Skip to content
Others · 1 building · 132 unitsRERA P52100021569

Divine Dazzle -A

Deedo IDDP-PUN-F0E5

Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 49% of its units are booked.

Rahatani, Pune 411017 · by Shiv Associates · 60% of its projects kept the RERA date

Delivery1 yr 11 mo past duePromised Dec 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales49% booked65 of 132 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 8 Jul 2019, completion promised 30 Dec 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100021569
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000215698 Jul 201930 Dec 202430 Dec 2024Shiv AssociatesProject page
Documents59

1 document held by Deedo, 58 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Legal Title reportSEARCH REPORT -DVN DZL-BLDG-A.pdf · uploaded 27 Jun 2019Source
  • Declaration Form BDECLARATION -FORM-B-DIVINE DAZZLE -A.pdf · uploaded 5 Jul 2019Source

Migrated

  • 1 Copy of the legal title reportSEARCH REPORT -DVN DZL-BLDG-A.pdf · uploaded 27 Jun 2019Source
  • 1 Details of encumbrancesLETTER OF ENCUMBARANCE-Dvn Dzl A.pdf · uploaded 27 Jun 2019Source
  • 1 Copy of Layout Approval (in case of layout)DIVINE DAZZLE A - Layout.pdf · uploaded 27 Jun 2019Source
  • 1 Building Plan Approval (IOD)DIVINE DAZZLE -A-IOD.pdf · uploaded 27 Jun 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTF - DVN DZL-A.pdf · uploaded 27 Jun 2019Source
Show all 59 documentsShow fewer documents

Migrated

  • 1 Declaration in FORM BDECLARATION -FORM-B-DIVINE DAZZLE -A.pdf · uploaded 5 Jul 2019Source
  • 1 Certificates of CA (Form 3)CA Certf-DIVINE DAZZLE-A.pdf · uploaded 5 Jul 2019Source
  • 1 Proforma of Allotment letterDRAFT AGREEMENT-DIVINE DAZZLE -A-SHIV ASSOCIATES.pdf · uploaded 5 Jul 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)DIVINE DAZZLE-A- ARCHT CERTF.pdf · uploaded 17 Feb 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)DIVINE DAZZLE-A.pdf · uploaded 17 Feb 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)DIVINE DAZZLE -A - FORM-2A.pdf · uploaded 17 Feb 2020Source
  • 2 Certificates of CA (Form 3)DIVINE DAZZLE A.pdf · uploaded 2 Mar 2020Source
  • 2 Details of encumbrancesLTR OF ENCUMBARANCE-Divine Dazzle-A -2.pdf · uploaded 13 Aug 2020Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)DIVINE DAZZLE-A- ARCHT CERTF.pdf · uploaded 13 Feb 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)DIVINE DAZZLE-A.pdf · uploaded 13 Feb 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)DIVINE DAZZLE - A.pdf · uploaded 13 Feb 2021Source
  • 3 Certificates of CA (Form 3)Divine Dazzle- A-Dec20_RERA.pdf · uploaded 25 Feb 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 - DIVINE DAZZLE-A.pdf · uploaded 11 Mar 2021Source
  • 2 Copy of Layout Approval (in case of layout)1-5 layout-ss.pdf · uploaded 8 Jan 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT DVN DZL- A.pdf · uploaded 8 Jan 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 - DIVINE DAZZLE-A.pdf · uploaded 24 Feb 2022Source
  • 3 Copy of Layout Approval (in case of layout)LAY OUT- DVN DZL-A -13 FLR-ss.pdf · uploaded 31 Oct 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 - DIVINE DAZZLE-A - ss.pdf · uploaded 27 Jan 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)DIVINE DAZZLE - A - Arch Certf.pdf · uploaded 1 Feb 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)DIVINE DAZZLE - A - Arch Certf - ss.pdf · uploaded 1 Feb 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)DIVINE DAZZLE - A - Engg Certf.pdf · uploaded 1 Feb 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)DIVINE DAZZLE - A - Engg Certf-ss.pdf · uploaded 1 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)DIVINE DAZZLE - A - ss.pdf · uploaded 1 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)DIVINE DAZZLE - A - ss.pdf · uploaded 2 Feb 2023Source
  • 4 Certificates of CA (Form 3)Divine Dazzle A_Dec21_RERA-CA.pdf · uploaded 16 Feb 2023Source
  • 5 Certificates of CA (Form 3)Divine Dazzle A_Dec22_RERA-ss.pdf · uploaded 16 Feb 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)DIVINE DAZZLE - A - Engg Certf-March'23-ss -.pdf · uploaded 28 Aug 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)DIVINE DAZZLE - A - Engg Certf-June'23-ss -.pdf · uploaded 29 Aug 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)DIVINE DAZZLE - A - Arch Certf-March'23 - ss.pdf · uploaded 31 Aug 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)DIVINE DAZZLE - A - Arch Certf-June'23 - ss.pdf · uploaded 31 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2 A- Dvn Dzl -A--31-03-2023 -ss.pdf · uploaded 31 Aug 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2 A- Dvn Dzl -A-30-06-2023 - ss.pdf · uploaded 31 Aug 2023Source
  • 6 Certificates of CA (Form 3)Divine Dazzle A_March'23_RERA-ss.pdf · uploaded 28 Oct 2023Source
  • 7 Certificates of CA (Form 3)Divine Dazzle A_June'23_RERA-ss.pdf · uploaded 28 Oct 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)DIVINE DAZZLE - A - Arch Certf-'Sep -23 - ss.pdf · uploaded 25 Nov 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)DIVINE DAZZLE - A - Engg Certf-'Sep -23 - ss.pdf · uploaded 25 Nov 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2 A- Dvn Dzl -A-30-09-2023 - ss.pdf · uploaded 25 Nov 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 - DIVINE DAZZLE-A - FY-2022-23.pdf · uploaded 22 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 - DIVINE DAZZLE-A - FY-2022-23.pdf · uploaded 22 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 - DIVINE DAZZLE-A - FY-2023-24.pdf · uploaded 21 Nov 2024Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)DIVINE DAZZLE -A -SOCIETY CERTIFICATE.pdf · uploaded 21 Nov 2024Source
  • 1 Certificates of CA (Form 3)CA Certificate Divine Dazzle A -Rera Sep 23-ss.pdf · uploaded 21 Nov 2024Source
  • 1 Certificates of CA (Form 3)CA Certificate Divine Dazzle A -Rera Sep 23-ss.pdf · uploaded 21 Nov 2024Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)DIVINE DAZZLE -A -SOCIETY CERTIFICATE.pdf · uploaded 21 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 - DIVINE DAZZLE-A - FY-2023-24.pdf · uploaded 21 Nov 2024Source

Technical

  • DocumentDIVINE DAZZLE -A-IOD.pdf · uploaded 27 Jun 2019Source
  • DocumentDIVINE DAZZLE A - Layout.pdf · uploaded 27 Jun 2019Source
  • Document1-5 layout-ss.pdf · uploaded 8 Jan 2022Source
  • DocumentLAY OUT- DVN DZL-A -13 FLR-ss.pdf · uploaded 31 Oct 2022Source

Technical (Architect)

  • DocumentDIVINE DAZZLE - A - Arch Certf-'Sep -23 - ss.pdf · uploaded 25 Nov 2023Source

Technical (Engineer)

  • DocumentDIVINE DAZZLE - A - Engg Certf-'Sep -23 - ss.pdf · uploaded 25 Nov 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S NO 70/2

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
2BHK, Shop132 units in all
Address
S No 70 2, Rahatani, RahataniPIN 411017
Village
Pimpri Chinchawad (M Corp.), Haveli taluka
Land area for this project
3,846 sq m (41,399 sq ft)
Permissible built-up area
5,537 sq m (59,600 sq ft)
Sanctioned built-up area
3,461 sq m (37,254 sq ft)
Recreational open space
385 sq m (4,145 sq ft)
Designated bank account
88
Developed in phases
No

Survey, CTS, gat or plot numbers

S NO 70/2

Land as published on MahaRERA's project page

S NO 70 2

Boundaries

North
By Bhoomi Developers
South
Property Of Kailash Thopte And Others
East
S No 70-2
West
By PCMC Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking132 units

65 of 132 units booked (49%), as the promoter reported to MahaRERA

2BHK · 129 unitsShop · 3 units
TypeCarpet areaUnitsBooked
2BHK53.09 sq m · 571 sq ft10345
2BHK53.18 sq m · 572 sq ft2620
Shop26.78 sq m · 288 sq ft20
Shop38.88 sq m · 419 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPatil Bugade Architects—
ArchitectPatil & Bugde Associates—
Chartered accountantG B Durande & Co—
Chartered accountantShubham Chavan Associates—
EngineerRohinee Badgujar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology