Promised date passed8 floorsRERA P52100014390
A-Phase2, Atlantis
Deedo IDDP-PUN-7GSX-AMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked43%23 of 54 · MahaRERA
Completion30 Sep 2020as registered
Units & parking in A-Phase2
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 53.3 m² (574 sq.ft) | 1 | 0 |
| 1 BHK | 53.3 m² (574 sq.ft) | 1 | 0 |
| 2.5 BHK | 72.8 m² (783 sq.ft) | 1 | 1 |
| 2.5 BHK | 75.4 m² (811 sq.ft) | 1 | 0 |
| 2.5 BHK | 78.1 m² (841 sq.ft) | 2 | 2 |
| 2 BHK | 63.4 m² (683 sq.ft) | 1 | 0 |
| 2 BHK | 63.4 m² (683 sq.ft) | 4 | 0 |
| 2 BHK | 63.5 m² (683 sq.ft) | 1 | 0 |
| 2 BHK | 63.5 m² (683 sq.ft) | 2 | 0 |
| 2 BHK | 65.4 m² (704 sq.ft) | 2 | 1 |
| 2 BHK | 65.5 m² (705 sq.ft) | 1 | 0 |
| 2 BHK | 65.6 m² (706 sq.ft) | 1 | 1 |
| 2 BHK | 65.6 m² (706 sq.ft) | 1 | 1 |
| 2 BHK | 66 m² (710 sq.ft) | 1 | 0 |
| 2 BHK | 66 m² (711 sq.ft) | 1 | 0 |
| 2 BHK | 67.3 m² (725 sq.ft) | 2 | 0 |
| 2 BHK | 67.4 m² (725 sq.ft) | 1 | 0 |
| 2 BHK | 67.5 m² (726 sq.ft) | 1 | 0 |
| 2 BHK | 67.5 m² (726 sq.ft) | 1 | 1 |
| 2 BHK | 67.5 m² (727 sq.ft) | 1 | 0 |
| 2 BHK | 67.6 m² (727 sq.ft) | 1 | 1 |
| 2 BHK | 67.6 m² (727 sq.ft) | 1 | 0 |
| 2 BHK | 67.6 m² (728 sq.ft) | 1 | 0 |
| 2 BHK | 67.8 m² (730 sq.ft) | 1 | 0 |
| 2 BHK | 68.1 m² (733 sq.ft) | 1 | 0 |
| 2 BHK | 68.9 m² (742 sq.ft) | 1 | 0 |
| 2 BHK | 69 m² (743 sq.ft) | 1 | 1 |
| 2 BHK | 69 m² (743 sq.ft) | 1 | 1 |
| 2 BHK | 69.3 m² (746 sq.ft) | 1 | 1 |
| 2 BHK | 69.3 m² (746 sq.ft) | 1 | 1 |
| 2 BHK | 69.3 m² (746 sq.ft) | 2 | 2 |
| 2 BHK | 69.3 m² (746 sq.ft) | 1 | 1 |
| 2 BHK | 69.3 m² (746 sq.ft) | 1 | 1 |
| 2 BHK | 69.9 m² (753 sq.ft) | 2 | 0 |
| 2 BHK | 70.5 m² (758 sq.ft) | 2 | 2 |
| 2 BHK | 70.8 m² (762 sq.ft) | 2 | 0 |
| 2 BHK | 75.8 m² (816 sq.ft) | 1 | 0 |
| 2BHK | 66.1 m² (711 sq.ft) | 2 | 2 |
| 2BHK | 66.1 m² (711 sq.ft) | 2 | 2 |
| 3 BHK | 99.8 m² (1,075 sq.ft) | 1 | 1 |
| 3 BHK | 101.2 m² (1,089 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P52100014390 · registered 29 Nov 2017
- Promised completion
- 30 Sep 2020
- Revised completion
- 30 Sep 2020
- Sanctioned habitable floors
- 8
- Sanctioned floors (incl. basement, stilt, podium)
- 8
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-7GSX-A
Questions about A-Phase2
When is A-Phase2 due for completion?
The MahaRERA registration promises 30 Sep 2020.
How many floors does A-Phase2 have?
8 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology