Promised date passed8 floorsRERA P52100001122
B, Adhya Rohan
Deedo IDDP-PUN-XYGM-BMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked33%12 of 36 · MahaRERA
Completion31 Dec 2018as registered
Units & parking in B
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 43 m² (463 sq.ft) | 24 | 10 |
| 2BHK | 59.1 m² (636 sq.ft) | 6 | 1 |
| 2BHK | 62.9 m² (677 sq.ft) | 6 | 1 |
As registered with MahaRERA
- RERA registration
- P52100001122 · registered 26 Jul 2017
- Promised completion
- 31 Dec 2018
- Revised completion
- 31 Dec 2018
- Sanctioned habitable floors
- 8
- Sanctioned floors (incl. basement, stilt, podium)
- 8
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-XYGM-B
Questions about B
When is B due for completion?
The MahaRERA registration promises 31 Dec 2018.
How many floors does B have?
8 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology