Sai Planet
Deedo IDDP-PUN-98MNMahaRERA shows it completed; no MahaRERA orders on record; 94% of its units are booked.
Punawale, Pune 411033 · by M K Associates
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 5 Aug 2017, completion promised 31 May 2018.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100003320
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100003320 | 5 Aug 2017 | 31 May 2018 | 31 May 2018 | M K Associates | Project page |
Documents33
1 document held by Deedo, 32 filings listed on MahaRERA's project page
Show all 33 documentsShow fewer documents
Migrated
- 1 Building Plan Approval (IOD)Layout merged.pdf · uploaded 29 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate-ilovepdf-compressed.pdf · uploaded 29 Jul 2017Source
- 1 Declaration in FORM BForm B-compressed.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect certificate MK.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM2.pdf · uploaded 29 Jul 2017Source
- 1 Proforma of Allotment letterallotment letter MK.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of CA (Form 3)FORM 3.pdf · uploaded 30 Jul 2017Source
- 2 Copy of Layout Approval (in case of layout)Layout MK Asoociate-ilovepdf-compressed.pdf · uploaded 27 Oct 2017Source
- 2 Commencement Certificates / NA Order for plotted developmentSKMBT_C36017101403080-ilovepdf-compressed-1-2.pdf · uploaded 27 Oct 2017Source
- 3 Commencement Certificates / NA Order for plotted developmentSKMBT_C36017101403080-ilovepdf-compressed-3-4.pdf · uploaded 27 Oct 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT 1.pdf · uploaded 27 Oct 2017Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)2.pdf · uploaded 27 Oct 2017Source
- 2 Certificates of CA (Form 3)Form 3 -ilovepdf-compressed.pdf · uploaded 27 Oct 2017Source
- 2 Proforma of Allotment letterBooking-Agreement-ilovepdf-compressed-1-10.pdf · uploaded 27 Oct 2017Source
- 3 Proforma of Allotment letterBooking-Agreement-ilovepdf-compressed-11-20.pdf · uploaded 27 Oct 2017Source
- 4 Proforma of Allotment letterBooking-Agreement-ilovepdf-compressed-21-30.pdf · uploaded 27 Oct 2017Source
- 5 Proforma of Allotment letterBooking-Agreement-ilovepdf-compressed-31-40.pdf · uploaded 27 Oct 2017Source
- 1 Certificates of CA (Form 5)M K Associates.pdf · uploaded 20 Dec 2018Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION CERTIFICATE.pdf · uploaded 21 Aug 2019Source
- 2 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 23 Jan 2020Source
Technical
Technical (Architect)
- DocumentARCHITECT 1.pdf · uploaded 27 Oct 2017Source
Technical (Engineer)
- Document2.pdf · uploaded 27 Oct 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel CTS NO 8182
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- FLAT 1 BHK, FLAT 2 BHK16 units in all
- Address
- Cts No 81-82PIN 411033
- Village
- Punawale, Mulshi taluka
- Location
- 18.63908, 73.74683
- Land area for this project
- 560 sq m (6,028 sq ft)
- Permissible built-up area
- 1,166 sq m (12,549 sq ft)
- Sanctioned built-up area
- 1,166 sq m (12,549 sq ft)
- Designated bank account
- 109
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
CTS NO 81-82
Boundaries
- North
- Gat No 81-82
- South
- River
- East
- Cts No 83
- West
- Cts No 80
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking16 units
15 of 16 units booked (94%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| FLAT 1 BHK | 36.41 sq m · 392 sq ft | 2 | 2 |
| FLAT 1 BHK | 36.43 sq m · 392 sq ft | 1 | 1 |
| FLAT 1 BHK | 36.51 sq m · 393 sq ft | 2 | 2 |
| FLAT 1 BHK | 38.36 sq m · 413 sq ft | 5 | 5 |
| FLAT 1 BHK | 38.38 sq m · 413 sq ft | 1 | 1 |
| FLAT 1 BHK | 38.43 sq m · 414 sq ft | 3 | 3 |
| FLAT 2 BHK | 56.94 sq m · 613 sq ft | 1 | 1 |
| FLAT 2 BHK | 57.04 sq m · 614 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vikhe Mandilkar Associates | — |
Source: MahaRERA project page. Contact details are not shown.