Residential / Group Housing · 1 building · 140 unitsRERA P52100002143

Bhalchandra Puram

Deedo IDDP-PUN-F49X

MahaRERA shows it completed, after its date was pushed back 1 year and 6 months; no MahaRERA orders on record; 100% of its units are booked.

Ravet, Pune 412101 · Property rates in Ravet · by Polite Buildwell

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 1 yr 6 mo extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked140 of 140 units · as the promoter reported to MahaRERAPrice₹8,000 /sq ft3.6% below Ravet · 150 registered sales

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year and 6 months

  • This projectRegistered 31 Jul 2017, completion promised 30 Jun 2019, revised to 30 Dec 2020.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

All 194 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Sep 2026A · 916Primary sale383 sq ftView Primary sale, Sep 2026
Jun 2026A · 710Resale357 sq ftView Resale, Jun 2026
Mar 2026A · 710Primary sale357 sq ftView Primary sale, Mar 2026
Jan 2026A · 110Resale—View Resale, Jan 2026
Dec 2025A · 516Other384 sq ftView Other, Dec 2025
Oct 2025A · 508Mortgage—View Mortgage, Oct 2025
May 2025A · 602Resale332 sq ftView Resale, May 2025
Mar 2025A · 602Primary sale332 sq ftView Primary sale, Mar 2025
Nov 2024A · 607Resale330 sq ftView Resale, Nov 2024
Oct 2024A · 607Primary sale330 sq ftView Primary sale, Oct 2024

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100002143
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210000214331 Jul 201730 Jun 201930 Dec 2020Polite BuildwellProject page
Documents45

2 documents held by Deedo, 43 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPOLITE BUILDWELL PAN CARD.pdf · uploaded 26 Jul 2017Source

Legal

  • OtherEASEMENT AGREEMENT DOC NO-7728-2016.pdf · uploaded 26 Jul 2017Source
  • OtherEASEMENT AGREEMENT DOC NO 7727 2016.pdf · uploaded 26 Jul 2017Source
  • Declaration Form BFORM B Bhalchandra Puram.pdf · uploaded 26 Jul 2017Source
  • Legal Title reportREVISED Search Report POLITE BUILDWELL 17112016.pdf · uploaded 26 Jul 2017Source

Migrated

  • 1 PAN CardPOLITE BUILDWELL PAN CARD.pdf · uploaded 26 Jul 2017Source
Show all 45 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportREVISED Search Report POLITE BUILDWELL 17112016.pdf · uploaded 26 Jul 2017Source
  • 1 Details of encumbrancesEncumbrances Bhalchandra Puram.pdf · uploaded 26 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)IOD 133.pdf · uploaded 26 Jul 2017Source
  • 1 Building Plan Approval (IOD)IOD 133.pdf · uploaded 26 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentSR NO CC 57 DT 20082015 POLITE BUILDWELL.pdf · uploaded 26 Jul 2017Source
  • 2 Commencement Certificates / NA Order for plotted developmentC C NEW 02072016 POLITE BUILDWELL.pdf · uploaded 26 Jul 2017Source
  • 1 Declaration in FORM BFORM B Bhalchandra Puram.pdf · uploaded 26 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 Architect Certificate Bhalchandra Puram.pdf · uploaded 26 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 26 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA Certificate Puram.pdf · uploaded 26 Jul 2017Source
  • 1 Proforma of Allotment letterAGREEMENT TO SALE BHALCHANDRA PURAM.pdf · uploaded 26 Jul 2017Source
  • 2 Proforma of Allotment letterAllotment Letter- RERA- 133.pdf · uploaded 26 Jul 2017Source
  • 1 OtherEASEMENT AGREEMENT DOC NO-7728-2016.pdf · uploaded 26 Jul 2017Source
  • 2 OtherEASEMENT AGREEMENT DOC NO 7727 2016.pdf · uploaded 26 Jul 2017Source
  • 3 Proforma of Allotment letter2 AGREEMENT TO SALE BHALCHANDRA PURAM.pdf · uploaded 5 Nov 2017Source
  • 4 Proforma of Allotment letter2 Allotment Letter RERA BHALCHANDRA PURAM.pdf · uploaded 5 Nov 2017Source
  • 5 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 11 Jul 2018Source
  • 1 Certificates of CA (Form 5)POLITE BUILDWELL (RERA ANNUAL AUDIT REPORT).pdf · uploaded 29 Sep 2018Source
  • 2 Copy of Layout Approval (in case of layout)Sanctiond Plan.PDF · uploaded 5 Jan 2019Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 5 Jan 2019Source
  • 3 Copy of Layout Approval (in case of layout)Sanctioned Plan 11012019.pdf · uploaded 21 Jan 2019Source
  • 4 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 21 Jan 2019Source
  • 6 Proforma of Allotment letterAgreement To Sale.pdf · uploaded 4 May 2019Source
  • 7 Proforma of Allotment letterALLOTMENT LETTER RERA.pdf · uploaded 4 May 2019Source
  • 2 Certificates of CA (Form 5)Form 5 CA Annual Report.pdf · uploaded 25 Sep 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION CERTIFICATE.pdf · uploaded 25 Sep 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)ARCHITECH CERIFICATE OF BUILDING COMPLETION.pdf · uploaded 28 Sep 2020Source
  • 3 Certificates of CA (Form 5)Polite Buildwell.pdf · uploaded 10 Oct 2020Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Bhalchandra Puram CO OP HSG SOCIETY Certificate.pdf · uploaded 19 Dec 2020Source
  • 4 Certificates of CA (Form 5)CA Certificate Form 5.pdf · uploaded 17 Dec 2021Source
  • 1 Status of ConveyanceCONVEYANCE DEED.pdf · uploaded 18 Jul 2024Source

Technical

  • DocumentIOD 133.pdf · uploaded 26 Jul 2017Source
  • DocumentIOD 133.pdf · uploaded 26 Jul 2017Source
  • DocumentSanctiond Plan.PDF · uploaded 5 Jan 2019Source
  • DocumentSanctioned Plan 11012019.pdf · uploaded 21 Jan 2019Source

Technical (Architect)

  • DocumentFORM 1 Architect Certificate Bhalchandra Puram.pdf · uploaded 26 Jul 2017Source

Technical (Engineer)

  • DocumentEngineer Certificate.pdf · uploaded 26 Jul 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 133/11 PART, 133/13 PART

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK140 units in all
Address
133/11 Part, 133/13 Part, 133/16, Near Shinde Wasti Chowk, RavetPIN 412101
Village
Pimpri Chinchawad (M Corp.), Haveli taluka
Land area for this project
3,600 sq m (38,750 sq ft)
Permissible built-up area
5,939 sq m (63,929 sq ft)
Sanctioned built-up area
5,471 sq m (58,892 sq ft)
Recreational open space
370 sq m (3,977 sq ft)
Designated bank account
109
Developed in phases
No

Survey, CTS, gat or plot numbers

133/11 PART133/13 PART133/16

Land as published on MahaRERA's project page

133/11 PART, 133/13 PART, 133/16

Boundaries

North
Road And Remaining Part Property Of Survey No 133
South
By Remaining Property Out Of Survey No 133
East
By Remaining Property Out Of Survey No 133
West
By Remaining Property Out Of Survey No 133

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking140 units

140 of 140 units booked (100%), as the promoter reported to MahaRERA

1BHK · 105 units2BHK · 35 units
TypeCarpet areaUnitsBooked
1BHK30.7 sq m · 330 sq ft1414
1BHK30.72 sq m · 331 sq ft1616
1BHK30.87 sq m · 332 sq ft77
1BHK33.14 sq m · 357 sq ft1616
1BHK35.62 sq m · 383 sq ft88
1BHK35.63 sq m · 384 sq ft3636
1BHK35.91 sq m · 387 sq ft88
2BHK37.92 sq m · 408 sq ft88
Show all 11 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK40.85 sq m · 440 sq ft1212
2BHK43.38 sq m · 467 sq ft77
2BHK46.22 sq m · 498 sq ft88

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMahendra thakur And Associates—
Chartered accountantV C A N & Associates LLP chartered Accountants CA Manatu S Kumbhar—
EngineerAjinkya A Lahigude—
OtherMEP system solutions PVT LTD—
OtherRavindra A. Karnavat—

Source: MahaRERA project page. Contact details are not shown.

Bhalchandra Puram in numbers

Registered deals, summarised

Deedo has 194 registered documents at Bhalchandra Puram, from Sep 2016 to Sep 2026: 150 sales, 1 leave and licence agreement, 40 mortgages. The median registered sale since Sep 2016 works out to about ₹8,000 per sq ft, at a median of ₹30 L a deal; 7% of sales were resales.

What is the price per sq ft at Bhalchandra Puram?
The median registered sale since Sep 2016 works out to about ₹8,000 per sq ft, at a median of ₹30 L a deal; 7% of sales were resales.
How many properties have been sold at Bhalchandra Puram?
150 sales are registered at Bhalchandra Puram, 11 of them resales.
Are properties at Bhalchandra Puram rented out?
Yes: 1 leave and licence agreement is registered at Bhalchandra Puram.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Bhalchandra Puram by Deedo, last updated with deals registered in Sep 2026.

Latest deal · Primary sale · Sep 2026

₹25–50 L

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology