)FORMAT B.pdf · uploaded 9 Nov 2024Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST BHAGUJI.pdf · uploaded 12 Nov 2024Source
  • 1 Copy of the legal title reportTITILE REPORT_compressed.pdf · uploaded 23 Nov 2024Source
  • 1 Other – FinanceBANK DECLARATION LANDOWNER FINAL.pdf · uploaded 28 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FINAL FORM 3.pdf · uploaded 6 Dec 2024Source
  • 1 Other – LegalPages from HAKKASODPATRA.pdf · uploaded 6 Dec 2024Source
  • 2 Other – LegalPages from HAKKASODPATRA(1).pdf · uploaded 6 Dec 2024Source
  • 2 Other – FinanceFINAL ASR NIL DECLARATION.pdf · uploaded 6 Dec 2024Source
  • Form 1Form 1 dec 2024.pdf · uploaded 12 Jun 2025Source
  • Form 2Form 2 dec 2024.pdf · uploaded 12 Jun 2025Source
  • Form 3Form 3 as on 31-12-2024.pdf · uploaded 12 Jun 2025Source
  • Disclosure of Sold and Booked InventoryDisclocure of sold Inventory December 2024.pdf · uploaded 12 Jun 2025Source
  • Self-declaration of Quarterly ProgressSelf Decleration December.pdf · uploaded 12 Jun 2025Source
  • Form 1Form 1 march 2025.pdf · uploaded 12 Jun 2025Source
  • Form 2Form 2 - march 2025.pdf · uploaded 12 Jun 2025Source
  • Form 3Form 3 - march 2025.pdf · uploaded 12 Jun 2025Source
  • Disclosure of Sold and Booked InventoryDisclocure of sold Inventory March 2025.pdf · uploaded 12 Jun 2025Source
  • Self-declaration of Quarterly ProgressSelf Decleration March.pdf · uploaded 12 Jun 2025Source
  • Withdrawal Update Form 1Form-1 Signed.pdf · uploaded 25 Aug 2025Source
  • Withdrawal Update Form 2Form-2 Signed.pdf · uploaded 25 Aug 2025Source
  • Withdrawal Update Form 3Form -3 - June 2025 JP Buildcon.pdf · uploaded 25 Aug 2025Source
  • Form 5 (FY 2024-2025)FORM 5 SIGNED SCAN COPY.pdf · uploaded 30 Sep 2025Source
  • Withdrawal Update Form 1Form 1 SCANNED COPY.pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 2Form 2 SCANNED COPY.pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 3Form 3 SCANNED COPY.pdf · uploaded 3 Nov 2025Source
  • Withdrawal Update Form 1form 1 dec 2025 signed.pdf · uploaded 29 Jan 2026Source
  • Withdrawal Update Form 2form 2 dec 2025 signed.pdf · uploaded 29 Jan 2026Source
  • Withdrawal Update Form 3form 3 dec 2025 signed.pdf · uploaded 29 Jan 2026Source
  • Withdrawal Update Form 1Form 1 Final.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 2Form 2 Final Change.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 3Form - 3 Final.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 1Form - 1_JP TOWERS June 2026 sigend by promotors.pdf · uploaded 19 Jul 2026Source
  • Withdrawal Update Form 1Form - 1_JP TOWERS June 2026 sigend by promotors.pdf · uploaded 19 Jul 2026Source
  • Withdrawal Update Form 2Form - 2_JP TOWERS June 2026 signed by promotor.pdf · uploaded 19 Jul 2026Source
  • Withdrawal Update Form 2Form - 2_JP TOWERS June 2026 signed by promotor.pdf · uploaded 19 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - JP Tower FROM CA sitgned by promotor.pdf · uploaded 19 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - JP Tower FROM CA sitgned by promotor.pdf · uploaded 19 Jul 2026Source
  • Form 5 (FY 2025-2026)Rera Form 5 SIGNED FY 2025-26.pdf · uploaded 16 Sep 2026Source

Technical

  • DocumentSigned plan.pdf · uploaded 21 Jun 2024Source
  • DocumentSigned plan.pdf · uploaded 21 Jun 2024Source
  • Other – TechnicalANNEXURE A.pdf · uploaded 9 Nov 2024Source

Technical (Architect)

  • DocumentForm - 1_JP TOWERS June 2026 sigend by promotors.pdf · uploaded 19 Jul 2026Source

Technical (Engineer)

  • DocumentForm - 2_JP TOWERS June 2026 signed by promotor.pdf · uploaded 19 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NO. 90/1A/1/1/3A/1

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
—140 units in all
Address
SURVEY NO. 90/1A/1/1/3A/1, Saswad Pargaon Road, SaswadPIN 412301
Village
Sasvad (M Cl), Purandhar taluka
Land area for this project
2,249 sq m (24,210 sq ft)
Permissible built-up area
6,009 sq m (64,675 sq ft)
Sanctioned built-up area
6,009 sq m (64,675 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
85
Developed in phases
Yes

Survey, CTS, gat or plot numbers

SURVEY NO. 90/1A/1/1/3A/1

Land as published on MahaRERA's project page

SURVEY NO. 90/1A/1/1/3A/1

Boundaries

North
12 meter Saswad Pargaon Road
South
Land of Pravin S Bhandari and Pune PAndarapur Road
East
Land Suryakant S Zurange and Pravin S Bhandari
West
UDYAM Bizhub

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking140 units

140 units registered

— · 140 units
BuildingTypeCarpet areaUnits
Jp Tower A——61
Jp Tower B——79

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectYogesh Borhade—
Chartered accountantMahesh Balaprasad Indani—
EngineerYogesh Borhade—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology