Extended 4 mo16 floorsRERA P52100046506

A Wing, Kosmas A Wing

Deedo IDDP-PUN-9JJ3-A

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

All of Kosmas A Wing
Median saleNot on recordneeds 3 or more sales
Completion30 Apr 202731 Dec 2026 · revised
Units & parking in A Wing
TypeCarpet areaUnitsBooked
1BHK45.6 m² (491 sq.ft)47Not on record
2BHK62.6 m² (674 sq.ft)24Not on record
2BHK67.3 m² (725 sq.ft)24Not on record
Shop24.3 m² (261 sq.ft)2Not on record
Shop24.3 m² (262 sq.ft)2Not on record
Shop25.7 m² (277 sq.ft)6Not on record
Shop30 m² (323 sq.ft)2Not on record
Shop30.1 m² (324 sq.ft)2Not on record
Shop31.2 m² (336 sq.ft)6Not on record

Parking: Closed/Covered 65 · Open Space 30 (as declared to MahaRERA)

Construction progress (declared)

Work completed, as the promoter reported it to MahaRERA (Form 1). Not verified on site.

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)50%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.15%
As registered with MahaRERA
RERA registration
P52100046506 · registered 10 Aug 2022
Promised completion
31 Dec 2026
Revised completion
30 Apr 2027
Sanctioned habitable floors
16
Sanctioned floors (incl. basement, stilt, podium)
16
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-PUN-9JJ3-A
Questions about A Wing

When is A Wing due for completion?

The MahaRERA registration promises 31 Dec 2026, revised to 30 Apr 2027.

How many floors does A Wing have?

16 sanctioned habitable floors, as registered with MahaRERA.

Data through3 Nov 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology