Tower 2 - AAVYA, Eevva
Deedo IDDP-PUN-X79F-T214 flats have a sale on record, 46 are booked without a sale deed yet and 120 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
Every flat, floor by floor
Tap a flat to see its record.
- Sale registered
- Booked, no deed yet
- Unsold
Other units on these floors (no stack in the number):
Sale status from MahaRERA's Oct 2026 disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.
Flat 2408
2 BHK · 721 sq ft · floor 24
- Deeds
- 0
- Last activity
- None on record
- Last sale
- None registered
Units & parking in Tower 2 - AAVYA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Not on record | Not on record | 180 | Not on record |
As registered with MahaRERA
- RERA registration
- PM1260002503079 · registered 31 Mar 2026
- Promised completion
- 31 Dec 2032
- Revised completion
- 30 Apr 2033
- Sanctioned habitable floors
- 24
- Units
- 180
- Floors with commencement certificate
- 28
- Deedo ID
- DP-PUN-X79F-T2
Questions about Tower 2 - AAVYA
How many flats in Tower 2 - AAVYA are sold?
14 flats have a sale on record, 46 are booked without a sale deed yet and 120 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
When is Tower 2 - AAVYA due for completion?
The MahaRERA registration promises 31 Dec 2032, revised to 30 Apr 2033.
How many floors does Tower 2 - AAVYA have?
24 sanctioned habitable floors, as registered with MahaRERA.