Five Oaks
Deedo IDDP-PUN-KB2CCompletion was pushed back 4 months, to Jul 2028; no MahaRERA orders on record; 5% of its units are booked.
Pimpale Saudagar, Pune 411027 · Property rates in Pimpale Saudagar · by R R Realtors
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Jul 2028
- This projectRegistered 25 Sep 2025, completion promised 31 Mar 2028, revised to 31 Jul 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPR1260002500968
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1260002500968 | 25 Sep 2025 | 31 Mar 2028 | 31 Jul 2028 | R R Realtors | Project page |
Documents48
1 document held by Deedo, 47 filings listed on MahaRERA's project page
Finance
Legal
- OthersDetails of Encumbrances Concerned to Legal - FIVE OAKS - RERA.pdf · uploaded 11 Sep 2025Source
- Declaration Form BForm B.pdf · uploaded 11 Sep 2025Source
- OthersRR REALTORS - Final Partnership Deed.pdf · uploaded 12 Sep 2025Source
- Declaration Form BR R Realtors Sale Deed.pdf · uploaded 12 Sep 2025Source
- OthersR R realtors 7_12.pdf · uploaded 21 Sep 2025Source
Show all 48 documentsShow fewer documents
Legal
- OthersPAN CARD- Oakstone Realty LLP.pdf · uploaded 21 Sep 2025Source
- OthersDOI - Anmol Kukreja.pdf · uploaded 21 Sep 2025Source
- OthersDOI - Darshan Ramnani.pdf · uploaded 21 Sep 2025Source
- OthersDOI - Vishal Kundnani.pdf · uploaded 21 Sep 2025Source
- OthersDOI -Rameshlal Mewani.pdf · uploaded 21 Sep 2025Source
- OthersDOI - Vishal Rajani.pdf · uploaded 21 Sep 2025Source
- Declaration Form BFormat - A -Legal Title Report with Annex.pdf · uploaded 21 Sep 2025Source
- OthersSUBMISSION OF CLARIFICATIONS AND DOCUMENTS AGAINST SCRUTINY.pdf · uploaded 23 Sep 2025Source
- OthersRR Realtors Partnership Deed No 1.pdf · uploaded 24 Sep 2025Source
- OthersAdmission-cum-Retire Partnership Deed No 2.pdf · uploaded 24 Sep 2025Source
- OthersAdmission Cum Retire Partnership Deed No 3.pdf · uploaded 24 Sep 2025Source
- OthersAnnexure A - DOI - Darshan Ramnani.pdf · uploaded 24 Sep 2025Source
- OthersANNEXURE A - DOI - Pooja Ramnani.pdf · uploaded 24 Sep 2025Source
- OthersAnnexure A - DOI - Oakstone Realty LLP.pdf · uploaded 24 Sep 2025Source
- OthersCLARIFICATION IN RESPECT OF QUERIES RAISED – PROJECT FIVE OAKS.pdf · uploaded 25 Sep 2025Source
Migrated
- Withdrawal Update Form 1Q-2 Form-1 Architect Certification for Five Oaks.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 1Q-3 Form-1 Architect Certification for Five Oaks.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 1Q-2 Form-1 Architect Certification for Five Oaks.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 2Q-2 Form-2 Engineer Certification for Five Oaks.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 2Q-3 Form-2 Engineer Certification for Five Oaks.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 2Q-2 Form-2 Engineer Certification for Five Oaks.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 3Q-2 Form-3 CA Certification for Five Oaks.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 3Q-3 Form-3 CA Certification for Five Oaks.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 3Q-2 Form-3 CA Certification for Five Oaks.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 1Q-2 Form-1 Architect Certification for Five Oaks.pdf · uploaded 9 Feb 2026Source
- Withdrawal Update Form 2Q-2 Form-2 Engineer Certification for Five Oaks.pdf · uploaded 9 Feb 2026Source
- Withdrawal Update Form 3Revised - Q -3 - Form-3 -C A Certificate for Five Oaks.pdf · uploaded 9 Feb 2026Source
- Withdrawal Update Form 1Q-4 Form-1 Architect Certification for Five Oaks.pdf · uploaded 26 Apr 2026Source
- Withdrawal Update Form 2Q-2 Form-2 Engineer Certification for Five Oaks.pdf · uploaded 26 Apr 2026Source
- Withdrawal Update Form 3Q4_ Form 3 - CA Certification for Five Oaks.pdf · uploaded 26 Apr 2026Source
- Withdrawal Update Form 1Q-1 Form-1 Architect Certification for Five Oaks.pdf · uploaded 3 Aug 2026Source
- Withdrawal Update Form 2Q-1 Form 2 - Engineers Certification for Five Oaks.pdf · uploaded 3 Aug 2026Source
- Withdrawal Update Form 3Q1_ Form 3 - CA Certification for Five Oaks.pdf · uploaded 3 Aug 2026Source
- Form 2A (FY 2025-2026)Form 2A (1).pdf · uploaded 2 Sep 2026Source
Technical
Technical (Architect)
- DocumentQ-1 Form-1 Architect Certification for Five Oaks.pdf · uploaded 3 Aug 2026Source
Technical (Engineer)
- DocumentQ-1 Form 2 - Engineers Certification for Five Oaks.pdf · uploaded 3 Aug 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel CTS No. 1015 (Part), Sr No. 5/9 A(PART)
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —19 units in all
- Address
- Sr No.5/9 A (Part), CTS No. 1015 (Part), Rahatni, RahatniPIN 411027
- Village
- Pimpale Saudagar, Haveli taluka
- Location
- 18.59917, 73.79152
- Land area for this project
- 1,300 sq m (13,993 sq ft)
- Permissible built-up area
- 2,286 sq m (24,610 sq ft)
- Sanctioned built-up area
- 2,286 sq m (24,610 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 220
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Sr No. 5/9 A(PART), CTS No. 1015 (Part), Rahatni, Pune
Boundaries
- North
- Remaining Land in this Survey Number
- South
- Property owned by Rajyog Construction
- East
- 6 Meter Road and Land Owned By Dipak Bhalerao
- West
- Compound wall and Royal Imperio
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking19 units
19 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 19 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vinay Sudam Kunjir Prop S K Associates | — |
| Chartered accountant | Akash Ramnani | — |
| Chartered accountant | Ayush Satish Goyal | — |
| Engineer | Shashikant Trilokinath Mishra | — |
| Engineer | Vijay Mahadev Davang | — |
Source: MahaRERA project page. Contact details are not shown.