Mohar Srushti
Deedo IDDP-PUN-5Z1VCompletion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record.
Nayagaon, Pune 410405 · by Mohar Projects Llp
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2031
- This projectRegistered 8 Jun 2023, completion promised 31 Dec 2030, revised to 30 Apr 2031.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100051231
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100051231 | 8 Jun 2023 | 31 Dec 2030 | 30 Apr 2031 | Mohar Projects LLP | Project page |
Documents26
1 document held by Deedo, 25 filings listed on MahaRERA's project page
Finance
- PAN CardPAN Mohar Projects LLP.pdf · uploaded 29 Apr 2023Source
Legal
Migrated
- 1 PAN CardPAN Mohar Projects LLP.pdf · uploaded 29 Apr 2023Source
- 1 Copy of the legal title reportTitle Report.pdf · uploaded 29 Apr 2023Source
- 1 Copy of Layout Approval (in case of layout)Sanctioned Lay out-compressed.pdf · uploaded 29 Apr 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentNA Order.pdf · uploaded 29 Apr 2023Source
Show all 26 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentNA Order.pdf · uploaded 29 Apr 2023Source
- 1 CERSAI detailsDECLARATION REGARDING ENCUMBRANCE.pdf · uploaded 29 Apr 2023Source
- 1 a Details of encumbrances concerned to FinanceDECLARATION REGARDING ENCUMBRANCE.pdf · uploaded 2 May 2023Source
- 1 b Details of encumbrances concerned to LegalDECLARATION REGARDING ENCUMBRANCE.pdf · uploaded 2 May 2023Source
- 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf · uploaded 2 May 2023Source
- 1 Declaration in FORM BForm B.pdf · uploaded 2 May 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 2 May 2023Source
- 1 Proforma of Agreement for saleAgreement Draft.pdf · uploaded 2 May 2023Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 2 May 2023Source
- 1 Deviation Report with respect to Allotment letterDeviations to proforma allotment letter.pdf · uploaded 2 May 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviations to Agreement.pdf · uploaded 2 May 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about Separate Bank Account.pdf · uploaded 31 May 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 2 Jun 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)QUALITY ASSURANCE CERTIFICATE-NAIGAON FEB 2025.pdf · uploaded 21 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Rera form 3 Mohar Projects LLP .pdf · uploaded 5 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Rera form 2 Mohar Projects LLP .pdf · uploaded 5 Apr 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 25
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- 25, Pune Mumbai Old Higway, Near Katraj dairyPIN 410405
- Village
- Nayagaon, Mawal taluka
- Location
- 18.45190, 73.30674
- Land area for this project
- 51,130 sq m (5,50,358 sq ft)
- Permissible built-up area
- 0 sq m (0 sq ft)
- Sanctioned built-up area
- 0 sq m (0 sq ft)
- Recreational open space
- 4,386 sq m (47,215 sq ft)
- Designated bank account
- 99
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
25
Boundaries
- North
- Gat No 18 and others
- South
- Gat No 26 and other
- East
- Road
- West
- Gavthan and Gat no 20 and others
Source: registration certificates and MahaRERA's project page, as stated there.