Shambhavi
Deedo IDDP-PUN-0SYBIts promised completion date, Oct 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.
Kothrud, Pune 411038 · Property rates in Kothrud · Promoter: M/S Kharde Patil
Its promised completion date, Oct 2023, has passed and MahaRERA does not show it completed
- This projectRegistered 18 Dec 2019, completion promised 20 Oct 2023, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100023514
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100023514 | 18 Dec 2019 | 20 Oct 2023 | 20 Oct 2023 | M/S Kharde Patil | Project page |
Documents81
1 document held by Deedo, 80 filings listed on MahaRERA's project page
Finance
- PAN Cardpan firm.pdf · uploaded 11 Dec 2019Source
Legal
Migrated
- 1 PAN Cardpan firm.pdf · uploaded 11 Dec 2019Source
- 1 Copy of the legal title reportSHAM TITLE REP (2).pdf · uploaded 11 Dec 2019Source
- 1 Details of encumbrancesEncumb Letter KP .pdf · uploaded 11 Dec 2019Source
- 1 Copy of Layout Approval (in case of layout)Shambhavi Layout.pdf · uploaded 11 Dec 2019Source
Show all 81 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentShambhavi Plan.pdf · uploaded 11 Dec 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentnew cc shambhavi.pdf · uploaded 11 Dec 2019Source
- 1 Declaration in FORM BAffidavit.pdf · uploaded 11 Dec 2019Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Shambhavi rera arch.pdf · uploaded 11 Dec 2019Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Lt.pdf · uploaded 11 Dec 2019Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA RERA.pdf · uploaded 11 Dec 2019Source
- 1 Proforma of Allotment letterFinal Draft- Agreement To Sale - Shambhavi Bldg - 2019.pdf · uploaded 11 Dec 2019Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)1.pdf · uploaded 4 Nov 2020Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2.pdf · uploaded 4 Nov 2020Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)3.pdf · uploaded 4 Nov 2020Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)3.pdf · uploaded 4 Nov 2020Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)3.pdf · uploaded 4 Nov 2020Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Letter.pdf · uploaded 14 Apr 2021Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Letter.pdf · uploaded 14 Apr 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Engineer's Letter.pdf · uploaded 14 Apr 2021Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Letter.pdf · uploaded 14 Apr 2021Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)3.pdf · uploaded 28 Aug 2021Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)3.pdf · uploaded 28 Aug 2021Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)3.pdf · uploaded 28 Aug 2021Source
- 1 Disclosure of sold/ booked inventoryStock Letter.pdf · uploaded 29 Oct 2021Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Letter-compressed.pdf · uploaded 14 Jan 2022Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE-compressed.pdf · uploaded 14 Jan 2022Source
- 2 Disclosure of sold/ booked inventorySOLD UNIT-compressed.pdf · uploaded 14 Jan 2022Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)1.pdf · uploaded 14 Jan 2022Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Shambhavi Society Formation Certificate-converted.pdf · uploaded 22 Jan 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)form 5 2019-20.pdf · uploaded 16 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)form 5 2020-21.pdf · uploaded 16 May 2023Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)form 5 2021-22.pdf · uploaded 16 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)form 5 2021-22.pdf · uploaded 16 May 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 21 Oct 2023Source
- Form 2A (FY 2019-2020)Form 2A 01.pdf · uploaded 13 Jun 2025Source
- Form 2A (FY 2020-2021)Form 2A 02.pdf · uploaded 13 Jun 2025Source
- Form 2A (FY 2021-2022)Form 2A 03.pdf · uploaded 13 Jun 2025Source
- Form 2A (FY 2022-2023)Form 2A 04.pdf · uploaded 13 Jun 2025Source
- Form 2A (FY 2023-2024)Form 2A 05.pdf · uploaded 13 Jun 2025Source
- Form 5 (FY 2019-2020)form 5 2019-20.pdf · uploaded 14 Jun 2025Source
- Form 5 (FY 2020-2021)form 5 2020-21.pdf · uploaded 14 Jun 2025Source
- Form 5 (FY 2021-2022)form 5 2021-22.pdf · uploaded 14 Jun 2025Source
- Form 5 (FY 2022-2023)Form 5 2022-23.pdf · uploaded 14 Jun 2025Source
- Form 5 (FY 2023-2024)Form 5 2023-24.pdf · uploaded 14 Jun 2025Source
- Form 2Form 2.pdf · uploaded 30 Jun 2025Source
- Form 3Form 3.pdf · uploaded 30 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 30 Jun 2025Source
- Form 1Form 1.pdf · uploaded 30 Jun 2025Source
- Form 1Form 1.pdf · uploaded 30 Jun 2025Source
- Form 2Form 2.pdf · uploaded 30 Jun 2025Source
- Form 3Form 3.pdf · uploaded 30 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 30 Jun 2025Source
- Form 1Form 1.pdf · uploaded 30 Jun 2025Source
- Form 2Form 2.pdf · uploaded 30 Jun 2025Source
- Form 3Form 3.pdf · uploaded 30 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 30 Jun 2025Source
- Form 1Form 1.pdf · uploaded 30 Jun 2025Source
- Form 2Form 2.pdf · uploaded 30 Jun 2025Source
- Form 3Form 3.pdf · uploaded 30 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 30 Jun 2025Source
- Form 1Form 1.pdf · uploaded 30 Jun 2025Source
- Form 2Form 2.pdf · uploaded 30 Jun 2025Source
- Form 3Form 3.pdf · uploaded 30 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 30 Jun 2025Source
- Form 1Form 1.pdf · uploaded 30 Jun 2025Source
- Form 2Form 2.pdf · uploaded 30 Jun 2025Source
- Form 3Form 3.pdf · uploaded 30 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 30 Jun 2025Source
- Form 1Form 1.pdf · uploaded 30 Jun 2025Source
- Form 2Form 2.pdf · uploaded 30 Jun 2025Source
- Form 3Form 3.pdf · uploaded 30 Jun 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 30 Jun 2025Source
- Occupational CertificateOccupancy Certificate.pdf · uploaded 26 Aug 2025Source
Technical
Technical (Architect)
- DocumentArchitect Letter-compressed.pdf · uploaded 14 Jan 2022Source
Technical (Engineer)
- DocumentENGINEER CERTIFICATE-compressed.pdf · uploaded 14 Jan 2022Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals71 6 4B 10A 2 2, 71 7A 1 4
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —48 units in all
- Address
- 71 6 4b 10a 2 2, 71 7a 1 4, 71 8 1 4 6, Sno 71 Part Pune Banglore Highway, Near Woods RoyalePIN 411038
- Village
- Kothrud, Haveli taluka
- Location
- 18.49881, 73.78793
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Adjoined Sno 71 Part
- South
- 9mtr Internal Road
- East
- 12 Mtr Internal Road
- West
- Adjoined Sno 71 Part
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking48 units
48 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 48 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Direction Next Design Studeo | — |
| Chartered accountant | Anil V Jagtap | — |
| Chartered accountant | P N Jagtap And Company | — |
| Engineer | Somnath Rode | — |
| Other | Hemant Patil | — |
Source: MahaRERA project page. Contact details are not shown.