Skip to content
Residential / Group Housing · 2 buildings · 11 unitsRERA P52100049821

Apple Shagun

Deedo IDDP-PUN-2REB

MahaRERA shows it completed; no MahaRERA orders on record; 45% of its units are booked.

Rahatani, Pune 411017 · by Mewani And Bhojwani Hospitality

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales45% booked5 of 11 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 24 Feb 2023, completion promised 31 May 2025.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100049821
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210004982124 Feb 202331 May 202531 May 2025Mewani And Bhojwani HospitalityProject page
Documents64

2 documents held by Deedo, 62 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN - Mewani and Bhojwani Hospitality.pdf · uploaded 6 Feb 2023Source

Legal

  • Declaration Form BForm B.pdf · uploaded 6 Feb 2023Source
  • Legal Title reportLEGAL TITLE REPORT.pdf · uploaded 13 Feb 2023Source

Migrated

  • 1 PAN CardPAN - Mewani and Bhojwani Hospitality.pdf · uploaded 6 Feb 2023Source
  • 1 Copy of Layout Approval (in case of layout)Layout planBuilding Layout.pdf · uploaded 6 Feb 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentLayout planBuilding Layout.pdf · uploaded 6 Feb 2023Source
Show all 64 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentcommencement rahatani 26-Dec-2022 10-44-00.pdf · uploaded 6 Feb 2023Source
  • 1 Declaration about Commencement CertificateDeclaration commencment.pdf · uploaded 6 Feb 2023Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 6 Feb 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Rahatani RERA.pdf · uploaded 6 Feb 2023Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 6 Feb 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration for seperate Bank.pdf · uploaded 6 Feb 2023Source
  • 1 Copy of the legal title reportLEGAL TITLE REPORT.pdf · uploaded 13 Feb 2023Source
  • 1 a Details of encumbrances concerned to FinanceDeclaration Encumbrances.pdf · uploaded 13 Feb 2023Source
  • 1 b Details of encumbrances concerned to LegalDeclaration Encumbrances.pdf · uploaded 13 Feb 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 acceptance_v2.pdf · uploaded 13 Feb 2023Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsdeclaration interest kishan.pdf · uploaded 13 Feb 2023Source
  • 2 Disclosure of Interest in Other Real Estate Organizationsdeclaration interest Naveen.pdf · uploaded 13 Feb 2023Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 13 Feb 2023Source
  • 1 Deviation Report with respect to Allotment letterDeclaration Deviation Allotment.pdf · uploaded 13 Feb 2023Source
  • 1 Proforma of Agreement for saleMEWANI AND BHOJWANI_SALE_DRAFT.pdf · uploaded 18 Feb 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation AFS.pdf · uploaded 18 Feb 2023Source
  • 2 Copy of Layout Approval (in case of layout)Amended Layout.pdf · uploaded 7 Jul 2023Source
  • 2 Declaration about Commencement Certificaterevised commencement apple shagun 05-Jul-2023_compressed.pdf · uploaded 7 Jul 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Apr 23_compressed.pdf · uploaded 12 Jan 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 July 23_compressed.pdf · uploaded 12 Jan 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Oct 23_compressed.pdf · uploaded 12 Jan 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Jan 24_compressed.pdf · uploaded 12 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 Signed (2022-23) Mewani and Bhojwani.pdf · uploaded 12 Jan 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Apr 23_compressed.pdf · uploaded 15 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 July 23_compressed.pdf · uploaded 15 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Oct 23_compressed.pdf · uploaded 15 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Jan 24_compressed.pdf · uploaded 15 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Apr 23_compressed.pdf · uploaded 15 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 July 23_compressed.pdf · uploaded 15 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Oct 23_compressed.pdf · uploaded 15 Jan 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Jan 24_compressed.pdf · uploaded 15 Jan 2024Source
  • 1 Disclosure of sold/ booked inventoryDetails of Booked Apartments.pdf · uploaded 17 Jan 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 January to march 26-Jan-2024 17-07-04 (1)_compressed.pdf · uploaded 27 Jan 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)form1april to june 26-Jan-2024 17-10-09.pdf · uploaded 27 Jan 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)form1july to sept 26-Jan-2024 17-12-02_compressed.pdf · uploaded 27 Jan 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 Q4 October to december 26-Jan-2024 17-13-20_compressed.pdf · uploaded 27 Jan 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 Q1 Jan to march 26-Jan-2024 17-15-52.pdf · uploaded 27 Jan 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 April to June 2023_compressed.pdf · uploaded 29 Jan 2024Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 Signed (2022-23) Mewani and Bhojwani Hospitality.pdf · uploaded 28 Mar 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)apple shagun f2 16 04 2024.pdf · uploaded 20 Apr 2024Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 January to march 24 20-Apr-2024 15-27-53.pdf · uploaded 20 Apr 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)apple shagun f2 16 04 2024.pdf · uploaded 20 Apr 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 08 04 2024.pdf · uploaded 22 Apr 2024Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Jan-Mar 24_compressed.pdf · uploaded 24 May 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 FY 2022-23.pdf · uploaded 24 May 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentNew Document(92) 31-May-2024 14-51-31.pdf · uploaded 31 May 2024Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)signed F1.pdf · uploaded 15 Jul 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Signed F2.pdf · uploaded 15 Jul 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)signed F3.pdf · uploaded 15 Jul 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)signed F4.pdf · uploaded 15 Jul 2024Source
  • 2 Disclosure of sold/ booked inventorysignedd sold unsold.pdf · uploaded 7 Aug 2024View

Technical

  • DocumentLayout planBuilding Layout.pdf · uploaded 6 Feb 2023Source
  • DocumentLayout planBuilding Layout.pdf · uploaded 6 Feb 2023Source
  • DocumentAmended Layout.pdf · uploaded 7 Jul 2023Source

Technical (Architect)

  • Documentsigned F1.pdf · uploaded 15 Jul 2024Source

Technical (Engineer)

  • DocumentSigned F2.pdf · uploaded 15 Jul 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK11 units in all
Address
71/1A/1B/1C/1/24 Rahatani, S.NO. 71/1A/1B/1C/1/24, RAHATANIPIN 411017
Village
Pimpri Chinchawad (M Corp.), Haveli taluka
Land area for this project
279 sq m (2,998 sq ft)
Permissible built-up area
486 sq m (5,233 sq ft)
Sanctioned built-up area
486 sq m (5,233 sq ft)
Designated bank account
76
Developed in phases
No

Land as published on MahaRERA's project page

71/1A/1B/1C/1/24 Rahatani

Boundaries

North
Cts No 3637 Cts No 3636
South
7m Wide Road
East
Cts No 3665
West
Cts No 3663

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking11 units

5 of 11 units booked (45%), as the promoter reported to MahaRERA

1BHK · 11 units
TypeCarpet areaUnitsBooked
1BHK33.14 sq m · 357 sq ft42
1BHK34.63 sq m · 373 sq ft30
1BHK34.63 sq m · 373 sq ft43

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMilind Jagtap—
Chartered accountantAyush Goyal—
EngineerAnup Bashani—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology