Skip to content
Others · 4 buildings · 138 unitsRERA P52100046815

Bhalchandra Blessings

Deedo IDDP-PUN-RF55

MahaRERA shows it completed; no MahaRERA orders on record; 89% of its units are booked.

Ravet, Pune 412101 · Property rates in Ravet · by N B Bhondave Infra

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales89% booked123 of 138 units · as the promoter reported to MahaRERAPrice₹8,620 /sq ft3.9% above Ravet · 138 registered sales

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 10 Sep 2022, completion promised 31 Dec 2025.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

All 147 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Aug 2026Not on recordResale227 sq ftView Resale, Aug 2026
May 2026In the buildingResale227 sq ftView Resale, May 2026
Mar 2026Not on recordMortgage—View Mortgage, Mar 2026
Dec 2025Not on recordMortgage—View Mortgage, Dec 2025
Jul 2025Main building · 104Primary sale673 sq ftView Primary sale, Jul 2025
Jun 2025Main building · 2605Primary sale668 sq ftView Primary sale, Jun 2025
Jan 2025Main building · 204Primary sale673 sq ftView Primary sale, Jan 2025
Dec 2024Main building · 2604Primary sale673 sq ftView Primary sale, Dec 2024
Nov 2024Not on recordMortgage—View Mortgage, Nov 2024
Oct 2024Main building · 2104Primary sale673 sq ftView Primary sale, Oct 2024

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100046815
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210004681510 Sep 202231 Dec 202531 Dec 2025N B Bhondave InfraProject page
Documents153

2 documents held by Deedo, 151 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPan Card.pdf · uploaded 18 Aug 2022Source

Legal

  • Legal Title reportLegal Search.pdf · uploaded 18 Aug 2022Source
  • Declaration Form BForm B.pdf · uploaded 18 Aug 2022Source

Migrated

  • 1 PAN CardPan Card.pdf · uploaded 18 Aug 2022Source
  • 1 Copy of the legal title reportLegal Search.pdf · uploaded 18 Aug 2022Source
  • 1 a Details of encumbrances concerned to FinanceNo Encumbrance concerned to finance .pdf · uploaded 18 Aug 2022Source
Show all 153 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to LegalNo Encumbrance concerned to legal.pdf · uploaded 18 Aug 2022Source
  • 1 Copy of Layout Approval (in case of layout)Plan 010101.pdf · uploaded 18 Aug 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 03.pdf · uploaded 18 Aug 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan 04.pdf · uploaded 18 Aug 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan 02.pdf · uploaded 18 Aug 2022Source
  • 4 Building Plan Approval / NA Order for plotted developmentPlan 06.pdf · uploaded 18 Aug 2022Source
  • 5 Building Plan Approval / NA Order for plotted developmentPlan 07.pdf · uploaded 18 Aug 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentC C.pdf · uploaded 18 Aug 2022Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 18 Aug 2022Source
  • 1 CERSAI detailsCERSAI Report .pdf · uploaded 18 Aug 2022Source
  • 2 CERSAI detailsCERSAI_Search_Report_.pdf · uploaded 18 Aug 2022Source
  • 1 Proforma of Allotment letterANNEXURE ALLOTMENT LETTER.pdf · uploaded 18 Aug 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report for Allotment.pdf · uploaded 18 Aug 2022Source
  • 1 Declaration about Commencement CertificateDeclaration CC.pdf · uploaded 20 Aug 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1-.pdf · uploaded 20 Aug 2022Source
  • 1 Disclosure of sold/ booked inventoryBhalchandra blessings Inventory .pdf · uploaded 20 Aug 2022View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 New.pdf · uploaded 20 Aug 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat 'A'.pdf · uploaded 20 Aug 2022Source
  • 2 Proforma of Allotment letterATS.pdf · uploaded 29 Aug 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report 29-08-2022 FINAL_compressed.pdf · uploaded 29 Aug 2022Source
  • 3 Proforma of Allotment letterDraft Agreement to Sale Model Bhalchandra Blessings Commercial.pdf · uploaded 27 Sep 2022Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same70 Bank Account 27-09-2022.pdf · uploaded 27 Sep 2022Source
  • 2 Copy of Layout Approval (in case of layout)Santioned Layout.pdf · uploaded 15 Dec 2022Source
  • 6 Building Plan Approval / NA Order for plotted development1.pdf · uploaded 15 Dec 2022Source
  • 7 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 15 Dec 2022Source
  • 8 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 15 Dec 2022Source
  • 9 Building Plan Approval / NA Order for plotted development4.pdf · uploaded 15 Dec 2022Source
  • 10 Building Plan Approval / NA Order for plotted development5.pdf · uploaded 15 Dec 2022Source
  • 11 Building Plan Approval / NA Order for plotted development6.pdf · uploaded 15 Dec 2022Source
  • 12 Building Plan Approval / NA Order for plotted development7.pdf · uploaded 15 Dec 2022Source
  • 13 Building Plan Approval / NA Order for plotted development8.pdf · uploaded 15 Dec 2022Source
  • 14 Building Plan Approval / NA Order for plotted development9.pdf · uploaded 15 Dec 2022Source
  • 15 Building Plan Approval / NA Order for plotted development10.pdf · uploaded 15 Dec 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencement certificate .pdf · uploaded 15 Dec 2022Source
  • 2 Declaration about Commencement CertificateCommencement certificate .pdf · uploaded 15 Dec 2022Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Finance 05-01-2023.pdf · uploaded 8 Jan 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Finance 05-01-2023.pdf · uploaded 8 Jan 2023Source
  • 1 Proforma of Agreement for saleDraft Agreement to sale Residentinal.pdf · uploaded 24 Jan 2023Source
  • 2 Proforma of Agreement for saleDraft Agreement to sale Commercial.pdf · uploaded 24 Jan 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)From 1.pdf · uploaded 11 Feb 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Bhalchandra Blessings Form 2.pdf · uploaded 11 Feb 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)N B Bhondave Infra Form 3.pdf · uploaded 11 Feb 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 19 Jun 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate.PDF · uploaded 19 Jun 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Form-3.PDF · uploaded 19 Jun 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 21 Aug 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)From 2.pdf · uploaded 21 Aug 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)From 3.pdf · uploaded 21 Aug 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)From 5.pdf · uploaded 2 Sep 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form - 2A 22-23.pdf · uploaded 8 Sep 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 16 Oct 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)From 3 Scan.pdf · uploaded 16 Oct 2023Source
  • 3 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 21 Nov 2023Source
  • 16 Building Plan Approval / NA Order for plotted developmentscan0000005814.pdf · uploaded 21 Nov 2023Source
  • 17 Building Plan Approval / NA Order for plotted developmentscan0000005815.pdf · uploaded 21 Nov 2023Source
  • 18 Building Plan Approval / NA Order for plotted developmentscan0000005816.pdf · uploaded 21 Nov 2023Source
  • 19 Building Plan Approval / NA Order for plotted developmentscan0000005817.pdf · uploaded 21 Nov 2023Source
  • 20 Building Plan Approval / NA Order for plotted developmentscan0000005818.pdf · uploaded 21 Nov 2023Source
  • 21 Building Plan Approval / NA Order for plotted developmentscan0000005819.pdf · uploaded 21 Nov 2023Source
  • 22 Building Plan Approval / NA Order for plotted developmentscan0000005820.pdf · uploaded 21 Nov 2023Source
  • 23 Building Plan Approval / NA Order for plotted developmentscan0000005821.pdf · uploaded 21 Nov 2023Source
  • 24 Building Plan Approval / NA Order for plotted developmentscan0000005822.pdf · uploaded 21 Nov 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 21 Nov 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.PDF · uploaded 15 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)BLESSINGS ( 31-12-23) Form 2.pdf · uploaded 15 Jan 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 15 Jan 2024Source
  • 4 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 17 Feb 2024Source
  • 25 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 17 Feb 2024Source
  • 26 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 17 Feb 2024Source
  • 27 Building Plan Approval / NA Order for plotted development4.pdf · uploaded 17 Feb 2024Source
  • 28 Building Plan Approval / NA Order for plotted development5.pdf · uploaded 17 Feb 2024Source
  • 29 Building Plan Approval / NA Order for plotted development6.pdf · uploaded 17 Feb 2024Source
  • 30 Building Plan Approval / NA Order for plotted development7.pdf · uploaded 17 Feb 2024Source
  • 31 Building Plan Approval / NA Order for plotted development8.pdf · uploaded 17 Feb 2024Source
  • 32 Building Plan Approval / NA Order for plotted development9.pdf · uploaded 17 Feb 2024Source
  • 33 Building Plan Approval / NA Order for plotted development10.pdf · uploaded 17 Feb 2024Source
  • 4 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 17 Feb 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Blessing.PDF · uploaded 22 Apr 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Blessings.pdf · uploaded 22 Apr 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 22 Apr 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Jul 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Jul 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 14 Jul 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentSR 181 FULL COMPLETION 1.pdf · uploaded 14 Aug 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentForm 4.pdf · uploaded 7 Oct 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentForm 4.pdf · uploaded 7 Oct 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentForm 4.pdf · uploaded 7 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.PDF · uploaded 11 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 11 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 5.PDF · uploaded 11 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.PDF · uploaded 11 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 11 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 5.PDF · uploaded 11 Oct 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 11 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 11 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.PDF · uploaded 11 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 5.PDF · uploaded 11 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.PDF · uploaded 14 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.PDF · uploaded 14 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.PDF · uploaded 14 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 New.pdf · uploaded 15 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 New.pdf · uploaded 15 Oct 2024Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 New.pdf · uploaded 15 Oct 2024Source

Technical

  • DocumentPlan 010101.pdf · uploaded 18 Aug 2022Source
  • DocumentPlan 03.pdf · uploaded 18 Aug 2022Source
  • DocumentPlan 04.pdf · uploaded 18 Aug 2022Source
  • DocumentPlan 02.pdf · uploaded 18 Aug 2022Source
  • DocumentPlan 06.pdf · uploaded 18 Aug 2022Source
  • DocumentPlan 07.pdf · uploaded 18 Aug 2022Source
  • DocumentSantioned Layout.pdf · uploaded 15 Dec 2022Source
  • Document1.pdf · uploaded 15 Dec 2022Source
  • Document2.pdf · uploaded 15 Dec 2022Source
  • Document3.pdf · uploaded 15 Dec 2022Source
  • Document4.pdf · uploaded 15 Dec 2022Source
  • Document5.pdf · uploaded 15 Dec 2022Source
  • Document6.pdf · uploaded 15 Dec 2022Source
  • Document7.pdf · uploaded 15 Dec 2022Source
  • Document8.pdf · uploaded 15 Dec 2022Source
  • Document9.pdf · uploaded 15 Dec 2022Source
  • Document10.pdf · uploaded 15 Dec 2022Source
  • Documentscan0000005814.pdf · uploaded 21 Nov 2023Source
  • Documentscan0000005815.pdf · uploaded 21 Nov 2023Source
  • Documentscan0000005816.pdf · uploaded 21 Nov 2023Source
  • Documentscan0000005817.pdf · uploaded 21 Nov 2023Source
  • Documentscan0000005818.pdf · uploaded 21 Nov 2023Source
  • Documentscan0000005819.pdf · uploaded 21 Nov 2023Source
  • Documentscan0000005820.pdf · uploaded 21 Nov 2023Source
  • Documentscan0000005821.pdf · uploaded 21 Nov 2023Source
  • Documentscan0000005822.pdf · uploaded 21 Nov 2023Source
  • DocumentLayout.pdf · uploaded 21 Nov 2023Source
  • Document8.pdf · uploaded 17 Feb 2024Source
  • Document9.pdf · uploaded 17 Feb 2024Source
  • Document10.pdf · uploaded 17 Feb 2024Source
  • Document2.pdf · uploaded 17 Feb 2024Source
  • Document3.pdf · uploaded 17 Feb 2024Source
  • Document4.pdf · uploaded 17 Feb 2024Source
  • Document5.pdf · uploaded 17 Feb 2024Source
  • Document6.pdf · uploaded 17 Feb 2024Source
  • Document7.pdf · uploaded 17 Feb 2024Source
  • DocumentLayout.pdf · uploaded 17 Feb 2024Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 14 Jul 2024Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 14 Jul 2024Source
  • DocumentForm 2.PDF · uploaded 11 Oct 2024Source
  • DocumentForm 2.PDF · uploaded 11 Oct 2024Source
  • DocumentForm 2.PDF · uploaded 11 Oct 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NUMBER 181/3 A

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
Shop, 2BHK138 units in all
Address
Survey Number 181/3 A, Ravet, Beside Bhondve Empire, ShindewastiPIN 412101
Village
Ravet, Haveli taluka
Land area for this project
3,336 sq m (35,904 sq ft)
Permissible built-up area
13,726 sq m (1,47,748 sq ft)
Sanctioned built-up area
13,726 sq m (1,47,747 sq ft)
Designated bank account
17
Developed in phases
Yes
Also registered as
Bhalachandr Blesings, भालचंद्र ब्लेसिंग्स, Bhalachandra Blesings

Survey, CTS, gat or plot numbers

SURVEY NUMBER 181/3 A

Land as published on MahaRERA's project page

SURVEY NUMBER 181/3 A, RAVET

Boundaries

North
Remaining Part Of Survey Number 181 1a
South
Remaining Part Of Survey Number 181 2
East
M I D C Pipe Line Road
West
Remaining Part Of Survey Number 181 3a 1

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking138 units

123 of 138 units booked (89%), as the promoter reported to MahaRERA

Shop · 8 units2BHK · 130 units
BuildingTypeCarpet areaUnitsBooked
CommercialShop31.41 sq m · 338 sq ft88
Residential2BHK58.03 sq m · 625 sq ft54
Residential2BHK62 sq m · 667 sq ft2621
Residential2BHK62.09 sq m · 668 sq ft2625
Residential2BHK62.2 sq m · 670 sq ft2625
Residential2BHK62.33 sq m · 671 sq ft2121
Residential2BHK62.56 sq m · 673 sq ft2619

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShailendra Ghorpade And Associates—
Chartered accountantVinit D Achha And Associates—
EngineerAvinash Hole—

Source: MahaRERA project page. Contact details are not shown.

Bhalchandra Blessings in numbers

Registered deals, summarised

Deedo has 147 registered documents at Bhalchandra Blessings, from Oct 2022 to Aug 2026: 138 sales, 5 mortgages. The median registered sale since Oct 2022 works out to about ₹8,600 per sq ft, at a median of ₹57 L a deal; 1% of sales were resales.

What is the price per sq ft at Bhalchandra Blessings?
The median registered sale since Oct 2022 works out to about ₹8,600 per sq ft, at a median of ₹57 L a deal; 1% of sales were resales.
How many properties have been sold at Bhalchandra Blessings?
138 sales are registered at Bhalchandra Blessings, 2 of them resales.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Bhalchandra Blessings by Deedo, last updated with deals registered in Aug 2026.

Latest deal · Resale · Aug 2026

₹50–75 L

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology