Skip to content
Residential / Group Housing · 2 buildings · 40 unitsRERA P52100076955

Twilight Terrace

Deedo IDDP-PUN-A9PB

Completion was pushed back 4 months, to Jul 2027; no MahaRERA orders on record; 0% of its units are booked.

Bhugaon, Pune 412115 · by Shri Swami Samarath Developers

DeliveryExtended 4 moPromised Mar 2027 · now due Jul 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 40 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jul 2027

  • This projectRegistered 9 Jul 2024, completion promised 31 Mar 2027, revised to 31 Jul 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100076955
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000769559 Jul 202431 Mar 202731 Jul 2027Shri Swami Samarath DevelopersProject page
Documents97

1 document held by Deedo, 96 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Company.pdf · uploaded 27 Feb 2024Source
  • Other – FinanceCA Certificate.pdf · uploaded 26 Mar 2024Source

Legal

  • Declaration Form BUndertaking Form B.pdf · uploaded 27 Feb 2024Source
  • Other – LegalTitle.pdf · uploaded 19 Apr 2024Source
  • Other – Legalभुगांव_251.pdf · uploaded 19 Apr 2024Source
  • Other – Legalभुगांव_259.pdf · uploaded 19 Apr 2024Source
  • Other – LegalClarification On Survey No.pdf · uploaded 27 Jun 2024Source
Show all 97 documentsShow fewer documents

Legal

  • Other – LegalPMRDA Inward Letter.pdf · uploaded 27 Jun 2024Source
  • Other – LegalMore undertaking .pdf · uploaded 27 Jun 2024Source
  • Legal Title reportSearch 251 com.pdf · uploaded 27 Jun 2024Source
  • Legal Title reportSearch 259 com.pdf · uploaded 27 Jun 2024Source

Migrated

  • 1 PAN CardPAN Company.pdf · uploaded 27 Feb 2024Source
  • 1 a Details of encumbrances concerned to FinanceLetter of Encumbrance.pdf · uploaded 27 Feb 2024Source
  • 1 b Details of encumbrances concerned to LegalLetter of Encumbrance.pdf · uploaded 27 Feb 2024Source
  • 1 Copy of Layout Approval (in case of layout)Saction 1.pdf · uploaded 27 Feb 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentSaction 1.pdf · uploaded 27 Feb 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentSaction 2.pdf · uploaded 27 Feb 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement co.pdf · uploaded 27 Feb 2024Source
  • 1 Declaration about Commencement CertificateDeclaration about Commencement certificate.pdf · uploaded 27 Feb 2024Source
  • 1 Declaration in FORM BUndertaking Form B.pdf · uploaded 27 Feb 2024Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold booked inventory.pdf · uploaded 27 Feb 2024Source
  • 1 CERSAI detailsAsset Based Search.pdf · uploaded 27 Feb 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate co.pdf · uploaded 27 Feb 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsANNEXTURE- A.pdf · uploaded 27 Feb 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexture A.pdf · uploaded 27 Feb 2024Source
  • 1 Proforma of Agreement for saleAgreement to sale co.pdf · uploaded 27 Feb 2024Source
  • 1 Proforma of Allotment letterAllotment Letter co.pdf · uploaded 27 Feb 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about separate Bank Account.pdf · uploaded 27 Feb 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report for AL AFS.pdf · uploaded 27 Feb 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report for AL AFS.pdf · uploaded 27 Feb 2024Source
  • 1 Other – FinanceCA Certificate.pdf · uploaded 26 Mar 2024Source
  • 1 Other – TechnicalAnnexture A.pdf · uploaded 26 Mar 2024Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance.pdf · uploaded 30 Mar 2024Source
  • 3 a Details of encumbrances concerned to FinanceLegal Litigation Encumbrance.pdf · uploaded 30 Mar 2024Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance.pdf · uploaded 30 Mar 2024Source
  • 3 b Details of encumbrances concerned to LegalLegal Litigation Encumbrance.pdf · uploaded 30 Mar 2024Source
  • 2 CERSAI detailsAsset Based CERSAI.pdf · uploaded 30 Mar 2024Source
  • 2 Other – TechnicalPMRDA Gmail 251 P 259 P.pdf · uploaded 30 Mar 2024Source
  • 3 CERSAI detailsCersai.pdf · uploaded 19 Apr 2024Source
  • 1 Other – LegalTitle.pdf · uploaded 19 Apr 2024Source
  • 2 Other – Legalभुगांव_251.pdf · uploaded 19 Apr 2024Source
  • 3 Other – Legalभुगांव_259.pdf · uploaded 19 Apr 2024Source
  • 1 Copy of the legal title reportSearch 251 com.pdf · uploaded 27 Jun 2024Source
  • 2 Copy of the legal title reportSearch 259 com.pdf · uploaded 27 Jun 2024Source
  • 4 Other – LegalClarification On Survey No.pdf · uploaded 27 Jun 2024Source
  • 5 Other – LegalPMRDA Inward Letter.pdf · uploaded 27 Jun 2024Source
  • 6 Other – LegalMore undertaking .pdf · uploaded 27 Jun 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certi.pdf · uploaded 7 May 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certi.pdf · uploaded 7 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 7 May 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certifi.pdf · uploaded 7 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Cer.pdf · uploaded 7 May 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engi.pdf · uploaded 7 May 2025Source
  • Form 1Architect Certi.pdf · uploaded 4 Aug 2025Source
  • Form 2Engi.pdf · uploaded 4 Aug 2025Source
  • Form 3CA Certifi.pdf · uploaded 4 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Sept 24.pdf · uploaded 4 Aug 2025Source
  • Form 1Arch Dec 24.pdf · uploaded 4 Aug 2025Source
  • Form 2Engg Dec 24.pdf · uploaded 4 Aug 2025Source
  • Form 3CA Dec 24.pdf · uploaded 4 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Dec 24.pdf · uploaded 4 Aug 2025Source
  • Form 1Arch Mar 25.pdf · uploaded 4 Aug 2025Source
  • Form 2Engg Mar 25.pdf · uploaded 4 Aug 2025Source
  • Form 3CA Mar 25.pdf · uploaded 4 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Mar 25.pdf · uploaded 4 Aug 2025Source
  • OthersFom 5 2425.pdf · uploaded 4 Aug 2025Source
  • Form 1Arch Jun 25.pdf · uploaded 4 Aug 2025Source
  • Form 2Engg Jun 25.pdf · uploaded 4 Aug 2025Source
  • Form 3CA Jun 25.pdf · uploaded 4 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Jun 25.pdf · uploaded 4 Aug 2025Source
  • Withdrawal Update Form 1Architect.pdf · uploaded 15 Oct 2025Source
  • Withdrawal Update Form 2Engineer.pdf · uploaded 15 Oct 2025Source
  • Withdrawal Update Form 3CA Certificate.pdf · uploaded 15 Oct 2025Source
  • Withdrawal Update Form 1Architect.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 2Engineer.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 3CA Certificate.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 1Architect.pdf · uploaded 27 Apr 2026Source
  • Withdrawal Update Form 2Engg.pdf · uploaded 27 Apr 2026Source
  • Withdrawal Update Form 3CA.pdf · uploaded 27 Apr 2026Source
  • Form 2A (FY 2024-2025)Quality 2024-25.pdf · uploaded 18 Aug 2026Source
  • Form 2A (FY 2025-2026)Quality 2025-26.pdf · uploaded 18 Aug 2026Source
  • Form 2A (FY 2026-2027)Quality 2026-27.pdf · uploaded 18 Aug 2026Source
  • Withdrawal Update Form 1Arch Jun 26.pdf · uploaded 19 Aug 2026Source
  • Withdrawal Update Form 2Engineer Jun 26.pdf · uploaded 19 Aug 2026Source
  • Withdrawal Update Form 3CA Jun 26.pdf · uploaded 19 Aug 2026Source
  • Form 5 (FY 2024-2025)Form 5 2024-25.pdf · uploaded 19 Aug 2026Source
  • Form 5 (FY 2025-2026)Form 5 2025-26.pdf · uploaded 19 Aug 2026Source

Technical

  • DocumentSaction 1.pdf · uploaded 27 Feb 2024Source
  • DocumentSaction 1.pdf · uploaded 27 Feb 2024Source
  • DocumentSaction 2.pdf · uploaded 27 Feb 2024Source
  • Other – TechnicalAnnexture A.pdf · uploaded 26 Mar 2024Source
  • Other – TechnicalPMRDA Gmail 251 P 259 P.pdf · uploaded 30 Mar 2024Source

Technical (Architect)

  • DocumentArchitect Certi.pdf · uploaded 7 May 2025Source
  • DocumentArch Jun 26.pdf · uploaded 19 Aug 2026Source

Technical (Engineer)

  • DocumentEngi.pdf · uploaded 7 May 2025Source
  • DocumentEngineer Jun 26.pdf · uploaded 19 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 251(P), 259(P) at Mulshi

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Landowner40 units in all
Address
251(P) And 259(P), Paud Road, BhugaonPIN 412115
Land area for this project
2,200 sq m (23,681 sq ft)
Permissible built-up area
2,200 sq m (23,681 sq ft)
Sanctioned built-up area
2,157 sq m (23,221 sq ft)
Recreational open space
224 sq m (2,410 sq ft)
Designated bank account
220
Developed in phases
Yes

Survey, CTS, gat or plot numbers

251(P)259(P) at Mulshi

Land as published on MahaRERA's project page

251(P) AND 259(P)

Boundaries

North
Adj 251p
South
Adj 259p
East
9m Wide Road
West
Adj 259p

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking40 units

0 of 40 units booked (0%), as the promoter reported to MahaRERA

1BHK · 4 units2BHK · 16 unitsLandowner · 20 units
BuildingTypeCarpet areaUnitsBooked
Twilight Terrace A Wing1BHK37.53 sq m · 404 sq ft40
Twilight Terrace A Wing2BHK50.91 sq m · 548 sq ft40
Twilight Terrace A Wing2BHK51.56 sq m · 555 sq ft80
Twilight Terrace A Wing2BHK51.84 sq m · 558 sq ft40
Twilight Terrace B WingLandowner35.12 sq m · 378 sq ft80
Twilight Terrace B WingLandowner35.58 sq m · 383 sq ft40
Twilight Terrace B WingLandowner48.88 sq m · 526 sq ft80

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectYogiraj Associates—
Chartered accountantDinesh Kudale—
EngineerShrikant Matre—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology