Extended 42 mo12 floorsRERA P52100008065
A Wing, Platinum Park
Deedo IDDP-PUN-6ETV-AMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked58%54 of 93 · MahaRERA
Completion31 Dec 202430 Jun 2021 · revised
Units & parking in A Wing
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 39.6 m² (426 sq.ft) | 10 | 6 |
| 1BHK | 40.2 m² (433 sq.ft) | 9 | 3 |
| 1BHK | 41.7 m² (449 sq.ft) | 14 | 8 |
| 1BHK | 43.8 m² (471 sq.ft) | 5 | 2 |
| 1BHK | 45 m² (484 sq.ft) | 1 | 1 |
| 1BHK | 47 m² (506 sq.ft) | 1 | 0 |
| 1BHK | 47.3 m² (509 sq.ft) | 1 | 1 |
| 1BHK | 48.4 m² (521 sq.ft) | 1 | 1 |
| 1BHK | 49.3 m² (531 sq.ft) | 1 | 0 |
| 2BHK | 62.7 m² (674 sq.ft) | 9 | 4 |
| 2BHK | 69.5 m² (748 sq.ft) | 25 | 17 |
| 2BHK | 70.2 m² (755 sq.ft) | 12 | 7 |
| 2BHK | 74.1 m² (797 sq.ft) | 1 | 1 |
| 2BHK | 77 m² (829 sq.ft) | 1 | 1 |
| 2BHK | 81.6 m² (878 sq.ft) | 2 | 2 |
As registered with MahaRERA
- RERA registration
- P52100008065 · registered 18 Aug 2017
- Promised completion
- 30 Jun 2021
- Revised completion
- 31 Dec 2024
- Sanctioned habitable floors
- 12
- Sanctioned floors (incl. basement, stilt, podium)
- 12
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-6ETV-A
Questions about A Wing
When is A Wing due for completion?
The MahaRERA registration promises 30 Jun 2021, revised to 31 Dec 2024.
How many floors does A Wing have?
12 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology