Skip to content
Residential / Group Housing · 1 building · 136 unitsRERA P52100048413

SkyHigh Towers D3

Deedo IDDP-PUN-D2Z7

Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 75% of its units are booked.

Man, Pune 411057 · by New World Landmark Llp

DeliveryExtended 4 moPromised Dec 2027 · now due Apr 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales75% booked102 of 136 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2028

  • This projectRegistered 3 Jan 2023, completion promised 31 Dec 2027, revised to 30 Apr 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100048413
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000484133 Jan 202331 Dec 202730 Apr 2028New World Landmark LLPProject page
Documents138

1 document held by Deedo, 137 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Card.pdf · uploaded 19 Nov 2022Source

Legal

  • Legal Title reportLegal Title Report with Annexure part 1.pdf · uploaded 29 Nov 2022Source
  • Legal Title reportLegal Title Report with Annexure part 2.pdf · uploaded 29 Nov 2022Source
  • Declaration Form BForm B.pdf · uploaded 29 Nov 2022Source
  • OthersEnvironmental Clearance EC.pdf · uploaded 12 Nov 2025Source

Migrated

  • 1 PAN CardPAN Card.pdf · uploaded 19 Nov 2022Source
  • 1 Copy of the legal title reportLegal Title Report with Annexure part 1.pdf · uploaded 29 Nov 2022Source
Show all 138 documentsShow fewer documents

Migrated

  • 2 Copy of the legal title reportLegal Title Report with Annexure part 2.pdf · uploaded 29 Nov 2022Source
  • 1 a Details of encumbrances concerned to FinanceDeclaration for Encumbrance D3.pdf · uploaded 29 Nov 2022Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Certificate forLEGAL TITLE D3.pdf · uploaded 29 Nov 2022Source
  • 1 b Details of encumbrances concerned to LegalDeclaration for Encumbrance D3.pdf · uploaded 29 Nov 2022Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Certificate forLEGAL TITLE D3.pdf · uploaded 29 Nov 2022Source
  • 1 Copy of Layout Approval (in case of layout)Layout 15-11-22-compressed.pdf · uploaded 29 Nov 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentLayout 15-11-22-compressed.pdf · uploaded 29 Nov 2022Source
  • 1 Declaration about Commencement CertificateDECLARATION FOR CC - D3.pdf · uploaded 29 Nov 2022Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 29 Nov 2022Source
  • 1 CERSAI detailsUNDERTAKING FOR CERSAI D3.pdf · uploaded 29 Nov 2022Source
  • 1 Proforma of Allotment letterAllotment letter draft for D3.pdf · uploaded 29 Nov 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation report for Allotment letter draft.pdf · uploaded 29 Nov 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC 15_11_2022.pdf · uploaded 30 Nov 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same0_D3 Declaration for AC.pdf · uploaded 9 Dec 2022Source
  • 2 Copy of Layout Approval (in case of layout)0_layout_Model.pdf · uploaded 10 Dec 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)0_Form 3 sky high tower D3 signed.pdf · uploaded 10 Dec 2022Source
  • 1 Proforma of Agreement for sale2-Agreement to Sale for SkyHigh Tower D3.pdf · uploaded 20 Dec 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report for ATS for D3.pdf · uploaded 20 Dec 2022Source
  • 2 CERSAI details0_CERSAI_Search_Report.pdf · uploaded 23 Dec 2022Source
  • 3 a Details of encumbrances concerned to FinanceEncumbrance updte D3.pdf · uploaded 21 Feb 2023Source
  • 3 b Details of encumbrances concerned to LegalEncumbrance updte D3.pdf · uploaded 21 Feb 2023Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameAC no Update D3.pdf · uploaded 21 Feb 2023Source
  • 3 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same0_Declaration about AC details D3.pdf · uploaded 28 Feb 2023Source
  • 2 Proforma of Agreement for sale2 Proforma of Agreement to sale.pdf · uploaded 24 Jun 2023Source
  • 3 Proforma of Agreement for sale2 Proforma of Agreement to sale.pdf · uploaded 27 Jun 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Bldg D3 March 2023.pdf · uploaded 17 Jul 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Skyhigh D 3 March 2023.pdf · uploaded 17 Jul 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 AS Sky High D3 30032023 both sign_compressed.pdf · uploaded 17 Jul 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 SKY HIGH D3 ARCHITECT CERTIFICATE.pdf · uploaded 31 Jul 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 SKY HIGH D3 ENGINEERING CERTIFICATE.pdf · uploaded 31 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2A SKY HIGH D3 QUALITY ASSURANCE CERTIFICATE.pdf · uploaded 31 Jul 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 AS Skyhigh D3 30062023-both sign_compressed.pdf · uploaded 7 Sep 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 PC FY 22-23 SkyHigh Towers D3_both sign_compressed.pdf · uploaded 7 Sep 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)From 1 SKY HIGH TOWERS D3.pdf · uploaded 7 Dec 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 SkyHigh Towers D3.pdf · uploaded 7 Dec 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 Sky High Towers D3 30092023_compressed.pdf · uploaded 7 Dec 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)From 1 SKY HIGH TOWER D3.pdf · uploaded 24 Feb 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Sky High Towers D3.pdf · uploaded 24 Feb 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 AS Sky High D3 31122023-both sign_compressed.pdf · uploaded 24 Feb 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 D3.pdf · uploaded 29 Apr 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 D3.pdf · uploaded 29 Apr 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 SkyHigh Towers D3 31-03-2024_compressed.pdf · uploaded 29 Apr 2024Source
  • 1 Disclosure of sold/ booked inventoryd3 q1.pdf · uploaded 4 May 2024Source
  • 2 Disclosure of sold/ booked inventoryd3 q2.pdf · uploaded 4 May 2024Source
  • 3 Disclosure of sold/ booked inventoryd3 q3.pdf · uploaded 4 May 2024Source
  • 4 Disclosure of sold/ booked inventoryd3 q4.pdf · uploaded 4 May 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_SkyHigh Towers D3.pdf · uploaded 20 Jul 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_SkyHigh Towers D4.pdf · uploaded 20 Jul 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_SkyHigh Towers D3.pdf · uploaded 20 Jul 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)From 2_SkyHigh Towers D4.pdf · uploaded 20 Jul 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 SkyHigh Towers D3 30-06-2024_compressed.pdf · uploaded 20 Jul 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 SkyHigh Towers D4 30-06-2024_compressed.pdf · uploaded 20 Jul 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM_2A_SkyHigh Towers D3.pdf · uploaded 13 Aug 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 SkyHigh Towers D3 31-03-2024.pdf · uploaded 8 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 D3.pdf · uploaded 12 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 Sky High Towers D3 compressed.pdf · uploaded 12 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_SkyHigh Towers D3.pdf · uploaded 12 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 SkyHigh Towers D3.pdf · uploaded 29 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 SkyHigh Towers D3 31-12-2024_compressed.pdf · uploaded 29 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 SkyHigh Towers D3.pdf · uploaded 29 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorySky High D3.pdf · uploaded 29 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 SkyHigh D3 Mar 2025.pdf · uploaded 2 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 AS Sky High D3 30032025_compressed.pdf · uploaded 2 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2 SkyHigh D3 Mar 2025.pdf · uploaded 2 May 2025Source
  • 1 Disclosure of sold/ booked inventorySKY High - D3 Wing Inventory till 31032025.pdf · uploaded 2 May 2025Source
  • Withdrawal Update Form 1FORM 1 SKY HIGH TOWER D3-Sept 2025.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 1FORM 1 SKY HIGH TOWERS D3.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Sky High Tower D3 - Sep 2025.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 2Form 2 - Jun 2025.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 3Revised Form 3 AS Sky High D3 06112025 F sign.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 3Form 3 - Jun 2025_compressed (7).pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 1FORM 1 SKY HIGH TOWERS D3.pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 1FORM 1 SKY HIGH TOWER D3-Sept 2025.pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 1FORM 1 SKY HIGH TOWER D3-Sept 2025.pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 1FORM 1 SKY HIGH TOWER D3-Sept 2025.pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 2Form 2 - Jun 2025.pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 2Form 2 - Jun 2025.pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 2Form 2 - Jun 2025.pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Sky High Tower D3 - Sep 2025.pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 3Form 3 - Jun 2025_compressed (7).pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 3Revised Form 3 AS Sky High D3.pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 3Revised Form 3 AS Sky High D3.pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 3Revised Form 3 AS Sky High D3.pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 1Form 1 SkyHigh Towers D3 31122025.pdf · uploaded 19 Feb 2026Source
  • Withdrawal Update Form 2Form 2 NWLLLP D3 31122025.pdf · uploaded 19 Feb 2026Source
  • Withdrawal Update Form 3Form 3 AS Sky High D3 31122025 Sign.pdf · uploaded 19 Feb 2026Source
  • Withdrawal Update Form 1Form 1 D3 31032026 sign.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 2Form 2 D3 31032026 sign.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 3Form 3 AS Sky High D3 30032026 F sign_compressed.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 1Form 1 Highsky Tower D3.pdf · uploaded 24 Jul 2026Source
  • Withdrawal Update Form 2Form 2 Skyhigh tower D3.pdf · uploaded 24 Jul 2026Source
  • Withdrawal Update Form 3Form 3 AS Sky High D3 30062026 F sign.pdf · uploaded 24 Jul 2026Source
  • Form 1Form1 SkyHigh D3 Mar 2025.pdf · uploaded 28 Jul 2026Source
  • Form 1Form 1 SkyHigh Towers D1D2-.pdf · uploaded 28 Jul 2026Source
  • Form 2Form2 SkyHigh D3 Mar 2025.pdf · uploaded 28 Jul 2026Source
  • Form 2Form 2 SkyHigh Towers D3.pdf · uploaded 28 Jul 2026Source
  • Form 3Form 3 SkyHigh Towers D3 mar 2025.pdf · uploaded 28 Jul 2026Source
  • Form 3Form 3 SkyHigh Towers D3.pdf · uploaded 28 Jul 2026Source
  • Disclosure of Sold and Booked InventorySkyHigh Towers D3 inventory March 2025.pdf · uploaded 28 Jul 2026Source
  • Disclosure of Sold and Booked InventorySky High D3.pdf · uploaded 28 Jul 2026Source
  • OthersD3 layout and CC.pdf · uploaded 28 Jul 2026Source
  • OthersIOD Plans for SkyHigh Towers.pdf · uploaded 28 Jul 2026Source
  • Form 5 (FY 2022-2023)Form 5 PC FY 22-23 SkyHigh Towers D3_both sign.pdf · uploaded 4 Aug 2026Source
  • Form 5 (FY 2023-2024)form 5 SkyHigh Towers D3 31-03-2024_.pdf · uploaded 4 Aug 2026Source
  • Form 5 (FY 2024-2025)Form 5_SkyHigh Towers D3_FY 2024-2025 sign_compressed.pdf · uploaded 4 Aug 2026Source
  • Form 2A (FY 2024-2025)Form 2A- SkyHigh D3 2024-25.pdf · uploaded 11 Aug 2026Source
  • Form 2A (FY 2025-2026)Form 2A- SkyHigh D3 2025-26.pdf · uploaded 11 Aug 2026Source
  • Form 5 (FY 2025-2026)Form 5_SkyHigh Towers D3_FY 2025-2026 Sign_compressed.pdf · uploaded 1 Oct 2026Source

Technical

  • DocumentLayout 15-11-22-compressed.pdf · uploaded 29 Nov 2022Source
  • DocumentLayout 15-11-22-compressed.pdf · uploaded 29 Nov 2022Source
  • Document0_layout_Model.pdf · uploaded 10 Dec 2022Source
  • Document01-21 - Highlighted.pdf · uploaded 19 Nov 2025Source
  • Document02-21.pdf · uploaded 19 Nov 2025Source
  • Document03-21.pdf · uploaded 19 Nov 2025Source
  • Document04-21.pdf · uploaded 19 Nov 2025Source
  • Document05-21.pdf · uploaded 19 Nov 2025Source
  • Document06-21.pdf · uploaded 19 Nov 2025Source
  • Document07-21.pdf · uploaded 19 Nov 2025Source
  • Document14-21_D3.pdf · uploaded 19 Nov 2025Source
  • Document15-21_D3.pdf · uploaded 19 Nov 2025Source
  • Document14-21_D3 - Parking Highlighted.pdf · uploaded 19 Nov 2025Source
  • Document01-21 - Plot Area and BUA Highlighted.pdf · uploaded 29 Dec 2025Source

Technical (Architect)

  • DocumentForm1 D3.pdf · uploaded 12 Nov 2024Source
  • DocumentForm 1 SkyHigh Towers D3.pdf · uploaded 29 Jan 2025Source
  • DocumentForm1 SkyHigh D3 Mar 2025.pdf · uploaded 2 May 2025Source
  • DocumentForm 1 Highsky Tower D3.pdf · uploaded 22 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2_SkyHigh Towers D3.pdf · uploaded 12 Nov 2024Source
  • DocumentForm 2 SkyHigh Towers D3.pdf · uploaded 29 Jan 2025Source
  • DocumentForm2 SkyHigh D3 Mar 2025.pdf · uploaded 2 May 2025Source
  • DocumentForm 2 Skyhigh tower D3.pdf · uploaded 22 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 3, S.No. 277 Plot No. 2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—136 units in all
Address
S.No. 277 Plot No. 2 & 3, Maan, Tal. Mulshi, Near Hinewadi Phase II, HinjewadiPIN 411057
Village
Man, Mulshi taluka
Land area for this project
3,413 sq m (36,733 sq ft)
Approved layout area
33,880 sq m (3,64,681 sq ft)
Permissible built-up area
7,571 sq m (81,490 sq ft)
Sanctioned built-up area
7,571 sq m (81,490 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

3S.No. 277 Plot No. 2

Land as published on MahaRERA's project page

S.No. 277 Plot No. 2 & 3, Maan, Tal. Mulshi

Boundaries

North
Future phase
South
Adj S No D2
East
Adj S NO 341
West
15 M wide road boundary

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking136 units

136 units registered

— · 136 units
TypeCarpet areaUnits
——136

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVKa architecture—
Chartered accountantPriyanka Chordiya And Associates—
Chartered accountantSAC & Co LLp—
EngineerManjiri Desai—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology