Deedo IDDP-PUN-HWQ4Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.
Man, Pune 411057 · Property rates in Man · by Joyville Shapoorji Housing Private Limited · 69% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed
- P52100027234Registered 25 Nov 2020, completion promised 30 Jun 2025, and still not shown completed today.
- P52100027244Registered 25 Nov 2020, completion promised 30 Jun 2025, and still not shown completed today.
No extension certificate on record.
2 registrations · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrations2
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100027234 | 25 Nov 2020 | 30 Jun 2025 | 30 Jun 2025 | Joyville Shapoorji Housing Private Limited | Project page |
| P52100027244 | 25 Nov 2020 | 30 Jun 2025 | 30 Jun 2025 | Joyville Shapoorji Housing Private Limited | Project page |
Documents314
2 documents held by Deedo, 312 filings listed on MahaRERA's project page
Registration certificate (2)
Finance
Legal
- Legal Title reportP52100027244 · Title Cer- p1.pdf · uploaded 23 Nov 2020Source
- Legal Title reportP52100027244 · Title Cer- p2.pdf · uploaded 23 Nov 2020Source
- Legal Title reportP52100027244 · Title Cer- p3.pdf · uploaded 23 Nov 2020Source
- Legal Title reportP52100027244 · Title Cer- p4.pdf · uploaded 23 Nov 2020Source
Show all 314 documentsShow fewer documents
Legal
- Declaration Form BP52100027244 · Form B Phase 4-min.pdf · uploaded 23 Nov 2020Source
- Legal Title reportP52100027234 · Title Cer- p1.pdf · uploaded 23 Nov 2020Source
- Legal Title reportP52100027234 · Title Cer- p2.pdf · uploaded 23 Nov 2020Source
- Legal Title reportP52100027234 · Title Cer- p3.pdf · uploaded 23 Nov 2020Source
- Legal Title reportP52100027234 · Title Cer- p4.pdf · uploaded 23 Nov 2020Source
- Declaration Form BP52100027234 · Form B Phase V-min.pdf · uploaded 23 Nov 2020Source
- OtherP52100027244 · Declaration.pdf · uploaded 29 Nov 2020Source
Migrated
- 1 PAN CardP52100027244 · Joyville PAN.PDF · uploaded 23 Nov 2020Source
- 1 Copy of the legal title reportP52100027244 · Title Cer- p1.pdf · uploaded 23 Nov 2020Source
- 2 Copy of the legal title reportP52100027244 · Title Cer- p2.pdf · uploaded 23 Nov 2020Source
- 3 Copy of the legal title reportP52100027244 · Title Cer- p3.pdf · uploaded 23 Nov 2020Source
- 4 Copy of the legal title reportP52100027244 · Title Cer- p4.pdf · uploaded 23 Nov 2020Source
- 1 Details of encumbrancesP52100027244 · ENCUMBRANCE PHASE 4.pdf · uploaded 23 Nov 2020Source
- 1 Copy of Layout Approval (in case of layout)P52100027244 · Layout.pdf · uploaded 23 Nov 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentP52100027244 · Building Plan Approval.pdf · uploaded 23 Nov 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentP52100027244 · Commencement Certificate.pdf · uploaded 23 Nov 2020Source
- 1 Declaration in FORM BP52100027244 · Form B Phase 4-min.pdf · uploaded 23 Nov 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · CA2-min.pdf · uploaded 23 Nov 2020Source
- 1 Proforma of Allotment letterP52100027244 · AFS 1-33.pdf · uploaded 23 Nov 2020Source
- 2 Proforma of Allotment letterP52100027244 · AFS 34-66.pdf · uploaded 23 Nov 2020Source
- 3 Proforma of Allotment letterP52100027244 · Hinjawadi Plot 2 Allotment Letter.pdf · uploaded 23 Nov 2020Source
- 1 PAN CardP52100027234 · Joyville PAN.PDF · uploaded 23 Nov 2020Source
- 1 Copy of the legal title reportP52100027234 · Title Cer- p1.pdf · uploaded 23 Nov 2020Source
- 2 Copy of the legal title reportP52100027234 · Title Cer- p2.pdf · uploaded 23 Nov 2020Source
- 3 Copy of the legal title reportP52100027234 · Title Cer- p3.pdf · uploaded 23 Nov 2020Source
- 4 Copy of the legal title reportP52100027234 · Title Cer- p4.pdf · uploaded 23 Nov 2020Source
- 1 Details of encumbrancesP52100027234 · Encumbrance Phase V.pdf · uploaded 23 Nov 2020Source
- 1 Copy of Layout Approval (in case of layout)P52100027234 · Layout.pdf · uploaded 23 Nov 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentP52100027234 · Building Plan Approval.pdf · uploaded 23 Nov 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentP52100027234 · Commencement Certificate.pdf · uploaded 23 Nov 2020Source
- 1 Declaration in FORM BP52100027234 · Form B Phase V-min.pdf · uploaded 23 Nov 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · CA1-min.pdf · uploaded 23 Nov 2020Source
- 1 Proforma of Allotment letterP52100027234 · Hinjawadi Plot 2 Allotment Letter.pdf · uploaded 23 Nov 2020Source
- 2 Proforma of Allotment letterP52100027234 · AFS 1-33.pdf · uploaded 23 Nov 2020Source
- 3 Proforma of Allotment letterP52100027234 · AFS 34-66.pdf · uploaded 23 Nov 2020Source
- 1 OtherP52100027244 · Declaration.pdf · uploaded 29 Nov 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Architect's Certificate Pune Plot 2 Phase 4 Tower D(Auris).pdf · uploaded 6 Jan 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris).pdf · uploaded 6 Jan 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Architect's Certificate Pune Plot 2 Phase 5 Tower A (Vista).pdf · uploaded 6 Jan 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista).pdf · uploaded 6 Jan 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · RERACERT1 PHASE 4 TOWER D AURIS.pdf · uploaded 25 Jan 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · RERACER2 PHASE 5 TOWER A VISTA.pdf · uploaded 25 Jan 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Architect's Certificate Pune Plot 2 Phase 4 Tower D(Auris).pdf · uploaded 13 Apr 2021Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_31st March 21_.pdf · uploaded 13 Apr 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100027244 · QA- Tower-D- AURIS.pdf · uploaded 13 Apr 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Architect's Certificate Pune Plot 2 Phase 5 Tower A (Vista).pdf · uploaded 13 Apr 2021Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista) - 31st March 21.pdf · uploaded 13 Apr 2021Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · hinjewadi2phase4_compressed.pdf · uploaded 26 May 2021Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · hinjewadi2phase5_Compressed.pdf · uploaded 26 May 2021Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Architect's Certificate Pune Plot 2 Phase 4 Tower D(Auris).pdf · uploaded 14 Jul 2021Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_30th June 21.pdf · uploaded 14 Jul 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100027244 · Form 2A - Plot-2 - Phase-4 - Sensorium - Auris - Tower-D.pdf · uploaded 14 Jul 2021Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Architect's Certificate Pune Plot 2 Phase 5 Tower A (Vista).pdf · uploaded 14 Jul 2021Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_30th June 21.pdf · uploaded 14 Jul 2021Source
- 1 Disclosure of sold/ booked inventoryP52100027244 · Phase 4_Merged.pdf · uploaded 4 Aug 2021Source
- 2 Disclosure of sold/ booked inventoryP52100027244 · Sensorium Phase 4.pdf · uploaded 7 Aug 2021Source
- 1 Disclosure of sold/ booked inventoryP52100027234 · Sensorium Phase 5.pdf · uploaded 7 Aug 2021Source
- 3 Disclosure of sold/ booked inventoryP52100027244 · Hinjewadi Plot 2 -Phase 4.pdf · uploaded 9 Sep 2021Source
- 4 Disclosure of sold/ booked inventoryP52100027244 · Hinjewadi Plot 2-Phase 4.pdf · uploaded 9 Sep 2021Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · Pune Plot 2 Phase 4 Tower D(Auris)- Form 3 CA Certificate.pdf · uploaded 12 Sep 2021Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · Pune Plot 2 Phase 5 Tower A (Vista)- Form 3 CA Certificate.pdf · uploaded 12 Sep 2021Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Architect's Certificate Pune Plot 2 Phase 4 Tower D(Auris)_compressed.pdf · uploaded 5 Oct 2021Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_30th September 21.pdf · uploaded 5 Oct 2021Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100027244 · Form 2A - Plot-2 - Phase-4 - Sensorium - Auris - Tower-D.pdf · uploaded 5 Oct 2021Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Architect's Certificate Pune Plot 2 Phase 5 Tower A (Vista)_compressed.pdf · uploaded 5 Oct 2021Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_30th September 21.pdf · uploaded 5 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100027244 · Hinjewadi Plot 2 Phase 4 Annual Certificate and Cover Letter .pdf · uploaded 30 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100027234 · Hinjewadi Plot 2 Phase 5 Annual Certificate and Cover Letter .pdf · uploaded 30 Oct 2021Source
- 5 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 29 Nov 2021Source
- 6 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 29 Nov 2021Source
- 7 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 29 Nov 2021Source
- 8 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 29 Nov 2021Source
- 2 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE IV - PHASE V.pdf · uploaded 29 Nov 2021Source
- 3 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 29 Nov 2021Source
- 4 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 29 Nov 2021Source
- 5 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE IV - PHASE V.pdf · uploaded 29 Nov 2021Source
- 9 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 30 Nov 2021Source
- 1 CERSAI detailsP52100027244 · Hinjewadi.pdf · uploaded 30 Nov 2021Source
- 6 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 30 Nov 2021Source
- 1 CERSAI detailsP52100027234 · Hinjewadi.pdf · uploaded 30 Nov 2021Source
- 10 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 2 Dec 2021Source
- 7 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 2 Dec 2021Source
- 11 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 15 Dec 2021Source
- 8 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 15 Dec 2021Source
- 12 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 23 Dec 2021Source
- 9 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 23 Dec 2021Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Architect's Certificate Pune Plot 2 Phase 4 Tower D(Auris).pdf · uploaded 15 Jan 2022Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_December 21.pdf · uploaded 15 Jan 2022Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100027244 · Form 2A - Plot-2 - Phase-4 - Sensorium - Auris - Tower-D-compressed.pdf · uploaded 15 Jan 2022Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Architect's Certificate Pune Plot 2 Phase 5 Tower A (Vista).pdf · uploaded 15 Jan 2022Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_Decemeber 21.pdf · uploaded 15 Jan 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100027234 · Form 2A - Plot-2 - Phase-5 - Sensorium - Vista - Tower-A-compressed.pdf · uploaded 15 Jan 2022Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202112 RERA Certificate Ph 4 - RERA.pdf · uploaded 18 Jan 2022Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202112 RERA Certificate Ph 5 - RERA.pdf · uploaded 18 Jan 2022Source
- 13 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 20 Jan 2022Source
- 10 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 20 Jan 2022Source
- 14 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 4 Feb 2022Source
- 11 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 4 Feb 2022Source
- 15 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 28 Feb 2022Source
- 12 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 28 Feb 2022Source
- 16 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 9 Mar 2022Source
- 13 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 9 Mar 2022Source
- 17 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 10 Mar 2022Source
- 14 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 10 Mar 2022Source
- 18 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 30 Mar 2022Source
- 15 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 30 Mar 2022Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_March 22.pdf · uploaded 12 Apr 2022Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_March 22.pdf · uploaded 12 Apr 2022Source
- 19 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 13 Apr 2022Source
- 16 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 13 Apr 2022Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Architect's Certificate Pune Plot 2 Phase 4 Tower D_4th Phase.pdf · uploaded 2 Jun 2022Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Architect's Certificate Pune Plot 2 Phase 5 Tower A_5th Phase.pdf · uploaded 2 Jun 2022Source
- 5 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100027244 · Form 2A - Plot-2 - Phase-4 - Sensorium - Auris - Tower-D.pdf · uploaded 3 Jun 2022Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202203 RERA Certificate Ph 4 - RERA.pdf · uploaded 3 Jun 2022Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100027234 · Form 2A - Plot-2 - Phase-5 - Sensorium - Vista - Tower-A.pdf · uploaded 3 Jun 2022Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Architect's Certificate Pune Plot 2 Phase 4 Tower D(Auris).pdf · uploaded 19 Jul 2022Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_June 22.pdf · uploaded 19 Jul 2022Source
- 20 Disclosure of sold/ booked inventoryP52100027244 · Sensorium Phase 4.pdf · uploaded 19 Jul 2022Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202206 RERA Certificate Ph 4 - RERA.pdf · uploaded 19 Jul 2022Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Architect's Certificate Pune Plot 2 Phase 5 Tower A (Vista).pdf · uploaded 19 Jul 2022Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_June 22.pdf · uploaded 19 Jul 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100027234 · Form 2A - Plot-2 - Phase-5 - Sensorium - Vista - Tower-A.pdf · uploaded 19 Jul 2022Source
- 17 Disclosure of sold/ booked inventoryP52100027234 · Sensorium Phase 5.pdf · uploaded 19 Jul 2022Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202206 RERA Certificate Ph 5 - RERA.pdf · uploaded 19 Jul 2022Source
- 21 Disclosure of sold/ booked inventoryP52100027244 · Sensorium Phase 4.pdf · uploaded 30 Jul 2022Source
- 18 Disclosure of sold/ booked inventoryP52100027234 · Sensorium Phase 5.pdf · uploaded 30 Jul 2022Source
- 22 Disclosure of sold/ booked inventoryP52100027244 · Sensorium Phase 4.pdf · uploaded 17 Aug 2022Source
- 19 Disclosure of sold/ booked inventoryP52100027234 · Sensorium Phase 5.pdf · uploaded 17 Aug 2022Source
- 23 Disclosure of sold/ booked inventoryP52100027244 · Phase 4.pdf · uploaded 25 Aug 2022Source
- 20 Disclosure of sold/ booked inventoryP52100027234 · Phase 5.pdf · uploaded 25 Aug 2022Source
- 24 Disclosure of sold/ booked inventoryP52100027244 · Sensorium Phase 4.pdf · uploaded 14 Sep 2022Source
- 21 Disclosure of sold/ booked inventoryP52100027234 · Sensorium Phase 5.pdf · uploaded 14 Sep 2022Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100027244 · Hinjewadi Plot 2 Phase 4 Signed.pdf · uploaded 29 Sep 2022Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100027234 · Hinjewadi Plot 2 Phase 5 Signed.pdf · uploaded 29 Sep 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100027244 · Hinjewadi Plot 2 Phase 4 Signed.pdf · uploaded 30 Sep 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100027234 · Hinjewadi Plot 2 Phase 5 Signed.pdf · uploaded 30 Sep 2022Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Architect's Certificate Pune Plot 2 Phase 4 Tower D(Auris).pdf · uploaded 6 Oct 2022Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_September 22.pdf · uploaded 6 Oct 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100027244 · Form 2A - Plot-2 - Phase-4 - Sensorium - Auris - Tower-D.pdf · uploaded 6 Oct 2022Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Architect's Certificate Pune Plot 2 Phase 5 Tower A (Vista).pdf · uploaded 6 Oct 2022Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_September 22.pdf · uploaded 6 Oct 2022Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100027234 · Form 2A - Plot-2 - Phase-5 - Sensorium - Vista - Tower-A.pdf · uploaded 6 Oct 2022Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202209 RERA Certificate Ph 4 - RERA.pdf · uploaded 13 Oct 2022Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202209 RERA Certificate Ph 5 - RERA.pdf · uploaded 13 Oct 2022Source
- 25 Disclosure of sold/ booked inventoryP52100027244 · Phase 4.pdf · uploaded 15 Oct 2022Source
- 22 Disclosure of sold/ booked inventoryP52100027234 · Phase 5.pdf · uploaded 15 Oct 2022Source
- 26 Disclosure of sold/ booked inventoryP52100027244 · Phase 4.pdf · uploaded 17 Oct 2022Source
- 23 Disclosure of sold/ booked inventoryP52100027234 · Phase 5.pdf · uploaded 17 Oct 2022Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100027244 · Auris.pdf · uploaded 18 Oct 2022Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100027234 · Vista.pdf · uploaded 18 Oct 2022Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Architect's Certificate Pune Plot 2 Phase 4 Tower D(Auris).pdf · uploaded 7 Jan 2023Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_December 22.pdf · uploaded 7 Jan 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Architect's Certificate Pune Plot 2 Phase 5 Tower A (Vista).pdf · uploaded 7 Jan 2023Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_December 22.pdf · uploaded 7 Jan 2023Source
- 27 Disclosure of sold/ booked inventoryP52100027244 · Sensorium Ph4.pdf · uploaded 12 Jan 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202212 RERA Certificate Ph 4 - RERA.pdf · uploaded 12 Jan 2023Source
- 24 Disclosure of sold/ booked inventoryP52100027234 · Sensorium Ph5.pdf · uploaded 12 Jan 2023Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_December 22 (1).pdf · uploaded 14 Jan 2023Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202212 RERA Certificate Ph 4 - RERA.pdf · uploaded 14 Jan 2023Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_December 22 (1).pdf · uploaded 14 Jan 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202212 RERA Certificate Ph 5 - RERA.pdf · uploaded 14 Jan 2023Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Tower D.pdf · uploaded 17 Apr 2023Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_March 23.pdf · uploaded 17 Apr 2023Source
- 28 Disclosure of sold/ booked inventoryP52100027244 · Phase4.pdf · uploaded 17 Apr 2023Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202303 RERA Certificate Ph 4 - RERA.pdf · uploaded 17 Apr 2023Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Tower A.pdf · uploaded 17 Apr 2023Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_March 23.pdf · uploaded 17 Apr 2023Source
- 25 Disclosure of sold/ booked inventoryP52100027234 · Phase5.pdf · uploaded 17 Apr 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202303 RERA Certificate Ph 5 - RERA.pdf · uploaded 17 Apr 2023Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Sensorium Phase 4.pdf · uploaded 18 Jul 2023Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_June 23.pdf · uploaded 18 Jul 2023Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202306 RERA Certificate Ph 4 - RERA.pdf · uploaded 18 Jul 2023Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Sensorium Phase 5.pdf · uploaded 18 Jul 2023Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_June 23.pdf · uploaded 18 Jul 2023Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202306 RERA Certificate Ph 5 - RERA.pdf · uploaded 18 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100027244 · Sensorium Phase 4 FY 22-23.pdf · uploaded 28 Sep 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100027234 · Sensorium Phase 5 FY 22-23.pdf · uploaded 28 Sep 2023Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Tower D.pdf · uploaded 18 Oct 2023Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_September 23.pdf · uploaded 18 Oct 2023Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202309 RERA Certificate Ph 4 - RERA.pdf · uploaded 18 Oct 2023Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Tower A.pdf · uploaded 18 Oct 2023Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_September 23.pdf · uploaded 18 Oct 2023Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202309 RERA Certificate Ph 5 - RERA.pdf · uploaded 18 Oct 2023Source
- 29 Disclosure of sold/ booked inventoryP52100027244 · Phase 4.pdf · uploaded 19 Oct 2023Source
- 26 Disclosure of sold/ booked inventoryP52100027234 · Phase 5.pdf · uploaded 19 Oct 2023Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Tower D.pdf · uploaded 16 Jan 2024Source
- 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_December 23.pdf · uploaded 16 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100027244 · Tower D.pdf · uploaded 16 Jan 2024Source
- 30 Disclosure of sold/ booked inventoryP52100027244 · Phase 4.pdf · uploaded 16 Jan 2024Source
- 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202312 RERA Certificate Ph 4 - RERA.pdf · uploaded 16 Jan 2024Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Tower A.pdf · uploaded 16 Jan 2024Source
- 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_December 23.pdf · uploaded 16 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100027234 · Tower A.pdf · uploaded 16 Jan 2024Source
- 27 Disclosure of sold/ booked inventoryP52100027234 · Phase 5.pdf · uploaded 16 Jan 2024Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202312 RERA Certificate Ph 5 - RERA.pdf · uploaded 16 Jan 2024Source
- 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · sensorium, Phase 4 - 30th Sept 2021.pdf · uploaded 23 Feb 2024Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · Sensorium, Phase 5 -31st Dec 2020.pdf · uploaded 23 Feb 2024Source
- 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · Sensorium Phase 5 -30th Sept_21.pdf · uploaded 23 Feb 2024Source
- 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · Sensorium, Phase 5 - 31st March 2022.pdf · uploaded 23 Feb 2024Source
- 16 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · Sensorium Phase 4.pdf · uploaded 26 Feb 2024Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Arch Phase 4.pdf · uploaded 19 Apr 2024Source
- 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_March 24.pdf · uploaded 19 Apr 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100027244 · Tower D.pdf · uploaded 19 Apr 2024Source
- 31 Disclosure of sold/ booked inventoryP52100027244 · Phase 4.pdf · uploaded 19 Apr 2024Source
- 17 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202403 RERA Certificate Ph 4 - RERA.pdf · uploaded 19 Apr 2024Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Arch Phase 5.pdf · uploaded 19 Apr 2024Source
- 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_March 24.pdf · uploaded 19 Apr 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100027234 · Tower A.pdf · uploaded 19 Apr 2024Source
- 28 Disclosure of sold/ booked inventoryP52100027234 · Phase 5.pdf · uploaded 19 Apr 2024Source
- 16 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202403 RERA Certificate Ph 5 - RERA.pdf · uploaded 19 Apr 2024Source
- 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Tower D.pdf · uploaded 20 Jul 2024Source
- 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_June 24.pdf · uploaded 20 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100027244 · Tower D.pdf · uploaded 20 Jul 2024Source
- 32 Disclosure of sold/ booked inventoryP52100027244 · Ph4.pdf · uploaded 20 Jul 2024Source
- 18 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202406 RERA Certificate Ph 4 - RERA.pdf · uploaded 20 Jul 2024Source
- 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Tower A.pdf · uploaded 20 Jul 2024Source
- 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_June 24.pdf · uploaded 20 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100027234 · Tower A.pdf · uploaded 20 Jul 2024Source
- 29 Disclosure of sold/ booked inventoryP52100027234 · Ph5.pdf · uploaded 20 Jul 2024Source
- 17 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202406 RERA Certificate Ph 5 - RERA.pdf · uploaded 20 Jul 2024Source
- Form 5 (FY 2023-2024)P52100027244 · Sensorium_Phase_4_Upload.pdf · uploaded 25 Sep 2024Source
- Form 5 (FY 2023-2024)P52100027234 · Sensorium_Phase_5_Upload.pdf · uploaded 28 Sep 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100027244 · Sensorium_Phase_4_-_March_24.pdf · uploaded 6 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100027234 · Sensorium_Phase_5_-March_24.pdf · uploaded 6 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Sensorium Phase 4.pdf · uploaded 20 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202409 RERA Certificate Ph 4 - RERA.pdf · uploaded 20 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_October 24.pdf · uploaded 20 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 20 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Sensorium Phase 5.pdf · uploaded 20 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202409 RERA Certificate Ph 5 - RERA.pdf · uploaded 20 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_October 24.pdf · uploaded 20 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 20 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Tower D.pdf · uploaded 19 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_December 24.pdf · uploaded 19 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202412 RERA Certificate Ph 4 - RERA.pdf · uploaded 19 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Tower D.pdf · uploaded 19 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_December 24.pdf · uploaded 19 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202412 RERA Certificate Ph 4 - RERA.pdf · uploaded 19 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Tower D.pdf · uploaded 19 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202412 RERA Certificate Ph 4 - RERA.pdf · uploaded 19 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_December 24.pdf · uploaded 19 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Tower A.pdf · uploaded 19 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_December 24.pdf · uploaded 19 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202412 RERA Certificate Ph 5 - RERA.pdf · uploaded 19 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Tower A.pdf · uploaded 19 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_December 24.pdf · uploaded 19 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202412 RERA Certificate Ph 5 - RERA.pdf · uploaded 19 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Tower A.pdf · uploaded 19 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202412 RERA Certificate Ph 5 - RERA.pdf · uploaded 19 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_December 24.pdf · uploaded 19 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027244 · Tower D.pdf · uploaded 20 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027244 · Tower D.pdf · uploaded 20 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100027234 · Tower A.pdf · uploaded 20 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100027234 · Tower A.pdf · uploaded 20 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027244 · 202503 RERA Certificate Ph 4 - RERA.pdf · uploaded 21 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryP52100027244 · Sensorium,PHASE IV - PHASE IV.pdf · uploaded 21 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100027234 · 202503 RERA Certificate Ph 5 - RERA.pdf · uploaded 21 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryP52100027234 · Sensorium,PHASE V - PHASE V.pdf · uploaded 21 Apr 2025Source
- Form 5 (FY 2024-2025)P52100027244 · Form 5_Hinjewadi Phase 4.pdf · uploaded 28 Sep 2025Source
- Form 5 (FY 2024-2025)P52100027234 · Form 5_Hinjewadi Phase 5.pdf · uploaded 30 Sep 2025Source
- Form 2A (FY 2025-2026)P52100027244 · f2a.pdf · uploaded 14 Aug 2026Source
- Form 5 (FY 2025-2026)P52100027244 · f5.pdf · uploaded 14 Aug 2026Source
- Form 1P52100027234 · f1.pdf · uploaded 14 Aug 2026Source
- Form 2P52100027234 · f2.pdf · uploaded 14 Aug 2026Source
- Form 3P52100027234 · f3.pdf · uploaded 14 Aug 2026Source
- Disclosure of Sold and Booked InventoryP52100027234 · sold.pdf · uploaded 14 Aug 2026Source
- Form 2A (FY 2025-2026)P52100027234 · f2a.pdf · uploaded 14 Aug 2026Source
- Form 5 (FY 2025-2026)P52100027234 · f5 26.pdf · uploaded 14 Aug 2026Source
- Form 1P52100027244 · f1.pdf · uploaded 18 Aug 2026Source
- Form 2P52100027244 · f2.pdf · uploaded 18 Aug 2026Source
- Form 3P52100027244 · f3.pdf · uploaded 18 Aug 2026Source
- Disclosure of Sold and Booked InventoryP52100027244 · sold.pdf · uploaded 18 Aug 2026Source
Technical
Technical (Architect)
- DocumentP52100027244 · Sensorium Phase 4 _Form 1.pdf · uploaded 25 Sep 2024Source
- DocumentP52100027234 · Sensorium Phase 5_Form 1.pdf · uploaded 25 Sep 2024Source
- DocumentP52100027244 · Sensorium Phase 4.pdf · uploaded 20 Oct 2024Source
- DocumentP52100027234 · Sensorium Phase 5.pdf · uploaded 20 Oct 2024Source
- DocumentP52100027244 · Tower D.pdf · uploaded 19 Jan 2025Source
- DocumentP52100027244 · Tower D.pdf · uploaded 19 Jan 2025Source
- DocumentP52100027244 · Tower D.pdf · uploaded 19 Jan 2025Source
- DocumentP52100027234 · Tower A.pdf · uploaded 19 Jan 2025Source
- DocumentP52100027234 · Tower A.pdf · uploaded 19 Jan 2025Source
- DocumentP52100027234 · Tower A.pdf · uploaded 19 Jan 2025Source
- DocumentP52100027244 · Tower D.pdf · uploaded 20 Apr 2025Source
- DocumentP52100027234 · Tower A.pdf · uploaded 20 Apr 2025Source
Technical (Engineer)
- DocumentP52100027244 · Form 2_Sensorium Phase 4.pdf · uploaded 25 Sep 2024Source
- DocumentP52100027234 · Engineer's Certificate_Sensorium Phase 5 Tower A (Vista)_September 24.pdf · uploaded 26 Sep 2024Source
- DocumentP52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_October 24.pdf · uploaded 20 Oct 2024Source
- DocumentP52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_October 24.pdf · uploaded 20 Oct 2024Source
- DocumentP52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_December 24.pdf · uploaded 19 Jan 2025Source
- DocumentP52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_December 24.pdf · uploaded 19 Jan 2025Source
- DocumentP52100027244 · Engineer's Certificate_Plot 2 Phase 4 Tower D(Auris)_December 24.pdf · uploaded 19 Jan 2025Source
- DocumentP52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_December 24.pdf · uploaded 19 Jan 2025Source
- DocumentP52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_December 24.pdf · uploaded 19 Jan 2025Source
- DocumentP52100027234 · Engineer's Certificate_Plot 2 Phase 5 Tower A (Vista)_December 24.pdf · uploaded 19 Jan 2025Source
- DocumentP52100027244 · Tower D.pdf · uploaded 20 Apr 2025Source
- DocumentP52100027234 · Tower A.pdf · uploaded 20 Apr 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 98/99/101/A/1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Phases
- 2
- Unit types
- 2BHK, 3BHK264 units in all
- Address
- 98/99/101/A/1, Village Maan, Village MaanPIN 411057
- Village
- Man, Mulshi taluka
- Location
- 19.38750, 75.16320
- Land area for this project
- 1,305 sq m (14,049 sq ft)
- Permissible built-up area
- 9,981 sq m (1,07,430 sq ft)
- Sanctioned built-up area
- 9,981 sq m (1,07,430 sq ft)
- Recreational open space
- 5,234 sq m (56,343 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
- Also registered as
- Sensorium, Phase V, Sensorium, Phase IV
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
98/99/101/A/1
Boundaries
- North
- 98 99 101 A 1
- South
- 98 99 101 A 1
- East
- 98 99 101 A 1
- West
- 98 99 101 A 1
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking264 units
264 of 264 units booked (100%), as the promoter reported to MahaRERA
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P52100027234 | Tower A - VISTA | 2BHK | 49.85 sq m · 537 sq ft | 3 | 3 |
| P52100027234 | Tower A - VISTA | 2BHK | 52.14 sq m · 561 sq ft | 18 | 18 |
| P52100027234 | Tower A - VISTA | 2BHK | 52.51 sq m · 565 sq ft | 18 | 18 |
| P52100027234 | Tower A - VISTA | 2BHK | 54.57 sq m · 587 sq ft | 3 | 3 |
| P52100027234 | Tower A - VISTA | 2BHK | 55.64 sq m · 599 sq ft | 20 | 20 |
| P52100027234 | Tower A - VISTA | 2BHK | 56.09 sq m · 604 sq ft | 22 | 22 |
| P52100027234 | Tower A - VISTA | 2BHK | 56.6 sq m · 609 sq ft | 2 | 2 |
| P52100027234 | Tower A - VISTA | 2BHK | 57.81 sq m · 622 sq ft | 1 | 1 |
Show all 18 unit rowsShow fewer unit rows
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P52100027234 | Tower A - VISTA | 2BHK | 60.72 sq m · 654 sq ft | 1 | 1 |
| P52100027234 | Tower A - VISTA | 3BHK | 73.13 sq m · 787 sq ft | 20 | 20 |
| P52100027234 | Tower A - VISTA | 3BHK | 73.55 sq m · 792 sq ft | 22 | 22 |
| P52100027234 | Tower A - VISTA | 3BHK | 74.05 sq m · 797 sq ft | 2 | 2 |
| P52100027244 | Tower D Auris | 2BHK | 50.97 sq m · 549 sq ft | 40 | 40 |
| P52100027244 | Tower D Auris | 2BHK | 51.37 sq m · 553 sq ft | 44 | 44 |
| P52100027244 | Tower D Auris | 2BHK | 51.88 sq m · 558 sq ft | 4 | 4 |
| P52100027244 | Tower D Auris | 2BHK | 58.63 sq m · 631 sq ft | 19 | 19 |
| P52100027244 | Tower D Auris | 2BHK | 59.18 sq m · 637 sq ft | 20 | 20 |
| P52100027244 | Tower D Auris | 2BHK | 59.69 sq m · 642 sq ft | 5 | 5 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals46
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. | RERA |
|---|---|---|---|
| Architect | Abhikalpan Architect and Planners | — | P52100027234 |
| Architect | Abhikalpan Architect and Planners | — | P52100027244 |
| Architect | MSK ARCH And ASSOCIATES | — | P52100027234 |
| Architect | MSK Architectsand Associates | — | P52100027234 |
| Architect | MSK ARCHITECTS and associates | — | P52100027234 |
| Architect | MSK Architects & Associates | — | P52100027234 |
| Architect | MSK Architects & Associates | — | P52100027244 |
| Chartered accountant | B R Nagda & Co | — | P52100027244 |
Show all 46 professionalsShow fewer professionals
| Role | Name | Registration no. | RERA |
|---|---|---|---|
| Chartered accountant | B R Nagda & Co | — | P52100027234 |
| Chartered accountant | Harshad Doshi | — | P52100027234 |
| Chartered accountant | Harshad Doshi | — | P52100027244 |
| Engineer | akshay lalit kasar | — | P52100027234 |
| Engineer | Akshay Lalit Kasar | — | P52100027244 |
| Engineer | akshay lalit kasar Celestia Phase 6 | — | P52100027244 |
| Registered real estate agent | Aditya Agarwalla | — | P52100027234 |
| Registered real estate agent | Akshay Prashant Fulambarkar | — | P52100027234 |
| Registered real estate agent | Aman Kumar Singh | — | P52100027234 |
| Registered real estate agent | Anant Haridas Kate | — | P52100027234 |
| Registered real estate agent | Anil Menon | — | P52100027244 |
| Registered real estate agent | Anil Menon | — | P52100027234 |
| Registered real estate agent | Ashok Chandrashekhar Patil | — | P52100027234 |
| Registered real estate agent | Badal Suresh Kharat | — | P52100027234 |
| Registered real estate agent | Bharat Digambar Beldar | — | P52100027234 |
| Registered real estate agent | Credent Property Advisory Private Limited | — | P52100027244 |
| Registered real estate agent | DInesh Shailandra Sawkar | — | P52100027244 |
| Registered real estate agent | DInesh Shailandra Sawkar | — | P52100027234 |
| Registered real estate agent | Firstdoor Realty LLP | — | P52100027244 |
| Registered real estate agent | Harmony Infrasolutions Private Limited | — | P52100027234 |
| Registered real estate agent | Harshal Balkrishna Patil | — | P52100027244 |
| Registered real estate agent | Jenny Bejoy | — | P52100027234 |
| Registered real estate agent | Magicstone Spaces LLP | — | P52100027234 |
| Registered real estate agent | Mallika Prashant Sharma | — | P52100027234 |
| Registered real estate agent | Manisha Lifespaces Consulting Pvt. Ltd. | — | P52100027244 |
| Registered real estate agent | Manish Kumar Satya Sahu | — | P52100027234 |
| Registered real estate agent | Pin Click Property Management Pvt Ltd. | — | P52100027234 |
| Registered real estate agent | Prasanna Vinod Thakkar | — | P52100027234 |
| Registered real estate agent | Propbizz Real Estate | — | P52100027244 |
| Registered real estate agent | Propengine Realtech Private Limited | — | P52100027234 |
| Registered real estate agent | R-Constellation Pvt. Ltd. | — | P52100027234 |
| Registered real estate agent | Rudram Realty | — | P52100027234 |
| Registered real estate agent | Rudram Realty | — | P52100027244 |
| Registered real estate agent | Sanket Pradip Deshmukh | — | P52100027244 |
| Registered real estate agent | Shishu Singh | — | P52100027234 |
| Registered real estate agent | Sneha Ambirkar | — | P52100027234 |
| Registered real estate agent | Sushila Suryakant Shinde | — | P52100027234 |
| Registered real estate agent | Yogesh Mohan Shahane | — | P52100027244 |
Source: MahaRERA project page. Contact details are not shown.