Residential / Group Housing · 1 building · 19 unitsRERA P52100013394

Devyani

Its promised completion date, Oct 2018, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Kothrud, Pune 411038 · Property rates in Kothrud · Promoter: M/S Kharde Patil

Delivery8 yrs past duePromised Oct 2018 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 19 units · as the promoter reported to MahaRERA
Devyani project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Oct 2018, has passed and MahaRERA does not show it completed

  • This projectRegistered 4 Oct 2017, completion promised 15 Oct 2018, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100013394
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000133944 Oct 201715 Oct 201815 Oct 2018M/S Kharde PatilProject page
Documents30

1 document held by Deedo, 29 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan firm.pdf · uploaded 11 Aug 2017Source

Legal

  • Legal Title reportDevyani TSR.pdf · uploaded 11 Aug 2017Source
  • Declaration Form BAffidavit Devyani.pdf · uploaded 11 Aug 2017Source
  • OtherDevyani Completion.pdf · uploaded 14 Oct 2018Source

Migrated

  • 1 PAN Cardpan firm.pdf · uploaded 11 Aug 2017Source
  • 1 Copy of the legal title reportDevyani TSR.pdf · uploaded 11 Aug 2017Source
  • 1 Details of encumbrancesEncumbrance Letter Devyani.pdf · uploaded 11 Aug 2017Source
Show all 30 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Devyani Layout.pdf · uploaded 11 Aug 2017Source
  • 1 Building Plan Approval (IOD)Devyani Plan.pdf · uploaded 11 Aug 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentDEVYANI C C.pdf · uploaded 11 Aug 2017Source
  • 1 Declaration in FORM BAffidavit Devyani.pdf · uploaded 11 Aug 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Devyani Architect .pdf · uploaded 11 Aug 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate Devyani.pdf · uploaded 11 Aug 2017Source
  • 1 Certificates of CA (Form 3)CA CERTIFICATE DEVYANI.pdf · uploaded 11 Aug 2017Source
  • 1 Proforma of Allotment letterDEVYANI ALLOTMENT LETTER Agreement.pdf · uploaded 11 Aug 2017Source
  • 2 Building Plan Approval (IOD)Devyani Plan 1.pdf · uploaded 26 Apr 2018Source
  • 2 Commencement Certificates / NA Order for plotted developmentDevyani CC.pdf · uploaded 26 Apr 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Devyani Architect.pdf · uploaded 26 Apr 2018Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Devyani Architect.pdf · uploaded 26 Apr 2018Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Devyani Eng .pdf · uploaded 26 Apr 2018Source
  • 2 Certificates of CA (Form 3)Devyani C A.pdf · uploaded 26 Apr 2018Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)devyani .pdf · uploaded 14 Oct 2018Source
  • 1 Certificates of Architect (Form 4)Devyani Architect .pdf · uploaded 14 Oct 2018Source
  • 1 OtherDevyani Completion.pdf · uploaded 14 Oct 2018Source

Technical

  • DocumentDevyani Layout.pdf · uploaded 11 Aug 2017Source
  • DocumentDevyani Plan.pdf · uploaded 11 Aug 2017Source
  • DocumentDevyani Plan 1.pdf · uploaded 26 Apr 2018Source

Technical (Architect)

  • DocumentDevyani Architect.pdf · uploaded 26 Apr 2018Source

Technical (Engineer)

  • Documentdevyani .pdf · uploaded 14 Oct 2018Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals71 HISSA 8/1/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2 BHK19 units in all
Address
71 Hissa 8 1 1PIN 411038
Village
Kothrud, Haveli taluka
Designated bank account
89
Developed in phases
No

Survey, CTS, gat or plot numbers

71 HISSA 8/1/1

Boundaries

North
Adjoined Sno 71 Part
South
9 Mtr Wide Internal Road
East
9 Mtr Wide Internal Road
West
9 Mtr Wide Internal Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking19 units

0 of 19 units booked (0%), as the promoter reported to MahaRERA

2 BHK · 19 units
TypeCarpet areaUnitsBooked
2 BHK52.23 sq m · 562 sq ft60
2 BHK52.23 sq m · 562 sq ft100
2 BHK53.11 sq m · 572 sq ft30

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDirection Next Design Studeo—
EngineerG Abhilare Consultants Pvt Ltd—
OtherMrs Vimal Pradeep Tilekar—
OtherP N Jagtap & Company—
Registered real estate agentPadmanabh Wasudeo Warade—
Registered real estate agentSheetal Padmanabh Warade—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology